Project Update

17 Jan 2022 07:00

RNS Number : 5573Y
Ncondezi Energy Limited
17 January 2022
 

 

News Release

 

 

Project Update

 

17 January 2022: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM:NCCL) is pleased to provide an update on the integrated Ncondezi 300MW power project in Tete, Mozambique (the "Project").

 

Highlights

· Awaiting further clarity on China's position on financing coal projects abroad ahead of progressing the Project tariff

· China Machinery Engineering Corporation ("CMEC") remains committed to the Project and continues to lead the process on Project financing

· Feedback on Transmission Integration Study expected during Q1 2022

· Company funded to the end of H1 2022

 

Ncondezi Chief Executive Officer, Hanno Pengilly said: "The Company continues to work closely with its strategic partner, CMEC, to gain further clarity on President Xi's announcement regarding availability of Chinese financing for coal power projects abroad. This is critical for the Project and all workstreams to progress the tariff are ready to proceed once this has been addressed. We understand this to be a global issue affecting all Chinese backed coal power development projects abroad, and that this impact is under review by the relevant Chinese authorities. CMEC continues to support the Project and is leading the financing process. In parallel to the Chinese financing process, Ncondezi and CMEC are reviewing potential alternative solutions for the Project which should be finalised during the quarter.

 

The case for the Project remains strong, there is a clear need for new baseload power in Mozambique to meet the Mozambique Government's own targets however we also recognise that the environment for new coal power is challenging and the uncertainty on timing is causing a drag on the share price. We were pleased to see that the US$2bn Temane Gas Power (450MW) and related transmission infrastructure projects reached financial close last month and that work has begun on the Mozambique - Malawi interconnector project. Both demonstrate the Government is delivering on their "Energy For All" strategy and improving credibility as an investment destination for large infrastructure projects, particularly in the energy sector. As one of the most advanced baseload development power projects in the country we are in a prime position to assist the Government in continuing to meet their targets and energy transition to more cost effective and reliable forms of supply.

 

While we await for clarity on financing for the Project and feedback from EDM on the Transmission Integration Study, the Board has taken the decision to review and implement a cash conservation strategy to further extend the Company's working capital position beyond H1 2022 to ensure no further funding is required in the immediate future.

 

The Company will provide further updates at the appropriate time"

 

 

Enquiries

 

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy

Hanno Pengilly

+27 (0) 71 362 3566

 

Liberum Capital LimitedNOMAD & Joint Broker

 

Scott Mathieson, Edward Thomas, Kane Collings

+44 (0) 20 3100 2000

Novum Securities Limited

Joint Broker

Colin Rowbury

+44 (0) 20 7399 9427

 

Pimlico Advisory Ltd

Investor Relations

Elizabeth Johnson

+44 (0) 777 56 55 927

 

About Ncondezi Energy

 

Ncondezi is an African power development company with an advanced staged, integrated 300MW thermal coal power plant and mine project located in the Tete Province, Northern Mozambique.

 

The Company is focused on providing reliable, affordable and accessible baseload energy to Mozambique and secure against the effects of water drought and intermittency of new renewables. This project supports Mozambique's energy strategy of universal electricity access by 2030. According to the World Bank, only 30% of the Mozambican population had access to energy in 2017. The Ncondezi Project would provide 300MW of reliable and available power helping to close the infrastructure gap of the region and serving as a catalyst for economic development.

 

The power plant will be designed to be equipped with state-of-the-art emissions controls technologies that will reduce local air pollutants, minimizing the plant's impact on the environment and ensuring its compliance with the most stringent emission standards

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDSFAFWMEESELF
Date   Source Headline
10th Mar 20207:00 amRNSGeneral Update
20th Feb 20207:45 amRNSChange of Registered Office
28th Jan 20207:00 amRNSFinancial Model Submitted for Internal Review
17th Jan 20207:00 amRNSPower Tariff Process Update
31st Dec 20197:00 amRNSEPC and O&M Bids Received
24th Dec 20197:00 amRNSHolding(s) in Company
20th Dec 20197:00 amRNSMeeting of Priority China Investment Projects
18th Dec 20197:00 amRNSTariff Process Update
12th Dec 20197:00 amRNSAppointment of Tariff Advisors
11th Dec 20197:00 amRNSHolding(s) in Company
29th Nov 20191:17 pmRNSResult of AGM
26th Nov 20192:30 pmRNSShare Option Grants
26th Nov 20197:00 amRNSShareholder Loan Restructuring Update
25th Nov 201912:00 pmRNSDirectorate Change
15th Nov 20197:00 amRNSHolding(s) in Company
13th Nov 20197:00 amRNSHolding(s) in Company
7th Nov 20197:00 amRNSNotice of AGM
29th Oct 20197:21 amRNSHolding(s) in Company
23rd Oct 201910:00 amRNSSolar Battery Project and Working Capital Facility
21st Oct 20197:00 amRNSStrategic Partner Site Visits Complete
15th Oct 20197:00 amRNSInterim COO & IR appointments
11th Oct 20197:00 amRNSProject Update Investor Presentation
10th Oct 20197:00 amRNSHolding(s) in Company
9th Oct 20197:00 amRNSHanno Pengilly Appointed as CEO Directorate Change
26th Sep 20197:00 amRNSHalf-year Report
15th Aug 20197:00 amRNSHolding(s) in Company
8th Aug 20197:00 amRNSHolding(s) in Company
30th Jul 20194:09 pmRNSExercise of Warrants
29th Jul 201910:11 amRNSHolding(s) in Company
23rd Jul 20194:40 pmRNSSecond Price Monitoring Extn
23rd Jul 20194:35 pmRNSPrice Monitoring Extension
23rd Jul 20192:05 pmRNSSecond Price Monitoring Extn
23rd Jul 20192:00 pmRNSPrice Monitoring Extension
23rd Jul 201911:07 amRNSNcondezi signs JDA with CMEC and GE
12th Jul 20192:30 pmRNSShareholder Loan Conversion
28th Jun 20199:02 amRNSFinal Results
30th May 20197:00 amRNSShareholder Loan Conversion and Correction
17th May 20194:15 pmRNSShareholder Loan Conversion and Options Exercise
29th Apr 20197:45 amRNSJDA Entering Final Phase
18th Apr 20197:00 amRNSShareholder Loan Conversion
11th Apr 20197:00 amRNSShareholder Loan Conversion - correction
10th Apr 20193:30 pmRNSShareholder Loan Conversion
9th Apr 20197:00 amRNSGridX Investor Presentation
5th Apr 20197:00 amRNSJV in Solar/Battery Energy Sector and Fundraise
1st Apr 201912:00 pmRNSExercise of Warrants
19th Mar 20192:00 pmRNSExercise of Warrants
15th Mar 20194:33 pmRNSHolding(s) in Company
28th Feb 20197:21 amRNSJDA Update
15th Feb 201912:30 pmRNSContracts with Synergy Consulting
1st Feb 20197:00 amRNSProject Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.