Project Update

20 Jul 2017 07:00

RNS Number : 5693L
Ncondezi Energy Limited
20 July 2017
 

News Release

 

 

Project Update

 

20 July 2017: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) is pleased to announce a project update on the new partner search and shareholder loans.

 

Key Highlights

 

· Positive feedback on new partner process with Letters of Interest received from several strategic parties

 

· Second phase of process initiated with select strategic parties

 

· New partner process completion targeted for Q4 2017, with the next update planned for August 2017

 

Partner Search Process

 

In June 2017, Ncondezi launched a new strategic partner process to identify a potential partner to develop the 300MW thermal coal power project (the "Project") jointly with the Company. Although the process is still at an early stage, the Company has been encouraged by the quality of the participating parties, which represent a combination of leading international power companies and regional power developers.

 

During July 2017, Ncondezi received Letters of Interest from several potential strategic parties which has allowed the Company to narrow the process down to a smaller select group for the second phase.

 

For the second phase of the process, potential partners will be expected to complete their necessary due diligence, Q&A and deal structuring work to submit non-binding offers to the Company. Based on the non-binding offers received from the parties, the Company will then narrow the process to a few preferred parties who will be further supported by the Company to complete their detailed due diligence for submission of the binding offers.

 

The process is currently targeting submission of binding offers before the end of Q3 2017 with transaction close during Q4 2017.

 

Further updates for shareholder are planned for August 2017.

Whilst the initial feedback in relation to the new strategic partner process is encouraging, there can be no certainty that the new strategic partner search process will be successful.

 

Shareholder Loans

 

Ncondezi plans to initiate discussions with Shareholder Loan holders to extend the maturity date of the Shareholder Loans, which currently reach maturity on 2 September 2017. The extension is being requested to provide the Company with sufficient time to close out the strategic partner process and further explore loan repayment options, however, there can be no certainty that an extension to the repayment date will be agreed.

 

The Company expects more attractive repayment options to become available once the new partner process has been completed.

 

Assuming that the Shareholder Loans' repayment date can be extended, the Company will have sufficient funding in place to cover its working capital commitments until the end of September 2017.

 

Enquiries

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly

+44 79 0161 6098

Liberum Capital Limited:NOMAD & Broker

Neil Elliot / Richard Crawley

+44 (0) 20 3100 2000

 

Note:

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation ("MAR"). Upon the publication of this announcement via Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain. If you have any queries on this, then please contact Hanno Pengilly, Chief Development Officer of the Company (responsible for arranging release of this announcement) on +44 79 0161 6098.

 

Ncondezi Energy owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW. The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSFDEEUFWSEEW
Date   Source Headline
24th Jan 20197:00 amRNSShareholder Loan Conversion
16th Jan 20197:00 amRNSIssue of Equity
28th Dec 20187:00 amRNSProject Update
21st Dec 20187:00 amRNSUpdated Project Presentation
10th Dec 201812:01 pmRNSHolding(s) in Company
5th Dec 20187:00 amRNSIssue of Equity
26th Nov 20187:00 amRNSProject Update
16th Nov 20187:01 amRNSShareholder Loan Restructuring Complete
5th Nov 201812:30 pmRNSResult of AGM
5th Nov 20187:00 amRNSGeneral Update
12th Oct 20187:00 amRNSNotice of AGM
3rd Oct 20188:07 amRNSHolding(s) in Company
28th Sep 20187:00 amRNSInterim Results and Directorate Change
30th Aug 201810:45 amRNSGeneral Update
10th Aug 20187:00 amRNSShareholder Loan Update
26th Jul 20187:00 amRNSProject Update
6th Jul 201811:49 amRNSHolding(s) in Company
6th Jul 201810:38 amRNSHolding(s) in Company
29th Jun 20187:00 amRNSAnnual Financial Report
11th Jun 20187:00 amRNSFinancial Model Update
30th May 20182:30 pmRNSIssue of Equity
29th May 20187:00 amRNSShare Option Grants
4th May 20187:00 amRNSPlacing to Raise £950,000
3rd May 20187:00 amRNSProject Update
30th Apr 20184:40 pmRNSSecond Price Monitoring Extn
30th Apr 20184:35 pmRNSPrice Monitoring Extension
27th Apr 201811:05 amRNSSecond Price Monitoring Extn
27th Apr 201811:00 amRNSPrice Monitoring Extension
25th Apr 20187:00 amRNSProject Update
18th Apr 20187:00 amRNSProject Update
27th Dec 20177:00 amRNSProject Update
28th Nov 20173:45 pmRNSResult of AGM
9th Nov 20177:09 amRNSNcondezi signs NBO with GE and CMEC
30th Oct 20172:30 pmRNSDirector/PDMR Shareholding
30th Oct 20177:00 amRNSNotice of AGM
20th Oct 20177:00 amRNSNcondezi Agrees Non-Binding Offer with GE and CMEC
18th Oct 20177:00 amRNSPlacing to Raise £750,000
29th Sep 20177:00 amRNSHalf-year Report
27th Sep 20172:05 pmRNSSecond Price Monitoring Extn
27th Sep 20172:00 pmRNSPrice Monitoring Extension
13th Sep 20174:00 pmRNSChange of Registered Office
4th Sep 20177:00 amRNSShareholder Loan Extension
25th Aug 20177:00 amRNSProject and Financing Update
20th Jul 20177:00 amRNSProject Update
30th Jun 20177:00 amRNSFinal Results
23rd Jun 20175:15 pmRNSUS$582,000 Loan Facility Agreed - Amend
23rd Jun 20177:00 amRNSUS$582,000 Loan Facility Agreed
26th May 20177:24 amRNSExclusive Discussions with SEP Suspended
11th May 20177:00 amRNSShareholder Loan Extension
10th May 20177:00 amRNSProject and Funding Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.