RHA Tungsten Project Update

25 Nov 2014 07:00

RNS Number : 8462X
Premier African Minerals Limited
25 November 2014
Β 

ο»Ώ

Premier African Minerals Limited / Ticker: PREM / Index: AIM / Sector: Mining

Β 

For immediate release

Β 

25 November 2014

Β 

Premier African Minerals Limited ("Premier" or "the Company")

RHA Tungsten Project Update

Premier African Minerals Limited, the AIM-traded, multi-commodity natural resource company with mineral projects located in Southern and Western Africa, today provides an update on the RHA Tungsten Project ("RHA"), in Zimbabwe in respect of which Premier is the operator and holds a 49% interest.

Β 

Highlights

Β· Dewatering of Old Mine workings completed

Β· Access to historic underground workings re-established

Β· Open pit mine design and scheduling completed

Β· Suitable water sources confirmed and secured

Β· Agreement obtained to re-use old tailings facility for start-up strategy

Β 

George Roach, CEO of Premier, commented: "Premier is making significant progress in bringing the RHA mine back into production. Each step further de-risks this project and assists in reaching final financing decisions. Premier remains in intensive negotiations that are expected in the near term to enable final decisions on off-take and/or marketing contracts and the preferred structure to fund the estimated US$4.1 million required prior to commencement of production."

Β 

Dewatering and Access to the Underground Mine

The underground mine below the 926 level that had been submerged for decades, has now been completely dewatered down to the 859 level, the lowest historical level developed. A vertical sub-shaft was re-equipped with ladder ways in parallel to the dewatering program. All development ends have been accessed as well as various raises and sub-levels. Significantly, this has allowed confirmation that the historic non-compliant developed reserve as reported in our press release of 19 June 2014 is intact and available for exploitation. Confirmatory channel sampling has commenced and subject to assay results confirming the historic data, Premier looks forward to adding to our known compliant resources.

Β 

Open pit mine design

The open pit optimization, mine design and scheduling has been completed by CAE Mining and confirmed the parameters included in the PEA announcement dated 28 October 2014. These detailed results will be incorporated into the implementation planning currently underway and allows Premier to initiate the adjudication process for the open pit mining contract.

Β 

Infrastructure

The camp upgrade has been completed and allows for all requirements during the construction and operational phase.

Β 

A hydrological study on the RHA surface dam catchment area has been completed in parallel to pump testing of the boreholes on site as well as the Lukhosi well, 16km to the North West of the mine. Preliminary results allowed for developing of the site water balance and confirmed the potential to supply the required water volumes. Premier has obtained approval from the Zimbabwean Railway Authority to lease the Lukhosi well.

Β 

Tailings storage facility

Premier has obtained provisional approval to re-commission the historic tailings facility as part of the low capital start-up strategy. This will allow production to commence without the need for a capital intensive new tailings storage facility. Design and implementation of the new facility will commence as soon as RHA has successfully initiated first production.

Β 

Finance

Premier remains well funded with in excess of US$1m in cash on hand and a final tranche of US$1m from the Circum Minerals transaction expected on 15 January 2015. Completed works described in this press release have been financed and paid for by Premier. Longest lead item to production is building the process plant. This is anticipated to require 20 weeks from the date on which payment is made and the order confirmed. First production is described in Premier's open pit model that is described in our press release of 28 October 2014.

Β 

The US$4.1m referred to in the quote above, represents the peak net operating cash shortfall that Premier as a group anticipates based on the assumption that RHA is in production by end April 2015.

Β 

Premier will update shareholders when the finance structure has been agreed and the order for the plant has been placed.

Β 

Qualified Person

Werner Swanepoel, Chief Operating Officer of Premier, has reviewed and approved this release to the extent that information contained herein relates to mining and mine development. Mr Swanepoel has 20 years' experience in the southern African mining industry and holds a Master's degree in Mining Engineering, an MBA and Mine Manager's Certificates in both Metalliferous and Coal Mining. He is a registered Professional Engineer with the Engineering Council of South Africa.

Forward Looking Statements

Certain statements in this announcement, are, or may be deemed to be, forward looking statements. Forward looking statements are identified by their use of terms and phrases such as ''believe'', ''could'', "should" ''envisage'', ''estimate'', ''intend'', ''may'', ''plan'', ''will'' or the negative of those, variations or comparable expressions, including references to assumptions. These forward looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth, results of operations, performance, future capital and other expenditures (including the amount, nature and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. A number of factors could cause actual results to differ materially from the results discussed in the forward looking statements including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes, actions by governmental authorities, the availability of capital markets, reliance on key personnel, uninsured and underinsured losses and other factors, many of which are beyond the control of the Company. Although any forward looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions, the Company cannot assure investors that actual results will be consistent with such forward looking statements.

Β 

For further information please visit www.premierafricanminerals.com or contact the following:

Pamela Hueston

Premier African Minerals Limited

Tel: +44 (0) 755 778 3855

Michael Cornish / Roland Cornish

Beaumont Cornish Limited

(Nominated Adviser)

Tel: +44 (0) 207 628 3396

Jerry Keen/ Edward Mansfield

Shore Capital Stockbrokers Limited

Tel: +44 (0) 207 408 4090

Tim Blythe/ Halimah Hussain

BlytheWeigh

Tel: +44 (0) 207 138 3204

Β 

Β 

Notes

Premier African Minerals Limited (AIM: PREM) is a multi-commodity exploration and development company focused in Southern and Western Africa. The Company has a diverse portfolio of multi-commodity projects which includes tungsten, rare earth elements, gold, lithium, tantalum, graphite and uranium in Zimbabwe and Togo, which span from brownfield projects with near-term production potential to grass-roots exploration. The Company holds 2m shares in Circum Minerals Ltd ("Circum"), the owners of the Danakil Potash Project. At inception, the shares had a fair value of US$1.4m. Circum is fully funded to completion of feasibility study.

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
MSCBSBDBIUDBGSS
Date   Source Headline
21st Mar 20177:00 amRNSExceptional Lithium Grades at Zulu Lithium Project
17th Mar 20171:35 pmRNSResult of Annual General Meeting
17th Mar 201710:21 amRNSRHA Update - XRT installation Complete
14th Mar 20177:00 amRNSCircum Minerals Update
27th Feb 20174:28 pmRNSNotice of Annual General Meeting
27th Feb 20172:17 pmRNSXRT installation at RHA Tungsten Mine
20th Feb 20177:01 amRNSSignificant Lithium Grades up to 3.3% Lithium
20th Feb 20177:00 amRNSMining Contractor Secured for RHA Tungsten Mine
10th Feb 201711:09 amRNSCircum Minerals Update
7th Feb 20172:00 pmRNSPrice Monitoring Extension
7th Feb 20179:34 amRNSConversion of last loan notes and issue of equity
3rd Feb 20177:00 amRNSConversion of loan note and issue of equity
1st Feb 20173:43 pmRNSConversion of loan note and issue of equity
31st Jan 20173:52 pmRNSZulu Lithium and Tantalum Project Update
31st Jan 20173:50 pmRNSConversion of loan note and issue of equity
30th Jan 20171:27 pmRNSDirector's Subscription
30th Jan 201710:38 amRNSPlacing and Corporate Update
26th Jan 20177:00 amRNSZulu Lithium and Tantalum Project Update
19th Jan 20174:15 pmRNSGrant of Options
19th Jan 201710:15 amRNSBoard appointment and corporate update
3rd Jan 201711:01 amRNSZulu Lithium and Tantalum Project Update
3rd Jan 201711:00 amRNSConversion of loan note and issue of equity
21st Dec 20163:28 pmRNSIssue of Equity
19th Dec 20167:00 amRNSCorporate Update - Replacement
16th Dec 201611:53 amRNSCorporate Update
9th Dec 20167:00 amRNSCasa Mining Update
30th Nov 20167:00 amRNSSubstantial increases in resources at RHA
23rd Nov 20167:05 amRNSRHA Update
23rd Nov 20167:00 amRNSConversion of loan note and issue of equity
9th Nov 20167:00 amRNSZulu Lithium and Tantalum Project Update
31st Oct 20167:00 amRNSAcquisition of controlling interest in TCT IF
21st Oct 20169:00 amRNSUpdate - Current Diamond Drilling Programme
18th Oct 20163:22 pmRNSCircum Minerals Update
18th Oct 20167:00 amRNSPremier buys into significant gold asset
10th Oct 20167:00 amRNSZulu Lithium Project - Drilling Update
5th Oct 20167:00 amRNSRHA Tungsten Mining Operations - Update
27th Sep 20164:38 pmRNSHalf-year Report
23rd Sep 20167:00 amRNSRHA Update and Notice of Results
20th Sep 20167:00 amRNSZulu Lithium Project - Drilling Update
14th Sep 20167:00 amRNSDrilling Programme on Zulu Commenced
22nd Aug 20167:01 amRNSLoan Note Instrument
22nd Aug 20167:00 amRNSCorporate Update
27th Jul 20168:07 amRNSDirector Resignation and Appointment of Consultant
21st Jul 20167:00 amRNSZulu Lithium and Tantalum update
18th Jul 20163:23 pmRNSProduction recommences at RHA
12th Jul 20167:00 amRNSRHA plant modifications and upgrades completed
6th Jul 20167:00 amRNSRHA Update
4th Jul 201611:06 amRNSCorporate Update
1st Jul 20167:00 amRNSZulu Lithium and Tantalum update
29th Jun 20167:00 amRNSRHA Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.