Suzlon Project Update

17 May 2011 10:30

RNS Number : 7248G
Caparo Energy Ltd
17 May 2011
 



NOT FOR RELEASE, PUBLICATION OR DISTRIBUTION, DIRECTLY OR INDIRECTLY, IN OR INTO THE UNITED STATES, AUSTRALIA, CANADA OR JAPAN

 

 

Press Release

17 May 2011

 

 

Caparo Energy Limited

("Caparo Energy" or the "Company")

 

Progress with Suzlon: Delivery of Initial Projects Ahead of Schedule

2,000 MW Gamesa Agreement

Secured Land for up to 3,000 MW

Update on Mezzanine Funding

 

 

The board of directors of Caparo Energy (the "Board") is pleased to announce a number of developments in connection with the Company's operations.

 

Suzlon

In connection with the Company's agreement with Suzlon Energy Limited ("Suzlon"), the Board is pleased to report that first deliveries, meaning commissioned and connected to the grid, of the initial 100.8 MW of projects, as announced on 28 January 2011, are now anticipated to commence by the end of June 2011, several months ahead of the previously announced schedule of Q4 2011. The company has also recently drawn down a tranche of senior debt from its lenders for these projects.

 

In addition, the Company is currently in the process of finalising the sites for the remaining 400 MW of projects, which are due to be commissioned and connected to the grid by March 2012, and anticipates placing purchase orders for these between July and September 2011. On this basis, the Board believes that the Company is on track to meet the roll-out schedule announced in January 2011, which would result in a cumulative 500 MW of capacity being commissioned by March 2012 and a further 500 MW to be commissioned progressively by March 2013.

 

Gamesa

The Company also announces that it has entered into, through its wholly owned subsidiary Caparo Energy (India) Ltd, an agreement with Gamesa Wind Turbines Pvt Ltd ("Gamesa"), a global leader in wind turbine manufacturing, for the supply, erection, commissioning and operation/maintenance of a further cumulative 2,000 MW of turbine capacity for wind power projects to be set up in India (the "Gamesa Agreement"). The Gamesa Agreement provides for the turbine capacity to be delivered progressively from 2012 up until the end of 2016.

 

The Board believes that the Gamesa Agreement is priced attractively, relative to current market prices for each of the models of turbines to be supplied, and is subject to certain adjustments, for deliveries after the first 450 MW, based on an agreed formula to reflect changes in applicable international indices. In return for the delivery of up to 2,000 MW of capacity, Gamesa will receive certain commitment advances over a period of three years..

 

Under the Gamesa Agreement, Caparo Energy will be responsible, inter alia, for site assessments and the procurement of the land required for installation of the wind farms.

 

Land

The Company has secured land that it believes will be suitable for the installation of 3,000 MW of wind power generation farms in sites across various wind-rich states. These include leases and direct allotments, licences and sanctions from the respective state authorities and the initial permissions for the installation and connection of power generation farms.

 

Preliminary wind assessment studies undertaken by the Company through an internationally recognised firm in this field indicate that these sites will represent attractive wind resources once developed. The Company has commenced the installation of wind masts on these sites, in order to collect more detailed wind data, and anticipates that the first wind power projects for these locations will be commissioned from Q4 2012.

 

The securing of independent access to land and turbines is part of the Company's long-term strategy for value creation, as previously disclosed in its AIM Admission Document.

 

Funding

As previously announced on 28 January 2011, in order to limit the Company's reliance on its internal cash flow in the short and medium term and to ensure that the Company is able to acquire generating capacity in accordance with the delivery timeframes set out in both the Suzlon and Gamesa agreements, the Company announces that it is in advanced discussions with a number of parties in connection with the provision of additional mezzanine financing and that several non-binding term sheets have been agreed. This financing, which is anticipated to fund in excess of 600 MW of projects to be delivered under both the Suzlon and the Gamesa agreements, is expected to be finalised in various tranches by the end of Q3 2011. A further update on the outcome of these financing initiatives will be provided in due course.

 

 

Ravi Kailas, Caparo Energy's Chief Executive Officer, said:

"We have been working closely with Suzlon and are pleased with the advancement of the delivery schedule of the initial projects and the progress on placing our next purchase orders with them.

"The long term agreement with Gamesa represents the kick-off of our second phase of building wind farm capacity. This has been achieved sooner than we expected. The Indian wind energy market has been very active and we view the terms of this new agreement as favourable to us. Through our strong relationships with market leaders Suzlon and Gamesa, the Company should, be able to secure its supply of wind power capacity in a rising market at preferential pricing.

"Successfully securing access to land required to meet this supply will create significant long-term value for the Company and its stake holders."

 

Further information on the Company can be found at www.caparoenergy.com.

 

- Ends -

 

For further information please contact:

 

Caparo Energy Limited

Ravi Kailas, Chief Executive Officer

+91 40 4396 0000

Strand Hanson Limited

Angela Peace / Paul Cocker / James Harris

+44 (0) 20 7409 3494

Mirabaud Securities LLP

Peter Krens / Rory Scott

+44 (0) 20 7878 3360

Pelham Bell Pottinger

Charles Vivian / Philippe Polman

+44 (0) 20 7861 3232

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLGGUMGAUPGURM
Date   Source Headline
31st May 20167:28 amRNSINDIAN SUBSIDIARY FINANCIAL RESULTS
13th May 20167:01 amRNSShare Options Changes
13th May 20167:00 amRNSTrading Update
11th May 20167:00 amRNSNotice of AGM
7th Apr 20167:00 amRNSNew US$175m loan to take Mytrah to 1000 MW
3rd Mar 20167:00 amRNSFinal Results
16th Nov 20157:00 amRNSTrading Update and Change of Registered Office
20th Oct 201510:24 amRNSDirector Share Dealing
5th Oct 20155:49 pmRNSDirector Share Dealing
28th Sep 20157:00 amRNSCommissioning of 16.8 MW Wind Energy Project
14th Aug 20157:00 amRNSInterim Results
6th Aug 20152:50 pmRNSResult of AGM
6th Aug 20157:00 amRNSAGM Trading Update
23rd Jul 201510:53 amRNSCEO receives 'Wind Power Person of the Year Award'
29th Jun 20157:00 amRNSNotice of AGM, Posting of Annual Report
1st Jun 20157:00 amRNSDirector Share Options
21st Apr 20157:00 amRNSFinal Results
20th Apr 20157:00 amRNSNotice of Results
16th Apr 20157:00 amRNSMYTRAH ENERGY RAISES USD 60 MILLION
25th Feb 20157:30 amRNS150MW Capacity Expansion Secures Project Finance
12th Dec 20147:00 amRNSFinancing and Trading Update
21st Nov 20147:05 amRNSUSD70m of New Debt, Fuelling Continued Growth
24th Sep 20147:00 amRNSInterim Results
25th Jul 20147:00 amRNSUpdate on Portfolio Assets
17th Jul 20142:00 pmRNSResult of AGM
23rd Jun 20144:40 pmRNSSecond Price Monitoring Extn
23rd Jun 20144:35 pmRNSPrice Monitoring Extension
16th Jun 20147:00 amRNSNotice of AGM
17th Mar 20147:00 amRNSFinal Results
10th Jan 20147:00 amRNSChange of Registered Office
23rd Dec 20137:00 amRNSProject Update
15th Nov 201311:09 amRNSDirector Share Purchase
5th Nov 20137:00 amRNSChange of Adviser
30th Sep 20137:00 amRNSInterim Results
12th Sep 20137:00 amRNSRe-introduction of GBI Incentive Scheme
4th Sep 20134:40 pmRNSSecond Price Monitoring Extn
4th Sep 20134:35 pmRNSPrice Monitoring Extension
30th Aug 20137:00 amRNSUSD17.5m Mezzanine Financing & Operations Update
1st Aug 20137:00 amRNSUpdate on Proposed Acquisition & Operations Update
31st Jul 20133:15 pmRNSResult of AGM
26th Jul 20135:40 pmRNSDirector Share Dealing - Replacement
26th Jul 20134:56 pmRNSDirector Share Dealing
24th Jun 20137:00 amRNSFinal Results
20th May 20137:00 amRNSUpdate Proposed Acquisition of 59.75 MW
24th Apr 201312:15 pmRNSHolding(s) in Company
4th Apr 20137:00 amRNSProposed Business Trust Listing
13th Mar 20137:00 amRNSOperational Update
5th Feb 20134:58 pmRNSHolding(s) in Company
5th Feb 201312:00 pmRNSHolding(s) in Company
18th Jan 20134:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.