Barruecopardo Tungsten Project

5 Sep 2017 07:00

RNS Number : 7863P
Ormonde Mining PLC
05 September 2017
 

05 September 2017

 

 

Ormonde Mining plc

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project

Construction Update

 

 

The Board of Ormonde is pleased to provide an update on construction activities at the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or the "Project").

 

Following the Company announcing, on 2nd June 2017, that the Project had moved into an accelerated construction and implementation phase, the ramp-up of site activities has advanced rapidly and is on track with the Project schedule, which anticipates mine commissioning in the third quarter of 2018. Progress at the Project has been made against a backdrop of strengthening tungsten demand and rising ammonium paratungstate ("APT") prices.

 

Key developments include:

 

· Priority 1 and Priority 2 equipment at manufacture stage; Priority 3 equipment order placement underway

 

· Construction of workshop, offices and other infrastructure continues

 

· Multiple construction contracts awarded, including dams and civil works, with main dam construction work underway

 

· Some 50 persons now working on the Project, including a majority from Barruecopardo and immediately adjacent towns

 

· APT prices continue to perform strongly, with significant price rises seen over recent months to a current level of US$285-300/mtu. This represents an increase of 30% on the prevailing price when the decision was taken to move to accelerated construction, and an 80% increase from its January 2016 low

 

 

Steve Nicol, Ormonde's Managing Director, commented:

 

"With the very positive decision, taken in early June this year, to advance the Project into an accelerated construction and implementation phase, the intervening period has been exceptionally busy at the Project. The speed and scale of the works progressed over this period has only been possible as a result of the meticulous preparation activities performed by the Project team over the past months.

 

With the APT price continuing to climb steadily, indications are that the decision to accelerate construction at the Project has been a timely and appropriate one, with the stage now set for the Project to commence commissioning in Q3 2018 against a backdrop of a much improved tungsten price environment."

 

 

About Ormonde

Ormonde has a 30% interest in the Barruecopardo Tungsten Project, located in northwest Spain. Barruecopardo is a fully permitted and fully funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest) in 2015.

 

A picture gallery illustrating recent site activities can be viewed at http://ormondemining.com/timeline-in-pictures/ 

 

 

 

 

 

Detail

 

Construction Activities

With the extensions to the Project timeline announced during 2016, the manufacturing of the ordered Priority 1 and Priority 2 equipment was necessarily deferred. This deferral has now been lifted and all ordered equipment is now being manufactured. In addition, new orders have been placed for the remainder of the outstanding Priority 2 equipment (including spirals, tables, main plant feed screen, and thickeners, etc), with Priority 3 (low criticality and/or short lead time) equipment orders also now being prepared for placement.

 

The dams' construction contract was recently awarded to Cerezo, a Spanish company with wide experience in the construction of dams and other mining infrastructure, including the execution of entire open pit mining operations for several international mining companies. Cerezo immediately mobilised to site with construction works having commenced in early July.

 

Meanwhile the civils works contract for the construction of all the foundations required for the Process Plant and associated infrastructure has been awarded to Copisa, a Spanish company active in Europe, Africa, Central America and South America. Copisa has particular experience in the execution of large projects in a wide range of sectors including infrastructure and industrial works. Copisa will be mobilising to site in early October.

 

In the meantime, construction of site facilities (workshops, welfare, etc) continues with contractors sourced from the local areas around the mine.

 

 

Tungsten Market

APT prices touched a low of US$162 per metric tonne unit ("mtu") in January 2016, following a period which had seen significant commodity price reductions associated with a general weakening of the commodity markets. However, since that time, the tungsten market has been gradually moving in an upwards direction, assisted by improvements in economic outlooks in both Europe and the US, and demand increase in some important markets. On the supply side, an estimated 4.2% reduction in primary supply from China during 2016 (China produces circa 80% of world primary tungsten supply), together with more recent supply disruptions to Chinese mine production, as a result of environmental impositions at certain Chinese mines, have had a material impact on the APT price.

 

Currently APT prices are US$285-300/mtu, following an increase in the rate of price appreciation since early July, shortly after the Barruecopardo Project partners decided to move the Project into an accelerated construction and implementation phase. While some consolidation in the near term may be expected, the outlook remains positive over the medium and longer term.

 

 

Enquiries to:

 

Ormonde Mining plc

Steve Nicol, Managing Director Tel: +353 (0)1 8014184

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)7703 167065

 

Murray Consultants

Mark Brennock  Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 679 6363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 3 470 0470

 

For more information please visit www.ormondemining.com

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUGUCPBUPMGQC
Date   Source Headline
28th Jun 20137:00 amRNSSalamanca Drilling Update
24th Jun 201310:27 amRNSHolding(s) in Company
6th Jun 201311:50 amRNSResult of AGM
6th Jun 20137:00 amRNSAGM Presentation
4th Jun 201311:50 amRNSNotification of Interest
21st May 20137:00 amRNSAppointment of Second Broker
16th May 20135:50 pmRNSNotification of Interest
16th May 20137:00 amRNSLa Zarza Update
15th May 201312:41 pmRNSNotification of Interest
1st May 20133:15 pmRNSAnnual Financial Report
17th Apr 20137:00 amRNSFinal Results
10th Apr 20137:00 amRNSBarruecopardo Permitting Update
11th Mar 20137:00 amRNSPeralonso Drilling Results
4th Feb 20137:00 amRNSSalamanca Prospect Update
23rd Jan 20137:00 amRNSDrilling Results at Peralonso
17th Dec 20127:00 amRNSCabeza Prospect Update
14th Dec 201212:25 pmRNSNotification of Interest
7th Dec 20127:00 amRNSEnterprise Securities Market Notice
4th Dec 20127:00 amRNSPlacing
22nd Nov 20127:00 amRNSBarruecopardo Progress Update
9th Nov 201211:00 amRNSAntofagasta opt out of La Zarza
23rd Oct 20127:00 amRNSCabeza Trenching Results
16th Oct 20127:00 amRNSFurther Drilling Results at Barruecopardo
15th Oct 20127:00 amRNSUpdate on Zamora Gold Project
27th Sep 20127:00 amRNSInterim Results
17th Sep 201212:08 pmRNSNotification of Interest
27th Jul 201212:42 pmRNSResult of AGM
26th Jul 20127:00 amRNSBarruecopardo Permitting
4th Jul 20127:00 amRNSJV Gold Project Update
26th Jun 20122:00 pmRNSAnnual Financial Report
18th Jun 20127:00 amRNSFurther Encouraging Progress in Gold Joint Venture
6th Jun 20127:00 amRNSFinal Results
28th Mar 20127:00 amRNSFurther Positive Results from Gold Joint Venture
14th Mar 20127:00 amRNSEnterpise Securities Market Notice
12th Mar 20127:00 amRNSPlacing
28th Feb 20127:00 amRNSDFS Results
13th Feb 20127:00 amRNSUpdate on Spanish Operations
8th Dec 20113:36 pmRNSNotification of share dealing by director
8th Dec 20117:00 amRNSLa Zarza Update
6th Dec 20117:00 amRNSExpanded Drilling Campaign Commencing on Gold JV
14th Nov 20114:18 pmRNSHolding(s) in Company
10th Nov 20117:00 amRNSFinal Barruecopardo Drilling Results
25th Oct 20117:00 amRNSInterim Report on Feasibility Study
19th Oct 20117:00 amRNSJV Gold Project Update
29th Sep 20117:00 amRNSInterim Results
15th Aug 20117:00 amRNSAntofagasta-Ormonde La Zarza Joint Venture Update
10th Aug 20117:00 amRNSBarruecopardo Drilling Update
21st Jul 20117:00 amRNSLa Zarza Copper Project Progress Update
15th Jul 20112:00 pmRNSResult of AGM
30th Jun 20117:00 amRNSAppointment of CFO

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.