The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksPan African Regulatory News (PAF)

Share Price Information for Pan African (PAF)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 24.00
Bid: 23.80
Ask: 24.05
Change: -0.30 (-1.23%)
Spread: 0.25 (1.05%)
Open: 23.60
High: 24.00
Low: 23.40
Prev. Close: 24.30
PAF Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

2015 Abridged Mineral Resource & Mineral Reserve Report

15 Sep 2015 16:00

PAN AFRICAN RESOURCES PLC - 2015 Abridged Mineral Resource & Mineral Reserve Report

PAN AFRICAN RESOURCES PLC - 2015 Abridged Mineral Resource & Mineral Reserve Report

PR Newswire

London, September 15

Pan African Resources PLC

(Incorporated and registered in England and Wales under Companies Act 1985 with registered number 3937466 on 25 February 2000)

Share code on AIM: PAF

Share code on JSE: PAN

ISIN: GB0004300496

("Pan African Resources" or the "Company" or the "Group")

2015 Abridged Mineral Resource & Mineral Reserve Report

Pan African Resources PLC (AIM: PAF, JSE: PAN), the African focused precious metals producer, is pleased to announce that the 2015 Abridged Mineral Resource and Mineral Reserve Report ("MR&MR") has now been published and is available on the Company's website at www.panafricanresources.com. A summary of the report, including the Group Mineral Resource and Mineral Reserve statement as at 30 June 2015 has been provided below.

Overview

0.3 million ounces (“Moz”) or 3.0% gross annual increase in Group’s gold reserve to 10.4Moz (2014: 10.1Moz) Increase in the Group’s gold reserve due to the extension of the Main Reef Complex (“MRC”) orebody on Fairview Mine (0.3Moz), at Barberton Mines 1.6Moz or 4.8% decrease in Group’s gold resource to 31.9Moz (2014: 33.5Moz) 20,000oz or 3.9% decrease in Group’s Platinum Group Elements (“PGE”) reserve to 0.50Moz (2014: 0.52Moz) No material change in Group’s PGE resource, 0.6Moz (2014: 0.6Moz) Exploration drilling and organic growth in accessing and development of orebodies at the Group's key assets progressed and has incremental resource ounces added Ongoing conversion of resources to reserves expected to continue to increase life of mine production profiles Preliminary economic assessments for Evander South brownfields project (“Evander South Project”) and Elikhulu

Gold

Group Gold Mineral Resources

The Group's attributable gold Mineral Resources decreased from 33.5 Moz in June 2014 to 31.9Moz in June 2015, equating to an annual decrease of 1.6Moz, or 4.8%. Of this variance, a decrease of 1.9Moz can be attributed to Evander Mines and an increase of 0.3Moz to Barberton Mines.

As at 30 June 2015
TonnesGradeContained Gold
Category(million)(g/t)kgMoz
Mineral ResourceMeasured6.510.3567,4712.2
Indicated273.72.33637,45720.5
Inferred38.67.43286,9909.2
Pan African ResourcesTotal318.83.11991,91831.9

The decrease in Mineral Resources can be attributed to inflationary cost drivers in the reporting of the 2015 Mineral Resources. The 0.3Moz positive variance in contained gold at Barberton Mines was a result of adding new mineral resources from the extension of the MRC orebody on Fairview Mine.

Group Gold Mineral Reserves

The Group's attributable Mineral Reserves increased from 10.1Moz in June 2014 to 10.4Moz in June 2015 - an annual increase of 0.3Moz, or 3.0%. Of this variance, 0.3Moz increase can be attributed to Barberton Mines.

As at 30 June 2015
TonnesGradeContained Gold
Category(million)(g/t)kgMoz
Mineral ReserveProved3.97.2728,4741.0
Probable81.03.62293,4789.4
Pan African ResourcesTotal84.93.79321,95210.4

The total increase in the Mineral Reserves can be attributed to the conversion of Mineral Resources at Barberton Mines, the extension of MRC orebody at Fairview Mine.

Platinum Group Elements

Group PGE Mineral Resources

The Group's attributable PGE Mineral Resources did not change materially in the year under review.

As at 30 June 2015
TonnesGradeContained PGE’s
Category(million)(g/t)kgMoz
Mineral ResourceMeasured1.62.463,9370.1
Indicated3.23.6611,5740.4
Inferred1.22.903,4460.1
Pan African ResourcesTotal6.03.1418,9570.6

Group PGE Mineral Reserves

The Group's attributable PGE Mineral Reserves decreased from 0.52Moz in June 2014 to 0.50Moz in June 2015 - an annual decrease of 20,000oz or 3.9%. This was due to the re-mining of the Buffelsfontein tailings dams in the current year.

As at 30 June 2015TonnesGradeContained PGE’s
Category(million)(g/t)kgMoz
Mineral ReserveProved1.62.463,9370.1
Probable3.23.5611,5740.4
Pan African ResourcesTotal4.83.2015,5110.5

Group organic growth

Group: Exploring the orebody - exploration drilling

OperationTotal metresNo. of boreholesAverage channel width (cm)No. of intersections above cut-offAverage grade (g/t)Total expenditure (Rm)
Barberton Mines11,4911571307219.798.5
Evander Mines63212132816.300.6
Phoenix Platinum

Highlights:

Exploration drilling projects at Barberton Mines yielded positive results, confirming the down dip extension of the high grade 11 Block of the MRC ore body by a further 170 meters. This extension to the MRC orebody resulted in an annual increase in Barberton Mines’ Mineral Reserves by 236,162 oz, thereby extending the life of mine of Barberton Mines to 20 years.

The Fairview MRC orebody has been the primary gold contributor towards gold produced at Barberton Mines. This orebody is an epigenetic hydrothermal lode-gold deposit with a strike length that ranges between 70m – 120m and also extending to depth. Gold mineralisation is associated with arsenopyrite and pyrite with an average reserve grade of 35 g/t declared for the MRC. The mineralised widths range between 7m – 15m.

Recent borehole results of the 11 Block are detailed hereunder:

Borehole numberChannel width (cm)Grade (g/t)
Bh 594068753.30
Bh 5816691120.03
Bh 5849162650.22
Bh 5864138343.82

Accessing the orebody - on-reef development

OperationTotal on-reef development (m)Average grade (g/t)
Barberton Mines1,0415.01
Evander Mines52822.72
Phoenix Platinum

Barberton Mines: Developing the orebody - capital ore reserve projects

ProjectY/E 30 June 2015 (m)Y/E 30 June 2014 (m)Y/E 30 June 2013 (m)Potential resource target (oz)
Sheba – pillar development82435131723,599
Sheba – Edwin Bray to Thomas and Joe’s Luck area5 (equipping incline shaft)17110213,246
Fairview – 11 Level Royal Reef0 (equipping old main shaft)0 (equipping old main shaft)017,000
Fairview – 1# ore reserve opening8415417914,821
Fairview – 3 Shaft deepening2602281,600
Fairview – 64-68 Level447295601840,704
Sheba Western C29571032,022
Royal Sheba16500206,750
Consort – 33-45PC25819325210,000
Consort – MMR pillar development0173129(new target area)
8-3 #327253900

Evander Mines: Developing the orebody - capital ore reserve projects

ProjectY/E 30 June 2015 (m)Y/E 30 June 2014 (m)Y/E 30 June 2013 (m)Potential resource target (oz)
2 Decline 24–25 Level9046855541,200,000
25 A block ventilation10925124

Growth projects:

An internal technical team from Evander Mines has been assigned to assess the merits of progressing the Evander South Project to the level of a feasibility study. The Evander South Project is a potentially attractive mining opportunity whereby the Kimberley reef can be exploited at shallow depths, commencing at 300m below surface.

In light of the positive results of the Evander Tailings Retreatment Plant, the Company is progressing studies on the viability of constructing “Elikhulu”, a tailings retreatment plant which can potentially treat slimes at a processing capacity of up to 12 million tonnes per annum at a head grade of 0.28g/t from the Winkelhaak, Leslie and Kinross tailings storage facilities. The total mineral resource for Elikhulu is 165Mt at 0.28g/t (1.5Moz).

The Sheba and New Consort tailings dams will provide potential future sources of tailings which will support the increased Barberton Tailings Retreatment Plant (“BTRP”) life of operation to 15 years (2014: 12 years). The BTRP has a mineral reserve of 0.6Moz (13.4Mt at 1.5 g/t). The BTRP payback period was 18 months from commissioning on 1 July 2013, therefore the increase in the BTRP life of operation is expected to result in further surplus free cash flows.

Reporting in compliance with SAMREC Code

To meet the requirement of the South African Code for the Reporting of Exploration Results, Mineral Resources and Mineral Reserves ("SAMREC Code") that the material reported as a Mineral Resource should have "reasonable and realistic prospects for eventual economic extraction", Pan African Resources has determined an appropriate cut-off grade which has been applied to the quantified mineralised body. In determining the cut-off grade, Pan African Resources uses a gold price of R500 000/kg. At our underground mines, the optimal cut-off is defined as the lowest grade at which an orebody can be mined such that the total profits, under a specified set of mining parameters, are maximised. The Mineral Resource optimiser tool that was accordingly developed in-house was applied to the Mineral Resource inventory.

The optimiser programme requires the following inputs to convert the Mineral Resource to the Mineral Reserve:

the database inventory of all mineral resource blocks; an assumed gold price - ZAR400 000/kg; planned production rates for each mine; mine call factor; plant recovery factors; and planned cash operating costs and other efficiency factors, which are calculated using historical achievements as a baseline.

The Mineral Reserves represent that portion of the Measured and Indicated Mineral Resources above cut-off in the life of mine plan, and have been estimated after consideration of the modifying factors affecting extraction. A range of disciplines has been involved at each mine in the life of mine planning process including geology, surveying, planning, mining engineering, rock engineering, metallurgy, financial management, human resources management and environmental management.

Note: Mineral Resources are inclusive of the Mineral Reserve, unless otherwise stated. Rounding of numbers contained in this announcement may result in minor computational discrepancies.

Competent Person

The competent person for Pan African Resources, Mr Barry Naicker, the group Mineral Resource Manager, signs off the MR&MR for the Group and has reviewed and approved the information contained in this announcement in writing. He is a member of the South African Council for Scientific Professions (400234/10). Mr Naicker has 14 years of experience in economic geology and mineral resource management.

He is based at 1st Floor, The Firs, cnr. Cradock and Biermann Avenues, Rosebank, 2196, Gauteng.

Contact Details

Corporate OfficeThe Firs Office Building1st Floor, Office 101Cnr. Cradock and Biermann AvenuesRosebank, JohannesburgSouth AfricaOffice: + 27 (0) 11 243 2900Facsmile: + 27 (0) 11 880 1240

Registered OfficeSuite 31Second Floor107 CheapsideLondonEC2V 6DNUnited KingdomOffice: + 44 (0) 207 796 8644Facsmile: + 44 (0) 207 796 8645

Cobus LootsDeon Louw
Pan African Resources PLCPan African Resources PLC
Chief Executive OfficerFinancial Director
Office: + 27 (0)11 243 2900Office: + 27 (0) 11 243 2900

Phil DexterJohn Prior / Paul Gillam / James Black
St James's Corporate Services LimitedNumis Securities Limited
Company SecretaryNominated Adviser & Joint Broker
Office: + 44 (0)207 796 8644Office: +44 (0)207 260 1000

Sholto SimpsonMatthew Armitt / Ross Allister
One CapitalPeel Hunt LLP
JSE SponsorJoint Broker
Office: + 27 (0)11 550 5009Office: +44 (0)020 7418 8900

Julian GwillimDaniel Thöle
Aprio Strategic CommunicationsBell Pottinger PR
Public & Investor Relations SAPublic & Investor Relations UK
Office: +27 (0)11 880 0037Office: + 44 (0)203 772 2500

www.panafricanresources.com

Date   Source Headline
14th Feb 20247:00 amPRNUnaudited Interim financial results for the six months ended 31 december 2023
2nd Feb 20247:00 amPRNTrading Statement
29th Jan 20243:45 pmPRNHolding(s) in Company
22nd Jan 20247:00 amPRNOperational Update for the Half Year ended 31 December 2023 (H1 FY2024)
7th Dec 202310:00 amPRNHolding(s) in Company
24th Nov 20237:00 amPRNResult of AGM & Salient Dividend Dates
22nd Nov 20237:00 amPRNInterim Production Update for half year ending 31 December 2023
10th Nov 202312:15 pmPRNDirector/PDMR Shareholding
10th Nov 202312:15 pmPRNDirector/PDMR Shareholding
8th Nov 20232:45 pmPRNDirector/PDMR Shareholding
7th Nov 20231:30 pmPRNDirector/PDMR Shareholding
31st Oct 20237:00 amPRNNotice of AGM & Abridged Annual Financial Statements for the year ended 30 June 2023
30th Oct 20232:00 pmPRNDirector/PDMR Shareholding
30th Oct 20232:00 pmPRNDirector/PDMR Shareholding
13th Sep 20237:00 amPRNProvisional summarised audited results for the year ended 30 June 2023
5th Sep 202311:45 amPRNHolding(s) in Company
1st Sep 20237:00 amPRNTrading Statement for the year ended 30 June 2023
7th Aug 20237:00 amPRNOperational Update for the year ended 30 June 2023
1st Aug 20239:10 amPRNUpdate to Commissioning Date of the Mintails Project
1st Aug 20237:24 amPRNMintails Project Funding Closed and Granting of Integrated Environmental Authorisation
1st Jun 20227:00 amPRNAppointment of Berenberg as Joint Broker
12th Apr 20227:00 amPRNTransaction in Own Shares
11th Apr 20227:00 amPRNHolding(s) in Company
7th Apr 20227:00 amPRNTransaction in Own Shares
4th Apr 20227:07 amPRNTransaction in Own Shares
1st Apr 20227:00 amPRNShare Buyback Programme
14th Mar 20227:00 amPRNGold Exploration Programme in Sudan
7th Mar 20229:30 amPRNHolding(s) in Company
7th Mar 20227:00 amPRNHolding(s) in Company
2nd Mar 20227:00 amPRNHolding(s) in Company
16th Feb 20227:00 amPRNUnaudited Interim Results for 6m to 31 Dec 2021
19th Jan 20227:00 amPRNOperational Update - 31 Dec 2021
17th Jan 202212:45 pmPRNHolding(s) in Company
31st Dec 202112:41 pmRNSSecond Price Monitoring Extn
31st Dec 202112:35 pmRNSPrice Monitoring Extension
15th Dec 20217:00 amPRNAcquisition: Blyvoor Gold Surface Tailings
6th Dec 20219:00 amPRNSecondary Listing on A2X Markets
3rd Dec 20217:00 amPRNRetraction of TR-1 Form
1st Dec 20217:00 amPRNHolding(s) in Company
30th Nov 20217:00 amPRNNew Revolving Credit Facility Becomes Effective
26th Nov 20217:00 amPRNResult of AGM and Salient Dividend Dates
29th Oct 20217:01 amEQSPan African Resources (PAF): Everything falling into place
27th Oct 20218:30 amPRNNotice of AGM & No Change Statement
1st Oct 20211:30 pmPRNDirector/PDMR Shareholding
22nd Sep 20211:00 pmPRNDirector/PDMR Shareholding
21st Sep 20217:00 amPRNDirectorate Change
20th Sep 20212:30 pmPRNCOO Seriously Injured
16th Sep 20211:00 pmPRNDirector/PDMR Shareholding
15th Sep 202112:00 pmPRNDirector/PDMR Shareholding
15th Sep 20217:00 amRNSProvisional summarised audited year end results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.