Ncondezi Project Update

15 Dec 2014 13:01

RNS Number : 7787Z
Ncondezi Energy Limited
15 December 2014
 



News Release

 

 

Ncondezi Project Update

 

15 December 2014: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) is pleased to provide shareholders with an update in relation to its 300MW power plant project ("Ncondezi Project" or the "Project"), located near Tete in northern Mozambique.

 

In September 2014 the Company announced that it had reached a conditional commercial deal with Electricidade de Mozambique ("EDM") on the sale of electricity from the Ncondezi Project. The agreed commercial deal includes the range for the starting electricity tariff to be paid by EDM, which will then be subject to adjustments during the 25 year operational life of the Project. The starting tariff range is based on a number of assumptions including indexation, financing costs, coal costs, operator & maintenance costs and the technical parameters and capital costs contained in the binding Power Plant EPC bids. Based on a target project capital structure of 70% debt and 30% equity the Company believes that the conditional commercial deal supports the economics of the Ncondezi Power Plant and provides a regionally competitive US$ based project equity IRR. Based on the Board's current expectations of the key project assumptions detailed above, the projected average annualised EBITDA from the Ncondezi Power Project is expected to be c.US$130 million per annum (nominal terms) and estimated net equity cash flows are expected to be in excess of US$2 billion (nominal terms) over the 25 year life of the power plant.

 

Ncondezi has been working to satisfy the conditions precedent and agree with EDM an indicative timetable to Financial Close, now targeted for Q1 2016. Notwithstanding the progress that has been made, the conditions precedent for the commercial deal will not be met prior to the end of 2014 and the Company intends to seek an extension from EDM to the period for satisfaction of the conditions precedent.

 

In October 2014, the Company announced that it had entered into a non-binding MOU with Shanghai Electric Power Company Limited ("SEP"), which may lead to SEP becoming a controlling shareholder in the Ncondezi Power Project and a minority shareholding in the Ncondezi Mine Project. SEP is a leading subsidiary of China Power Investment Corporation ("CPI") which has total installed capacity of 90,000 MW and is one of the largest power companies in the Peoples' Republic of China. A deal with SEP has the potential to provide the Company, and all stakeholders in the Ncondezi Project, with the opportunity to partner with a major power generation company and potentially fast track the timetable to Financial Close. SEP has undertaken a detailed due diligence process in relation to the Company that started in December 2013 and the Company continues to make good progress with SEP in relation to finalising their outstanding due diligence items. A binding agreement with SEP is now targeted for Q1 2015.

 

In October 2014, the Company received a number of binding bids for the engineering, procurement and construction ("EPC") contract for the 92km transmission line and substations to connect the Ncondezi Project to the Mozambican Northern Grid. Ncondezi and its technical and commercial advisors are currently evaluating the bids. In addition, the Company recently completed and submitted its transmission Environmental and Social Impact Assessment ("ESIA") study to the Mozambican Ministry for Coordination of Environmental Action ("MICOA") for approval.

 

In November 2014, the Company received its land use agreement, or DUAT in Mozambique, from the Mozambican Government granting exclusive use for power plant operations. The DUAT covers an area of 9500 hectares.

 

 

 

 

Enquiries:

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly / Alex Buck

+44 (0) 20 7183 5402

Liberum Capital Limited:NOMAD & Broker

Richard Crawley / Christopher Britton

+44 (0) 20 3100 2000

finnCap:

Joint Broker

Matthew Robinson / Joanna Weaving

+44 (0) 20 7220 0500

Bell Pottinger:

Daniel Thöle / Marianna Bowes

+44 (0) 20 7861 3232

 

Ncondezi Energy owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW.The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCQKPDPBBDDCBD
Date   Source Headline
28th Feb 202312:30 pmRNSResult of EGM
13th Feb 20237:00 amRNSNotice of EGM – Change of Name – Solgenics Limited
9th Feb 20237:00 amRNSDirector/PDMR Shareholding
6th Feb 20237:00 amRNSConvertible Loan Fully Converted
18th Jan 20237:00 amRNSPDMR Dealing
17th Jan 20237:00 amRNSPDMR Dealing & Conversion Notice
16th Jan 20237:00 amRNSConvertible Loan Conversions
13th Jan 20237:00 amRNSTransmission Route Approved
10th Jan 20234:35 pmRNSPrice Monitoring Extension
9th Jan 20237:00 amRNSSolar Land Agreement
30th Dec 202211:05 amRNSResult of AGM
22nd Dec 20227:00 amRNSAppointment of Solar Project Advisors
20th Dec 20221:08 pmRNSHolding(s) in Company
2nd Dec 20227:00 amRNSNotice of AGM
23rd Nov 202211:18 amEQSNcondezi Energy provides fresh numbers for Mozambique solar project
21st Nov 20227:30 amRNSPlacing
21st Nov 20227:00 amRNSSolar Valuation Update
31st Oct 20227:00 amRNSPositive Solar Feasibility Draft Delivered
25th Oct 20222:42 pmEQSNcondezi Energy pivoting to solar in Mozambique
21st Oct 20227:00 amRNSStrategic review of Coal Asset
30th Sep 20227:00 amRNSHalf-year Report
29th Sep 20227:00 amRNSSolar Feasibility Study Update
28th Sep 20222:06 pmRNSSecond Price Monitoring Extn
28th Sep 20222:00 pmRNSPrice Monitoring Extension
16th Sep 20227:00 amRNSConvertible Loan Finalised
1st Aug 202212:15 pmRNSSolar FS Update and Loan Restructuring
15th Jul 20227:00 amRNSSolar Project FS Launched with target NPV $60m
11th Jul 20229:46 amRNSSeritza Loan Restructuring Agreed "In Principle"
30th Jun 20227:00 amRNSSeritza Loan Extension
27th Jun 20227:00 amRNSAnnual Financial Report
1st Jun 20227:00 amRNSSeritza Loan Extension
12th May 20222:05 pmRNSSecond Price Monitoring Extn
12th May 20222:00 pmRNSPrice Monitoring Extension
12th May 202211:06 amRNSSecond Price Monitoring Extn
12th May 202211:00 amRNSPrice Monitoring Extension
12th May 20229:05 amRNSSecond Price Monitoring Extn
12th May 20229:00 amRNSPrice Monitoring Extension
11th May 20227:00 amRNSDirector/PDMR Shareholding
9th May 20227:00 amRNSPotential for Significant Solar & Battery Project
29th Apr 20227:00 amRNSSeritza Loan Extension
29th Mar 20227:00 amRNSWorking Capital Extended & Seritza Loan Update
25th Feb 20227:00 amRNSWorking Capital Facility Update
21st Feb 20222:06 pmRNSSecond Price Monitoring Extn
21st Feb 20222:01 pmRNSPrice Monitoring Extension
21st Feb 202211:06 amRNSSecond Price Monitoring Extn
21st Feb 202211:00 amRNSPrice Monitoring Extension
18th Feb 20229:05 amRNSSecond Price Monitoring Extn
18th Feb 20229:00 amRNSPrice Monitoring Extension
31st Jan 20227:00 amRNSTotal Voting Rights
19th Jan 20224:41 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.