Project Update

3 May 2018 07:00

RNS Number : 9517M
Ncondezi Energy Limited
03 May 2018
 

 

News Release 

 

 

Project Update

 

03 May 2018: Following the announcement on 25 April 2018, Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) is pleased to provide an update on its process to conclude a binding Joint Development Agreement ("JDA") for the Company's integrated 300MW power and coal mine project in Tete Mozambique (the "Project").

 

Key Highlights:

 

· Integrated financial model ("FM") updated with proposals for engineering, procurement, and construction ("EPC") and operations and maintenance ("O&M") contracts.

 

· The Project consists of two 150MW coal fired power plants, open pit coal mine and 2km conveyor connecting to the power plant together with common infrastructure such as water dams, dumps, electrical reticulation and villages and a 92km transmission line connecting into the Mozambican northern power grid.

 

· Positive initial results, which continue to indicate the viability of the Project and confirm economics.

 

· Initial review indicates that there is the potential to deliver a more competitive power tariff to Electricity de Mozambique ("EDM") and the Ministry of Mineral Resources and Energy ("MIREME") for approval.

 

· The FM is currently under review by potential partners.

 

· Target completion of FM review in May 2018.

 

· Submission of FM to EDM and MIREME targeted for June 2018 to seek in principle support for a new power tariff envelope, this is the main priority for the Company.

 

All other timetable deliverables remain as per previous announcements.

 

There is no certainty that the transactions contemplated by this announcement will occur.

 

Ncondezi's Non-Executive Chairman, Michael Haworth, commented: "Although still at an early stage, the preliminary results from the updated EPC and O&M information in the FM are positive and allude to the potential for delivery of a more competitive tariff to the Mozambican Government and EDM for approval. This also represents a significant milestone in the Project development process as the Company did not reach this stage of development with its previous potential partner. The next phase of the partner process is to finalise the FM by the end of May 2018, confirming a new tariff envelope which can be submitted to MIREME and EDM during June 2018. Should support be received for the new tariff envelope, the Company believes it will be well positioned to close out the JDA process and progress the Project to Financial Close." 

 

 

 

Enquiries

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly

+27 (0) 71 362 3566

 

Liberum Capital Limited:NOMAD & Joint Broker

 

Neil Elliot / Richard Crawley

+44 (0) 20 3100 2000

Novum Securities Limited:

Joint Broker

Colin Rowbury

+44 (0) 20 7399 9427

 

Note:

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation ("MAR"). Upon the publication of this announcement via Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain. If you have any queries on this, then please contact Hanno Pengilly, Chief Development Officer of the Company (responsible for arranging release of this announcement) on +27 (0) 71 362 3566.

 

 

Ncondezi owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW. The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDSSMFWEFASEDI
Date   Source Headline
30th Mar 20177:00 amRNSProject and Corporate Update
23rd Mar 20172:05 pmRNSSecond Price Monitoring Extn
23rd Mar 20172:00 pmRNSPrice Monitoring Extension
23rd Mar 201711:05 amRNSSecond Price Monitoring Extn
23rd Mar 201711:00 amRNSPrice Monitoring Extension
17th Feb 20172:41 pmRNSRecent share price movement
16th Dec 20167:00 amRNSProject Update
4th Oct 201611:57 amRNSResult of AGM
30th Sep 20163:04 pmRNSIssue of Equity
30th Sep 20167:00 amRNSHalf-year Report
2nd Sep 20162:18 pmRNSNotice of AGM
31st Aug 20167:00 amRNSUp to US$3.0 million Loan Facility Agreed with AFC
12th Jul 201610:00 amRNSShanghai Electric Power Video
7th Jul 20167:00 amRNSAnnouncement of Ncondezi Power Plant discussions
30th Jun 20167:00 amRNSFinal Results
15th Jun 20161:41 pmRNSUpdated Investor Presentation
23rd May 20163:42 pmRNSHolding(s) in Company
11th May 20164:24 pmRNSUS$1.32 million Shareholder Loan
6th May 20167:00 amRNSProject and Corporate Update
5th Feb 20162:11 pmRNSExtension of JDA with Shanghai Electric Power
11th Jan 20164:03 pmRNSJDA signed with Shanghai Electric Power
16th Dec 20154:40 pmRNSSecond Price Monitoring Extn
16th Dec 20154:35 pmRNSPrice Monitoring Extension
11th Dec 201512:03 pmRNSFinalising JDA with Shanghai Electric Power
10th Dec 20153:37 pmRNSHolding(s) in Company
22nd Oct 20159:45 amRNSEdM Commercial Deal Extension
29th Sep 20152:49 pmRNSHalf Yearly Report - Correction
29th Sep 20157:00 amRNSHalf Yearly Report
3rd Sep 201512:31 pmRNSResult of AGM
3rd Aug 20152:00 pmRNSNotice of AGM
29th Jul 20151:00 pmRNSFinal Results - Text Format
26th Jun 20157:00 amRNSFinal Results
21st May 20157:00 amRNSDirectorate Change
19th May 201510:22 amRNSHolding(s) in Company
31st Mar 20157:00 amRNSProject Update
24th Mar 201510:41 amRNSHolding(s) in Company
6th Feb 20158:00 amRNSShare Options
29th Jan 20159:02 amRNSHolding(s) in Company
20th Jan 20151:42 pmRNSHolding(s) in Company
16th Jan 20152:34 pmRNSHolding(s) in Company
12th Jan 20157:00 amRNSResult of Open Offer
2nd Jan 20153:13 pmRNSHolding(s) in Company
22nd Dec 20147:00 amRNSOpen Offer
19th Dec 20143:24 pmRNSHolding(s) in Company
19th Dec 20143:22 pmRNSHolding(s) in Company
19th Dec 20148:25 amRNSHolding(s) in Company
15th Dec 20141:10 pmRNSProposed Investment in Ncondezi by AFC
15th Dec 20141:01 pmRNSNcondezi Project Update
29th Oct 20148:28 amRNSHolding(s) in Company
27th Oct 20147:00 amRNSMoU with Shanghai Power

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.