SpaceX IPO launches today. Join the conversation.Click here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksNCCL.L Regulatory News (NCCL)

  • There is currently no data for NCCL

Project Update

25 Apr 2018 07:00

RNS Number : 9859L
Ncondezi Energy Limited
25 April 2018
 

 

News Release 

 

 

Project Update

 

25 April 2018: Following the announcement on 18 April 2018, Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) is pleased to provide an update on its process to conclude a binding Joint Development Agreement ("JDA") for the Company's integrated 300MW power and coal mine project in Tete Mozambique (the "Project").

 

Updated information for the engineering, procurement, and construction ("EPC") and operations and maintenance ("O&M") proposals were received on the 23 April 2018 deadline.

 

The new information is currently under internal review by Ncondezi to ensure it is complete and will allow the updating of the integrated financial model. The internal review is targeted for completion by the end of May 2018, and an update will be provided to shareholders at the appropriate time.

 

There is no certainty that the transactions contemplated by this announcement will occur.

 

Enquiries

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly

+27 (0) 71 362 3566

 

Liberum Capital Limited:NOMAD & Joint Broker

 

Neil Elliot / Richard Crawley

+44 (0) 20 3100 2000

Novum Securities Limited:

Joint Broker

Colin Rowbury

+44 (0) 20 7399 9427

 

Note:

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation ("MAR"). Upon the publication of this announcement via Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain. If you have any queries on this, then please contact Hanno Pengilly, Chief Development Officer of the Company (responsible for arranging release of this announcement) on +27 (0) 71 362 3566.

 

 

Ncondezi owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW. The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDBUGDSCBDBGIS
Date   Source Headline
19th Jan 20224:36 pmRNSPrice Monitoring Extension
18th Jan 20224:41 pmRNSSecond Price Monitoring Extn
18th Jan 20224:36 pmRNSPrice Monitoring Extension
17th Jan 20222:06 pmRNSSecond Price Monitoring Extn
17th Jan 20222:01 pmRNSPrice Monitoring Extension
17th Jan 20227:00 amRNSProject Update
29th Dec 20217:00 amRNSHolding(s) in Company
22nd Dec 202111:06 amRNSSecond Price Monitoring Extn
22nd Dec 202111:00 amRNSPrice Monitoring Extension
20th Dec 202111:45 amRNSHolding(s) in Company
13th Dec 20212:05 pmRNSSecond Price Monitoring Extn
13th Dec 20212:00 pmRNSPrice Monitoring Extension
10th Dec 202111:05 amRNSSecond Price Monitoring Extn
10th Dec 202111:00 amRNSPrice Monitoring Extension
10th Dec 20217:00 amRNSSubmission of Transmission Integration Study
7th Dec 20217:00 amRNSRepayment of Director’s Bridge Loan
3rd Dec 20217:00 amRNSUS$1.3 million Sale of C&I Subsidiary
17th Nov 202110:30 amRNSResult of AGM
28th Oct 20216:35 pmRNSHolding(s) in Company-Amendment
28th Oct 20212:30 pmRNSHolding(s) in Company
25th Oct 20217:00 amRNSNotice of AGM
15th Oct 20217:00 amRNSDirectors Bridge Loan Extension
13th Oct 20214:41 pmRNSSecond Price Monitoring Extn
13th Oct 20214:36 pmRNSPrice Monitoring Extension
13th Oct 20213:00 pmRNSMaiden C&I Project Fully Commissioned
29th Sep 20217:00 amRNSHalf-year Report
22nd Sep 20219:05 amRNSSecond Price Monitoring Extn
22nd Sep 20219:00 amRNSPrice Monitoring Extension
9th Sep 20217:00 amRNSPower Plant EPC Contract Signed
26th Aug 20214:40 pmRNSSecond Price Monitoring Extn
26th Aug 20214:35 pmRNSPrice Monitoring Extension
26th Aug 20212:05 pmRNSSecond Price Monitoring Extn
26th Aug 20212:00 pmRNSPrice Monitoring Extension
26th Aug 202112:45 pmRNSPlacing
23rd Aug 20217:00 amRNSEPC Contract Target Signature Date Agreed
12th Jul 20211:45 pmRNSTermination of EBTs
12th Jul 20217:00 amRNSCorporate Presentation
25th Jun 20217:00 amRNSAnnual Financial Report
14th Jun 20217:00 amRNSNESA Power Joint Venture Term Sheet Signed
9th Jun 20217:00 amRNSC&I Solar Battery Pipeline Update
4th Jun 20214:41 pmRNSSecond Price Monitoring Extn
4th Jun 20214:36 pmRNSPrice Monitoring Extension
1st Jun 20217:00 amRNSSolar Battery Project Update
19th May 20217:00 amRNSProject Update
4th May 20217:00 amRNSSolar Battery Project Fully Financed
8th Apr 20217:00 amRNSNon-Executive Director/ PDMR dealing
6th Apr 20217:00 amRNSC&I Project Update & Directors Bridge Loan
25th Mar 20217:05 amRNSCEO Share Subscription
25th Mar 20217:00 amRNSProject Update
9th Mar 20217:00 amRNSAppointment of Project Advisors

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.