July 2018 Operations Update

Β 

Β 

Mosman Oil and Gas Limited (AIM: MSMN) the oil exploration, development and production company, is pleased to provide the following update to operations.

Β 

Strategy

Β 

Mosman's strategic objective continues to be that of identifying opportunities which will provide operating cash flow and further development upside, in conjunction with adding value to the Company's existing exploration permits. Presently short term focus is on developing the existing production assets in the USA to deliver production increases and cash flow.

Β 

Summary

Β 

Total Gross Production across all of Mosman's underlying acreage on a Total Project Basis was 12,260 boe over the 6 months to 30 June 2018 representing a 28% increase over the previous 6 months Total Project Production of 9,604 boe.

Β 

Net Production Attributable to Mosman increased to 4,417 boe for the six months ended 30 June 2018. This is a 35% increase over the Net Production of 3,274 boe for the previous six months ended 31 December 2017.

Β 

Sales Revenue attributable to Mosman was $534,500, a 191% increase over the previous six months reflecting Mosman's further investment into production assets, increases to production, and oil prices over the comparative period.

Β 

Production and sales are anticipated to continue strong growth due to rod replacements at Welch, the new ESP's at Arkoma, and the potential horizontal wells at Welch. Further details are outlined below and in the table at the end of this announcement.

Β 

Welch Permian Basin Project (Texas): 100% Working Interest and Operator

The property was acquired for both immediate production income and development potential. Oil Production for the six months ending June 2018 was 4,309 barrels (Net Attributable to Mosman: 3,303 barrels). This represents an increase of 39% over the previous six months.

Since June, three additional wells have now been repaired and restored to production (utilizing part of the recent placing funds). In addition, a recent resource Report was completed by Moyes & Co.

Β 

The development potential remains the drilling of horizontal wells that are expected to increase both Reserves and production. Mosman has commissioned a feasibility study to further define the project for an investment decision. Part of that process was the Report completed by Moyes & Co. Current work is to firm up the wells' design and cost estimates.

A final decision by the Board on a horizontal well is subject to completion of the Company's economic evaluation, a development plan, permitting, prevailing economic conditions and funding alternatives.

Currently, discussions are proceeding with the Texas Rail Road Commission to secure the well approvals. The feasibility remains on time and budget with an investment decision due later in 2018.

Arkoma Stacked Pay Project (Oklahoma): 27% Working Interest with options to increase to 33.3%

The property was acquired for both immediate production income and development potential. Oil Sales for the six months ending June 2018 was 6,434 barrels (Net Attributable to Mosman: 507 barrels). This represents an increase to Net Production Attributable to Mosman of 246% over the previous six months.

It is noted that Mosman increased it's participation from 10% to 27% throughout this recent six month period so the net share of production attributable to Mosman would have been higher had the full 27% ownership been maintained for the entire 6 months.

A recent resource Report was completed by Moyes & Co.

The development potential is large as the area has potential for additional wells to be drilled to produce from multiple zones. The Operator recently installed electric submersible pumps ("ESPs") in two wells to produce simultaneously from several zones.Β This was initially disrupted by weather events, and in July water injection issues. Following upgrade work to water injection facilities, these wells will be brought on production. It may take some time to establish steady flow rates.

Β 

From Mosman's perspective the results are also important to enable the investment decision which is due by the end of July 2018.

Β 

Strawn (Texas): 50% Working Interest and Operator

The property was acquired for production income.

Total project production (100%) at Strawn for the 6 months to 30 June 2018 was 1,519 barrels.

Net Production Attributable to Mosman for the six months ending June 2018 was 608 barrels. This represents an decrease of 11.5% when compared to the previous six months.

No further workovers are planned in the short term and staff and other costs continue to be streamlined to maximise cash generation. Selected repairs will however be completed to maintain production levels.

Amadeus Basin in the Northern Territory (NT) of Australia.

Mosman has two granted leases and one application in the Amadeus region.

Β 

EP 145

Β 

This permit is near several oil and gas producing fields and key infrastructure, including a gas pipeline connecting the gas fields to Alice Springs and Darwin, and a pipeline being built to connect to gas markets in Eastern Australia.

Β 

Newly reprocessed legacy seismic data has greatly improved the imaging of the subsurface. Significant salt diaprism has been interpreted and subsalt horizons and structures have been mapped with a high level of confidence. The reprocessed seismic indicates similarities with seismic that of the Dukas prospect that Santos Limited plan to drill early in 2019.

Β 

This new information includes indications of a salt diapir that may provide the sort of trapping mechanism found in the Gulf of Mexico. Notably, the sub-salt has been penetrated by two wells, Magee-1 and Mount Kitty-1 that tested over 5% helium as well as Hydrocarbons. Helium is worth 10-12 times the value of hydrocarbon gas.

Β 

Given the success of stage one of the reprocessing Mosman has extended the work to Stage Two, including reprocessing the 1991 seismic data. Results from Stage Two are expected in the third quarter.

Β 

EP156

Β 

Processing and evaluation of newly acquired proprietary high resolution aeromagnetic data survey supports the presence of complex anticlinal structures within the prospective Neoproterozoic stratigraphy. The final report is due shortly.

Β 

EP(A) 155

Β 

A stakeholders meeting with the indigenous parties has now been called.

Β 

New Zealand (NZ)

Β 

Work has commenced on well sites to conclude operations in New Zealand, including plug and abandonment of three wells. The cost of this work is expected to be less than the sale proceeds from the recent sale of freehold property, sale of surplus equipment and return of bonds.Β 

Β 

John W Barr, Chairman, said: "Β If production at existing projects is maintained, and we achieve the planned success at Welch and Arkoma, production from could see a further significant increase over current levels. The task now is to continue to develop Mosman to achieve that success."

Β 

Competent Person's Statement

The information contained in this announcement has been reviewed and approved by Andy Carroll, Technical Director for Mosman, who has over 35 years of relevant experience in the oil industry. Mr. Carroll is a member of the Society of Petroleum Engineers.

Β 

Market Abuse Regulation (MAR) Disclosure

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement.

Β 

Enquiries:

Β 

Mosman Oil & Gas Limited

John W Barr, Executive Chairman

Andy Carroll, Technical Director

jwbarr@mosmanoilandgas.com

acarroll@mosmanoilandgas.com

Β 

NOMAD and Broker

SP Angel Corporate Finance LLP

Stuart Gledhill / Richard Hail / Soltan Tagiev

+44 (0) 20 3470 0470

Β 

Gable Communications Limited

Justine James / John Bick

+44 (0) 20 7193 7463

mosman@gablecommunications.com

Β 

Updates on the Company's activities are regularly posted on its websiteΒ www.mosmanoilandgas.com

Β 

Production by Project

The below table is an unaudited summary of production by project for the financial period 1 July 2017 through 30 June 2018. The below figures are prepared by management using established industry practice.

Β 

6 Months to 31 December 2017

6 Months to 31 December 2017

Β Total Project Basis

Β Net Production Attributable to Mosman

Β Gross BOE

Β Net BOE

Strawn

1,716

686

Welch

3,108

2,383

Arkoma

4,781

206

Total BOE

9,604

3,274

Β 

6 Months to 30 June 2018

6 Months to 30 June 2018

Β Total Project Basis

Β Net Production Attributable to Mosman

Β Gross BOE

Β Net BOE

Strawn

1,519

608

Welch

4,309

3,303

Arkoma

6,434

507

Total BOE

12,262

4,417

Β 

Definitions

Sales

Reference to sales is boe that has actually been sold throughout the period

Net Sales

Gross sales less royalties owed to leaseholders

Gross Production

boe produced on the reference project throughout the period. Includes oil still held as inventory

Net Attributabe to Mosman

Β 

Gross production of a project representative of Mosman's ownership percentage of that project. In Welch this is 100% of production, in Strawn 50%, in Arkoma it is representative of Mosman's ownership % at the time of production (currently 27%) less amounts to leaseholders and royalty holders.

Total Project Basis

Refers to performance of Sales or Production on a 100% basis of the identified projects that Mosman has invested in.

Β 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
Β 
END
Β 
Β 
UPDLIFETDAIDLIT
Date   Source Headline
5th Aug 20197:00 amRNSSpudding of Stanley-3
31st Jul 20198:02 amRNSSix Month Production Update
24th Jul 201911:59 amRNSAustralian Exploration Update
15th Jul 20197:00 amRNSStanley-2 Initial Production
1st Jul 20197:00 amRNSSale of Strawn Production Facilities and Leases
27th Jun 201912:38 pmRNSStanley Project Update
25th Jun 20197:00 amRNSOperations Update
14th May 20197:00 amRNSChampion drilling, fundraising and Stanley update
8th May 20197:05 amRNSCorporate Presentation
8th May 20197:00 amRNSFarm-out of Champion Project
24th Apr 20199:00 amRNSProduction Update
18th Apr 20198:38 amRNSStanley Production Update
11th Apr 201910:03 amRNSStanley Project Update
1st Apr 20197:00 amRNSStanley-2 Drilling Update
28th Mar 201911:10 amRNSHalf-year Report
25th Mar 20199:16 amRNSStanley Project Update
19th Mar 20197:00 amRNSStanley-2 Drilling Update
14th Mar 201911:55 amRNSTechnical Presentation at AGES conference in NT
13th Mar 20198:43 amRNSRecompletion of Stanley-1
12th Mar 20194:40 pmRNSSecond Price Monitoring Extn
12th Mar 20194:35 pmRNSPrice Monitoring Extension
4th Mar 20199:53 amRNSStanley Update
12th Feb 201911:33 amRNSUpdate on Gem International Resources Inc
7th Feb 201910:51 amRNSIncreased Interest in Texas Production Lease
6th Feb 20197:00 amRNSProduction Update
7th Jan 20192:30 pmRNSStanley-2 well update
20th Dec 20189:49 amRNSResult of AGM
11th Dec 201812:41 pmRNSSpudding Stanley-2 and Increased Working Interest
5th Dec 20182:24 pmRNSDirectors' Subscription
30th Nov 20187:00 amRNSStanley-2 Drilling Update
28th Nov 201812:54 pmRNSNotice of AGM
28th Nov 201812:50 pmRNSFinal Results
13th Nov 20188:57 amRNSStanley-1 Well Test Results
9th Nov 20188:38 amRNSPlanned drilling, operational update & fundraising
29th Oct 201811:53 amRNSTexas Projects Update
18th Oct 20188:03 amRNSWeather causes delays in Texas
18th Oct 20187:58 amRNSStanley-1 Production and Stanley-2 Update
4th Oct 20187:52 amRNSStanley First Sales and Planning of Stanley-2
28th Sep 20181:16 pmRNSArkoma Project Update
24th Sep 20187:00 amRNSAcquisitions and Baja Strategic Alliance Update
18th Sep 201812:58 pmRNSArkoma Project Update
17th Sep 20188:09 amRNSHydrocarbon Production and Sales at Stanley-1
4th Sep 20187:00 amRNSIncreased Production & new Corporate Presentation
2nd Aug 20188:11 amRNSJoint Broker Appointment
1st Aug 20187:00 amRNSSuccessful drilling at Stanley completed
30th Jul 20187:07 amRNSProduction almost doubles at Welch Project
25th Jul 20187:00 amRNSArkoma: 27% WI with option to increase to 33.3%
20th Jul 20187:32 amRNSStanley Drilling Project Update
17th Jul 201810:01 amRNSJuly 2018 Operations Update
2nd Jul 20187:00 amRNSArkoma Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.