Roundtable Discussion; The Future of Mineral Sands. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksMetals Exploration Regulatory News (MTL)

Share Price Information for Metals Exploration (MTL)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 5.10
Bid: 5.00
Ask: 5.20
Change: -0.15 (-2.86%)
Spread: 0.20 (4.00%)
Open: 5.25
High: 5.25
Low: 5.05
Prev. Close: 5.25
MTL Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Operational Update to July 2013

20 Aug 2013 07:52

RNS Number : 0646M
Metals Exploration PLC
20 August 2013
 



METALS EXPLORATION PLC

 

OPERATIONAL UPDATE TO 31 JULY 2013

 

Metals Exploration plc (AIM: MTL) ("Metals Exploration" or "the Company"), the natural resources exploration and development company with assets in the Pacific Rim region, is pleased to provide an operations update on matters relating to its Runruno gold-molybdenum project ("the Project") and exploration activities in the Philippines.

 

AIM Code : MTL

At:31 July 2013

Shares in Issue: 1,158,469,436

Options in Issue: 14,275,000

Warrants in Issue: 2,500,000

 

Directors:

Ian Holzberger, Executive Chairman

Timothy Dean

Guy Walker

Christopher Whitehouse

Julian Wilson

 

Management:

Ian Holzberger, Executive Chairman

Liam Ruddy, Company Secretary

John Stubbs, CFO

Craig Watkins, GM Runruno Project

Chevy Albo, Finance & Administration

Rosalie Soriano, Legal Counsel

Agnes Goze, Environment & Permitting

Tommy Alfonso, Financial Controller

Peter Clark, GM Mining

Larry McGeechan, GM Process Plant Construction

Kevin Oxenham, GM Maintenance

Jeff Jardine, Process Engineering Mgr.

 

 

For further Information please contact:

 

Metals Exploration plc

Ian Holzberger: +61 41 888 6165

Liam Ruddy; +44 7911 719 960

 

Nominated Adviser:

Westhouse Securities Limited

Martin Davison

+44 (0)20 7601 6114

 

Broker:

SP Angel Corporate Finance LLP

Ewan Leggat

+44 (0)20 3463 2260

 

Public Relations:

Tavistock Communications

Edward Portman / Jos Simson

+44(0) 20 7920 3150

Highlights

 

· Shareholders approve a three tranche US$57.7 million share placing resulting in funds that allow the commencement of full construction at Runruno.

· The build duration is forecast to take approximately 15 month from July 2013 with first gold pour anticipated in Q4 2014.

· Funds received totalling US$37.7 million from the initial two tranches - a third tranche totalling US$22.9 million is due to be completed on 15 October.

· Completion of a successful Open Offer to shareholders raises a further £366,711.

· Early infrastructure and site construction works near completion.

· Completion of stage 1 overhead power line from Maddiangat to Runruno. Stage 2 from Bayambong to Maddiangat to commence during Q3 2013.

· Completion and commissioning of Runruno potable water system.

· Access to the mine starter pits established for large mining fleet

· Delivery of new mining fleet to site, Komatsu complete machinery assembly and commence operator training.

· Development and operational team is significantly strengthened through a number of senior hires.

· Dialogue continues with various Resource Banks with the aim of finalising a US$70 million debt package to provide sufficient funding to take Runruno through to commercial production.

· MTL's subsidiary, FCF, defends its position and rights in the Supreme Court of the Philippines through the Court Of Appeals, and on 24 May 2013 the petitions for the issuance of the Writ of Kalikasan and the Writ of Continuing Mandamus were dismissed.

· Two diamond rigs committed to regional exploration continue work within the FTAA.

 

 

About Runruno Gold Project,

 

Location: Central Luzon, Philippines, 320km north of Manila.

 

Status: Development ready,

Feasibility study completed May 2010.

 

Mine life: 10.3 years.

 

Payable Au: 1 million ozs.

 

Annual Production:

Year 1-5: 101,800 ozs Au ave.

Years 6-10: 92,700ozs Au ave.

 

Capital Cost1: US$182.8 m

 

Operating Cost2: US$ 442/oz Au

 

Mining: Open pit, truck and shovel operation.

 

Operational Strip Ratio: 5.2:1 waste to ore.

 

Processing: gravity, BIOX® oxidation and CIL to recover gold as doré bullion.

 

2P Reserves3: 15mt @ 1.85g/t Au and 603 ppm Mo.

 

Mineral Resource3:

Runruno Main - 26mt @1.69 g/t Au and 453ppm Mo, including reserves.

Malilibeg South - 7.55mt @1.4 g/t Au and 1,200 ppm Mo

 

Upside: by-product molybdenum, mine life extension, highly prospective mineralised system.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Notes:

 

1. Capital Cost updated October 2011 - estimated in Q3 2011 US$, at US$167.8 million increased by the cost of the acquisition of the mining fleet at US$15 million

2. May 2010 Feasibility Study - estimated in Q4 2009 US$ reduced by US$ 35 per ounce attributed to the removal of the mining fleet operation lease in favour of outright purchase.

3. Refer to the Company website, www.metalsexploration.com for complete Mining Reserve and Mineral

 

 

Ian Holzberger, Executive Chairman, commented:

 

"It has been another very positive period in which the company has made great strides on both the operational and corporate fronts. The financial backing shown by our shareholders provided further endorsement for the company's Runruno project and allowed us to move into the full construction phase on 1 July. A key milestone is to agree a suitable debt facility before the end of 2013 to move us through to project completion in Q4 2014.

 

"The visible signs of progress made on-site are moving apace. The arrival of our new mining fleet together with the near completion of the early infrastructure and site works shows just how close we are to realising our objective of gold production, which in turn should generate shareholder value. I would also like to take this opportunity to welcome a number of significant senior hires to the company, their experience and expertise through the development and operational phases will be invaluable.

 

Finally, working with The Department of Environment and Natural Resources, The Mines and Geosciences Bureau and the National Commission on Indigenous Peoples, the Company was successful in defending its position and rights in the Supreme Court of the Philippines through the Court of Appeals resulting in the dismissal of both writs. This lays down a strong marker for future as the Company will always vigorously defend its stance as a leader in observing environmental laws and obligations."

 

For associated images, please click on, or paste the following link in to your web browser, to view the PDF file:http://www.rns-pdf.londonstockexchange.com/rns/0646M_-2013-8-20.pdf

 

 

Development of the Runruno Gold Project

 

The Runruno Gold project transitioned into full development on 1 July 2013 with first gold expected in Q4 2014. Project activities have ramped up rapidly and a number of highly qualified senior employees have been retained to execute the development and operational phases of the Project including the General Manager Process Plant Construction, General Manager Maintenance, Process Engineering Manager, General Manager Technical Services and a Procurement and Contracts Manager. These new additions to the Project team strengthen and compliment the pre-existing well experienced and Filipino and expatriate team. The Project is advancing strongly.

 

Step out drilling activities to further test the potential of the Runruno Financial or Technical Assistance Agreement ("FTAA") for gold and copper mineralisation continued with promising results.

 

 

 

Funding Package

 

On 23 April 2013 the first of three tranches of a Share Placing announced on 26 March 2013 completed successfully and resulted in gross contributions equivalent of US$14.7m and after deducting commissions and costs the net equivalent of US$14.4m was raised. In return 139,090,690 new ordinary 1 pence shares were issued.

 

The second tranche completed successfully on 18 June 2013 resulting in gross contributions equivalent of US$20.1m and after deducting commissions and costs the net equivalent of US$19.7m was raised. In return 189,439,765 new ordinary 1pence shares were issued.

 

The third tranche is due to be completed on 15 October 2013 and should result in gross contributions equivalent of US$22.9m and after deducting commissions and costs the equivalent of US$22.5m is expected to be raised. In return 216,502,589 new ordinary 1pence shares will be issued.

 

In total this Share Placing is planned to raise an equivalent of $57.7m in gross contributions and US$56.6 after deducting commissions and costs. A total of 545,033,044 new ordinary shares of 1 pence each in the Company will be issued in total for these contributions.

 

On 10 May 2013 the Company announced an Open Offer to all of its shareholders other than those principal shareholders who participated in the $57.7m Share Placing, the Company having received waivers from participation from these principal shareholders. The Open Offer was made on principally the same commercial terms as the Share Placing with the intention of allowing all shareholders the chance to participate in the issuing of new shares at the same price. In particular the offer provided for 65 new shares for every 100 shares held at a share price of 7pence for each new share issued. This offer had the potential to increase the shares in issue by 54,294,052 new shares, and raise a maximum gross capital contribution of £3,800,584.

 

The offer completed on 31 May 2013 and the Company announced on 5 June 2013 that a total of 5,195,877 new ordinary shares were issued and a total of £363,711 in gross contributions was received.

 

At the time of the announcement the Chairman commented "I am delighted by the support shown by our shareholders and their endorsement of the Runruno project. There is still a funding gap which we are working to fill, but the strength of our Balance Sheet through this additional equity capital will make this a less risky project to finance. We are in an enviable position relative to many other junior mining stockholding companies, and it will be most welcoming in future news releases to be updating our shareholders on progress with the construction of the processing plant. The whole team have worked diligently for several years to achieve this position and I can assure our shareholders that management will not be complacent and our full efforts will be to bring the company into commercial production at the earliest opportunity. There have been some new large yellow trucks, dozers and excavators recently delivered to site and a full training program has commenced involving local personnel. All of a sudden the excitement factor has risen and this has enthused and energised the local workforce."

 

The Company continues to work with a number of Resource Banks to raise approximately US$70 million in debt with the intention that the debt facility will be available by the end of 2013

 

 

Infrastructure Site Works

 

The early construction works previously reported is now near complete and with the Project in full construction mode the infrastructure development crew has commenced constructing the remainder of the infrastructure components. The work completed to date has been completed within budget.

 

A synopsis of these works is as follows:

 

 

 

Early works

 

• General site earthworks including site access roads, river crossings and the development of infrastructure pads - completed;

• Processing plant pad earthworks - complete;

• Construction of the camp and office facilities - stage 1 complete and commissioned;

• Installation of a construction power system - complete and energised;

• Construction of the permanent connection to the power grid - stage 1 complete;

• Establishment of the potable water system - complete and commissioned;

• Erection of a concrete batching plant to support construction activities - complete and commissioned;

• Rehabilitation of the Solano - Runruno access road - 95% complete;

• Development of the pit access and tailing storage facility haul roads, the run of mine pad area and the heavy equipment workshop pad - complete; and

• Acquisition of selected units of the mobile fleet - 90% complete.

Stage 2 works

 

· Stage two of the mine camp - expand camp to 750 bed spaces;

· Emergency services building;

· General store;

· Heavy vehicle workshop;

· Mine office;

· Stage 2 of the 69kV power line to the Bayombong switchyard;

· General structures including new laundry and recreational facilities;

· Instillation of fire fighting systems including the purchase of mobile plant;

· Process Plant workshop; and

· Construction of an aggregate crusher.

 

 

General site earthworks

 

The batch plant, accommodation camp and office site pads and foundations have been completed and commissioned. The new mess which has the capacity to serve 1,000 personnel has been commissioned and is in full service.

 

A permanent road dedicated to project use has been constructed from the national Solano - Runruno road into the project site. The local access "Barangay" road has been rehabilitated for use by the local residents.

 

Please refer to image number 1 "Mess Hall" in the attached images file.

 

 

Processing plant earthworks

 

The processing plant earthworks are complete and civil works for the construction of the processing plant will commence late in August. Please refer to image number 2 "Processing plant pad viewed from the mine "starter pit" area" in the attached images file.

 

Construction camp and site office

 

The General Office facilities have been completed and occupied. The upper story is used for administration with the ground floor accommodating the construction group. Please refer to image number 3 "two storey office block" in the attached images file.

 

Stage one of the construction camp has been completed and 576 bed spaces commissioned in five buildings. Stage two of the camp has commenced which will add a further 168 bed spaces in two buildings, a new laundry facility and recreation facilities. Stage two is forecast to be completed in Q4 2013. Please refer to image number 4 "Construction camp - ablutions, accommodation and messing facilities (central building)" in the attached images file.

 

The potable water plant has been commissioned and is now delivering water to the accomodation complex. Please refer to image number 5 "Accommodation Area Potable Water Header Tank" in the attached images file.

 

A package sewage plant has been installed to service the camp and office facilities. It is currently being commissioned.

 

 

Site power system

 

Power has been reticulated to all of the infrastructure sites including the general office and associated buildings, accommodation and mess, batch plant, mine office, heavy vehicle workshop and the process plant areas. The power network distributes power from the permanent switchyard located in the processing plant area where two 1,000kVA generator sets have been installed and commissioned and the 69kV power line connecting the site to the main 230 kV grid at the Bayombong switch yard terminates. Please refer to image number 6 "Power Reticulation Network" in the attached images file.

  

Power Supply - Off Site

 

Permanent power will be supplied to the project from the Philippine National Grid via a connection at the Bayambong switch yard. The 69kV overhead power line connecting the switchyard to the mine site is being constructed in two stages, stage one from Maddiangat to Runruno over a distance of 22 kilometres and stage two Bayambong to Maddiangat distance of 15 kilometres. Stage one to Maddingat has been completed and energised at 13.8 kV. Power is being drawn from the local distributer during the construction phase of the project. Construction of stage two of the line will commence during the Q3 and continue for around 6 months. Once complete the line will provide a direct connection to the national grid at the Bayombong switchyard. The Project will commence drawing power from the direct connection once plant commissioning commences.

 

The Project has now been licenced for a direct connection to the grid with the Commission finding in favour of the Project's application during the quarter. Negotiations with the Independent Power Producers to secure a power supply contract and to determine bulk pricing have been initiated.

 

The early connection to the 13.8 kV grid has cut the cost of power to the project by around 40%.

 

An aerial fibre optic cable is being strung along the top of the power poles to connect the project to the National fibre network at Solano. This will significantly improve external site communications. Please refer to image number 7 "Stage One - 69kV powerline Runruno to Maddiangat showing Fibre Optic Cable (top of poles)" in the attached images file.

  

Potable water system

 

The potable water system drawing water from the Lintugan River has been completed and commissioned. The 3.2 kilometre pipeline from the weir and pump house has been laid, and the weir, pump house and processing facilities are operating. In addition to supplying the project requirements potable water will be made available to the Runruno town residents to replace the current raw water sources used for domestic supply. Please refer to image number 8 "Potable Water Processing Plant at the Lintugan River " in the attached images file.

  

Concrete Batch Plant

 

The concrete batch plant has been commissioned and is currently producing concrete for the infrastructure works. Around 14,000 cubic metres of concrete will be used in the construction of the project.

  

Solano - Runruno Access Road

 

The Solano to Runruno access road has now been extensively upgraded through the combined work of the Department of Public Works and Highways (DWPH) and the Company. These include concreting a further four kilometres of the roadway, replacement of two bridges, realignment of a number of tight curves and resurfacing of the remaining unsealed section of the roadway. Only eight kilometres of the 27 kilometre roadway remains unsealed but has now been rehabilitated to support all weather use. These works are now 97% completed and will be finalised during September following the Company handing over a newly constructed box culvert on the last section of road alignment works. Please refer to image number 9 "Box Culvert, Solano - Runruno Road" in the attached images file.

 

The Solano - Runruno road is now established as a sound all weather road which will satisfactorily support the local communities and the project during development and operations. Please refer to image number 10 "Road Rehabilitation Solano - Runruno Road - Concrete Surfacing by DWPH, Solano" in the attached images file.

  

Mine Area

 

Access to the mine starter pits has now been established to a production ready standard. Two roads access the commencement of the stage one pit haul road from the run of mine ore (ROM) pad adjacent to the processing plant crusher site. The second road connects the stage one pit to the tailing storage facility dam wall site. Waste Rock from the stage one pit area will be mined during the construction period to build the tailing storage facility dam wall. The roads have been constructed to a high safety factor to support the safe operation of the large mining equipment in wet and dry conditions. Please refer to image number 11 "Stage 1 pit to ROM Pad Haul Road showing 100 tonne dump trucks passing" in the attached images file.

  

Mine Fleet

 

The new mining fleet was delivered to site by Komatsu late in quarter 1 (reported in Operational Update to 31 March 2013). Komatsu has now fully assembled, commissioned and handed over the entire fleet to the Company.

 

Operator training has commenced following a very structured and comprehensive trading program which is overseen by highly qualified and extensively experienced Company personnel teamed with Komatsu trainers. The majority of the operators have been employed from the local community, most of whom had no or little previous heavy vehicle experience. The program has progressed very well with all operators having graduated from training in flat conditions to training in mining conditions within the pit area. Training will continue throughout Q3 with production expected to commence in Q4. Please refer to image number 12 "In pit mining fleet training" and image number 13 "The Extremes"in the attached images file.

 

Additional support fleet has been purchased and is being modified for propose. This equipment will be progressively commissioned at site during the coming six month period.

 

Heavy Vehicle Workshop and Mine Office

 

Work has commenced on the construction of a heavy vehicle workshop to maintain the mine fleet and a mine office to support the mine production staff adjacent to the ROM Pad in an area which will eventually include bulk fuel storage, a warehouse / store compound and truck washing bay. These facilities will be progressively developed and commissioned during the next six month period. Please refer to image number 14 "Layout of Heavy Vehicle Workshop and Mine Office Area" in the attached images file.

 

Tailing Storage Facility

 

Access from the mine is about a 1km distance over the Sulong river via a custom built causeway and into the tailing storage facility dam wall. Please refer to image number 15 "Access in to Tailing Storage Facility Dam Wall Site (from Stage 1 pit)" in the attached images file.

  

Process Plant

 

The Company is now managing all aspects of the design and construction of the processing plant using its own personnel, well experienced consultants and contractors and specialist service providers. Contronmation Energy Services (CES) who have provided engineering design services to the Project over the last 15 month period, have been retained to complete the detailed design. Design of the processing plant has advanced substantially and it is expected that the first of the major civil works including the pouring of the first slab will commence early in September. Site work will advance rapidly from that point on.

 

Procurement of long lead time equipment has progressed well with several key deliveries secured which will support the Company's target of producing first gold in Q4 2014. The nine key packages which have been placed to date include the SAG mill, agitators, flotation cells, thickener and CCDs. Five additional packages are currently under assessment and will be awarded during Q3 2013.

  

Environment

 

The Company continues to maintain a high environmental standard with a commitment to rehabilitation, reforestation and green stabilisation of cut face. Routine on-going environment and social monitoring programs continue. The Company is an active participant in the Mining Forest Program and the Greening Philippines program. At Runruno, the Company is working with property owners to re-establish previously logged forests by planting large stands of trees endemic to the area. To date the project has planted in excess of 1.08 million trees and coffee seedlings in its various programs.

  

Safety

 

Safety remains a key priority of the Company. However, unfortunately during the quarter a fatality was recorded after a contractor retained to erect the high voltage power lines to site suffered a fatal injury. In addition one of its linesmen was electrocuted. There have been no other lost time accidents recorded in the quarter.

 

The accident has caused the Company to review its sub-contractor's safety procedures and implementation, and is in the process of further strengthening its safety capabilities.

 

Government

 

The Company continues to work with the Government to resolve the contents of the Philippines Bureau of Internal Revenue (BIR) of a Revenue Memorandum Circular No 17-2013 (RMC17) which casts doubt upon the Company's ability to avail any fiscal exemptions expressly provided for in its FTAA, to the extent it states FTAA Contractors are liable to pay the taxes due under the National Internal Revenue Code (reported in the Operational Update to March 31).

 

Writ of Kalikasan

 

On 24 May 2013 the Court of Appeals delivered its resolution on (i) a petition for the issuance of the Writ of Kalikasan, and a Writ of Continuing Mandamus against FCF Minerals Corporation (FCF) in the Barangay of Runruno, Nueva Vizcaya, and (ii) FCF's request to deny these writs on the basis they were designed as a Strategic Lawsuit Against Public Participation ('SLAPP') and effectively nothing more than harassment actions against FCF wherein FCF had lodged a claim for damages and costs. The resolution dismissed both writs and upheld our petition of SLAPP but was silent on the award of damages and costs.

 

At the time Mr Ian Holzberger, Chairman of the Company commented "as responsible miners and proud winners and holders of several prestigious mining environmental awards in the Philippines, FCF will always vigorously defend its position as a leader in observing environmental laws and obligations. This lawsuit was vexatious and devious from its inception but FCF, together with the DENR, MGB and NCIP were resolute in defending its entitlement to mine in the contract area provided it in its Financial or Technical Assistance Agreement with the Philippine Government. Our focus had been marginally diverted whilst we sought to dismiss these writs and now we have successfully achieved this we can continue the important work of putting Runruno into production, and always mindful of our duty of care to the environment as we progress'.

 

The resolution did not award damages or costs and we are advised this is most probably due to the value of damages included which would be customarily associated with corporations rather than individuals. However, FCF has reluctantly agreed to dispense with its damages claim but will seek to recover costs associated with its defence. There was sufficient independent material provided to the courts to support the vexatious nature of these writs by the petitioners. The judged ruled on the suit brought by the petitioners as follows:

 

i. it was unsubstantiated and the petitioners showed a 'clear lack of interest in prosecuting',

ii. it wasn't motivated by a concern for the protection of the environment, and

iii. it was a frivolous action as FCF is not and had not been 'committing acts inimical to the observance of environmental laws'.

 

FCF will seek to recover its costs by filing a 'Motion for the Partial Reconsideration of the Judgment' only insofar as it has been denied a claim for actual costs. The request for reconsideration will be isolated, focused solely on damages (actual costs) that FCF has already established with receipts which have been confirmed and authenticated through the testimony of our company attorney. If the appellate court denies FCF's motion it will have recourse to the Supreme Court for a petition for review.

 

 

Regional Exploration

 

Exploration work for the period was designed to continuously and systematically assess the FTAA for additional Runruno style gold mineralisation and also for porphyry copper-gold mineralisation. Diamond drilling activities were carried out beneath the main Runruno deposit and also to the south of the pit area, targeting resource extension connected to the main Runruno deposit and IP chargeability anomalies. Two diamond drill rigs were committed to the program.

 

 

Runruno Mineral Resource Extension

 

Resource extension drilling continued to extend the limits of the known mineralisation both south and east from the current Malilibeg South Mineral Resource Estimate (March 2013). Three additional drill holes have been completed which extends the potential of the zone a further 150m to the south and 40 metres to the east of the previously known mineralisation.

 

Runruno Deeps Drilling

 

The presence of anhydrite-biotite-sulphide veins in the deeper part of hole MXD18 (previously drilled to 200m below the main Runruno deposit in the Tayab area has been highlighted as of interest by geological consultants. These zones of anhydrite/gypsum veining show brecciation textures and may represent transitions to deeper, higher temperature styles of alteration and mineralisation suggesting the possibility of copper-gold porphyry deposits at depth.

 

To test this potential, a new hole MXD860 was drilled as an extension of hole MXD18 to a depth of 562 meters. The hole intersects alteration and sulphide mineralisation consisting of predominately pyrite over a wide interval. Steeply dipping gypsum veining was present throughout the bottom 150m of the hole. No significant gold or copper assays were reported from the hole, but the hole is considered significant due to the alteration and mineral assemblages. After petrographic examination of the core further follow-up drilling will be designed.

 

 

Regional Exploration

Regional exploration activities in the southern part of the project area included geological mapping, trenching and geochemical sampling.

Follow up trenching activities continued to evaluate the soil geochemistry results from the 500m long northerly-trending zone of coincident gold, molybdenum and arsenic anomalism that was discovered following a geochemical sampling program in the Malong/Burnt Tree area in the south east of the FTAA. Channel cut samples are being collected at 5m intervals if bedrock is encountered above a trenching depth of 2m and auger samples at 10m intervals in zones of deeper weathering.

Encouraging anomalous gold assays have been returned from some of the trench and auger work. Once complete the results will be reviewed and interpreted and follow up work planned.

Follow up work with the objective of delineating potential drill targets will commence after a thorough review of data is completed.

 

 

Approval

 

Mr Ian Holzberger, a director of the Company, who has been involved in the mining industry for more than 40 years, is a Member of the Australasian Institute of Mining and Metallurgy and the Australian Institute of Geoscientists, has compiled, read and approved the technical disclosure in this regulatory announcement.

 

 

Forward Looking Statements

 

Statements relating to the estimated or expected future production, operating results, cash flows and costs and financial condition of Metals Explorations, planned work at the Company's projects and the expected results of such work are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by words such as the following: expects, plans, anticipates, forecasts, believes, intends, estimates, projects, assumes, potential and similar expressions. Forward-looking statements also include reference to events or conditions that will, would, may, could or should occur. Information concerning exploration results and mineral reserve and resource estimates may also be deemed to be forward-looking statements, as it constitutes a prediction of what might be found to be present when and if a project is actually developed.

 

These forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable at the time they are made, are inherently subject to a variety of risks and uncertainties which could cause actual events or results to differ materially from those reflected in the forward-looking statements, including, without limitation: uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from logistical, technical or other factors; the possibility that results of work will not fulfil projections/expectations and realize the perceived potential of the Company's projects; uncertainties involved in the interpretation of drilling results and other tests and the estimation of gold reserves and resources; risk of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of environmental issues at the Company's projects; the possibility of cost overruns or unanticipated expenses in work programs; the need to obtain permits and comply with environmental laws and regulations and other government requirements; fluctuations in the price of gold and other risks and uncertainties.

 

 

Technical Notes and Glossary of Technical Terms

 

"assay" qualitative or quantitative analysis of a metal or ore to determine its components

"Au" chemical symbol for gold

"block model" a computer based representation of a deposit in which geological zones are defined and filled with blocks which are assigned estimated values of grade and other attributes. The purpose of the block model (BM) is to associate grades with the volume model. The blocks in the BM are basically cubes with the size defined according to certain parameters.

"bulk density" the dry in-situ tonnage factor used to convert volumes to tonnage. Bulk density testwork is carried out on site and is relatively comprehensive, although samples of the more friable and broken portions of the mineralised zones are often unable to be measured with any degree of confidence, therefore caution is used when using the data. Bulk density measurements are carried out on selected representative samples of whole drill core wherever possible. The samples are dried and bulk density measured using the classical wax-coating and water immersion method. The average bulk density for the mineralisation has been estimated at 2.5 using more than 3,000 measurements on drill core.

"cut-off grade" the lowest grade value that is included in a resource statement. Must comply with JORC requirement 19: "reasonable prospects for eventual economic extraction" the lowest grade, or quality, of mineralised material that qualifies as economically mineable and available in a given deposit. May be defined on the basis of economic evaluation, or on physical or chemical attributes that define an acceptable product specification.

"g/t" grammes per tonne, equivalent to parts per million

"g/t Au" grammes of gold per tonne

"grade cap" the maximum value assigned to individual informing sample composites to reduce bias in the resource estimate. They are capped to prevent over estimation of the total resource as they exert an undue statistical weight. Capped samples may represent "outliers" or a small high-grade portion that is volumetrically too small to be separately domained.

"JORC" or "JORC 2012"

The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (the "JORC Code" or "the Code"). The Code sets out minimum standards, recommendations and guidelines for Public Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves.

The definitions in the JORC Code are either identical to, or not materially different from, those similar codes, guidelines and standards published and adopted by the relevant professional bodies in Australia, Canada (NI43-101), South Africa, USA, UK, Ireland and many countries in Europe.

"JORC Inferred Resource"

that part of a Mineral Resource for which tonnage, grade and mineral content can be estimated with a low level of confidence. It is inferred from geological evidence and assumed but not verified geological and/or grade continuity. It is based on information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drillholes which may be limited or of uncertain quality and reliability.

"JORC Indicated Resource"

that part of a Mineral Resource for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a reasonable level of confidence. It is based on exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. The locations are too widely or inappropriately spaced to confirm geological and/or grade continuity but are spaced closely enough for continuity to be assumed.

"JORC Measured Resource"

that part of a Mineral Resource for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a high level of confidence. It is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. The locations are spaced closely enough to confirm geological and grade continuity.

"JORC Proven Reserve"

is the economically mineable part of a Measured Mineral Resource. It includes diluting materials and allowances for losses which may occur when the material is mined. Appropriate assessments and studies have been carried out, and include consideration of and modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors. These assessments demonstrate at the time of reporting that extraction could reasonably be justified.

"JORC Probable Reserve"

is the economically mineable part of an Indicated, and in some circumstances, a Measured Mineral Resource. It includes diluting materials and allowances for losses which may occur when the material is mined. Appropriate assessments and studies have been carried out, and include consideration of and modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and governmental factors These assessments demonstrate at the time of reporting that extraction could reasonably be justified.

A Probable Ore Reserve has a lower level of confidence than a Proved Ore Reserve but is of sufficient quality to serve as the basis for a decision on the development of the deposit.

"kriging neighbourhood analysis, or KNA"

The methodology for quantitatively assessing the suitability of a kriging neighbourhood involves some simple tests. It has been argued that KNA is a mandatory step in setting up any kriging estimate. Kriging is commonly described as a "minimum variance estimator" but this is only true when the block size and neighbourhood are properly defined. The objective of KNA is to determine the combination of search neighbourhood and block size that will result in conditional unbiasedness.

"Km" Kilometres

"lb" Avoirdupois pound (= 453.59237 grammes). Mlb = million avoirdupois pounds

"M" Metres

"Mineral Resource"

a concentration or occurrence of material of intrinsic economic interest in or on the Earth's crust in such form, quality and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade, geological characteristics and continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge. Mineral Resources are sub-divided, in order of increasing geological confidence, into Inferred, Indicated and Measured categories when reporting under JORC.

"micron (µ)" a unit of length (= one thousandth of a millimetre or one millionth of a metre).

"Mining Reserve"

the part of a mineral resource which is economically and technically feasible to extract.

"2P Mining Reserve"

Proven and Probable Reserves.

"Mo" chemical symbol for molybdenum

"Monzonite-monzodoirite"

A course grained intrusive igneous rock intermediate between syenite and diorite

"oz" Troy ounce (= 31.103477 grammes). Moz = million troy ounces

"ROM" Run of mine

"screen fire assay"

a method of analysing gold through separating the coarse and fine grained particles then assaying them to produce a weighted average.

"strip ratio" the ratio of the amount of waste which needs to be extracted in order to remove 1 unit of ore.

"Syenite" A course grained intrusive igneous rock belonging to the alkali series

"t" tonne (= 1 million grammes)

 

  

 

For further information please visit: www.metalsexploration.com or contact:

 

 

Metals Exploration PLC info@metalsexploration.com

 

 

Ian R. Holzberger +63 (0) 9189 795 992

(Chairman) +61 (0) 418 886 165

 

Liam A. Ruddy +44 (0) 207 869 5109

(Company Secretary) +44 (0) 7911 719960

 

Nominated Adviser

Westhouse Securities Ltd +44 (0) 207 601 6100

Martin Davison

Paul Gillam

 

Public Relations

Tavistock Communications

Edward Portman +44 (0) 207 920 3168

Jos Simson +44 (0) 207 920 3157

 

Broker

SP Angel Corporate Finance LLP +44 (0) 203 463 2260

Ewan Leggat

Katy Birkin

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAKPEALXDEEF
Date   Source Headline
29th Apr 20247:00 amRNSQuarterly Update to 31 March 2024
25th Apr 202410:18 amRNSHolding(s) in Company
5th Apr 20242:00 pmRNSExercise of Options, PDMR Dealing and TVR
27th Mar 20247:00 amRNSUpdate on Debt Facilities
18th Mar 20247:00 amRNSAppointment of Chairman
5th Feb 202412:01 pmRNSInvestor Presentation
24th Jan 20247:00 amRNSQuarterly Update to 31 December 2023
12th Jan 20247:00 amRNSAcquisition of Prospective Philippine Exploration
14th Dec 20232:00 pmRNSExercise of Options and Total Voting Rights
11th Dec 20237:00 amRNSReceipt of Awards
1st Dec 20237:00 amRNSAppointment of New Auditor
17th Oct 20237:00 amRNSQuarterly Update To 30 September 2023
27th Sep 20237:00 amRNSInterim Results
18th Sep 20237:00 amRNSDirector Resignation
20th Jul 20237:00 amRNSQuarterly Update to 30 June 2023
19th Jun 20234:45 pmRNSResult of AGM
22nd May 20234:30 pmRNSPosting of Annual Report and Notice of AGM
16th May 20237:00 amRNSFinal Results for the Year Ended 31 December 2022
9th May 202310:51 amRNSMine Site Incident
28th Apr 20237:00 amRNSQuarterly update to 31 March 2023
31st Jan 202311:05 amRNSSecond Price Monitoring Extn
31st Jan 202311:00 amRNSPrice Monitoring Extension
31st Jan 20237:00 amRNSQuarterly Update to 31 December 2022
9th Nov 20227:00 amRNSReceipt of Presidential Award
14th Oct 20227:00 amRNSQuarterly Update to 30 September 2022
14th Sep 20227:00 amRNSInterim Results
29th Jul 20228:56 amRNSReduction of Capital Effective
21st Jul 20227:00 amRNSUpdate on Reduction of Capital
20th Jul 20227:00 amRNSQuarterly Update to 30 June 2022
17th Jun 20223:26 pmRNSResult of AGM
16th May 20227:01 amRNSProposed Capital Reorganisation & Notice of AGM
16th May 20227:00 amRNSFinal Results for the Year Ended 31 December 2021
5th May 20227:00 amRNSAppointment of Non-Executive Director
25th Apr 20227:00 amRNSQuarterly update to 31 March 2022
14th Feb 20227:00 amRNSUpdated Mineral Resource and Ore Reserve Estimate
11th Feb 20227:00 amRNSInvestor Presentation
21st Jan 20227:00 amRNSQuarterly update to 31 December 2021
18th Oct 20217:00 amRNSQuarterly Update to 30 September 2021
20th Sep 20217:00 amRNSInterim Results for Six Months Ended 30 June 2021
1st Sep 20217:00 amRNSDirectorate Changes
27th Jul 202111:05 amRNSSecond Price Monitoring Extn
27th Jul 202111:00 amRNSPrice Monitoring Extension
27th Jul 20217:00 amRNSQUARTERLY UPDATE TO 30 JUNE 2021
1st Jul 20214:51 pmRNSHolding(s) in Company
30th Jun 20214:44 pmRNSResult of AGM
17th Jun 20212:00 pmRNSAnnual General Meeting Arrangements
7th Jun 202112:46 pmRNSPosting of Annual Report and Notice of AGM
25th May 20217:00 amRNSInvestor Presentation
21st May 20217:00 amRNSFinal Results for the year ended 31 December 2020
18th May 20217:00 amRNSUpdated Website, Presentation & Broker Research

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.