Projects Update

13 Jul 2009 07:00

RNS Number : 5110V
Coal of Africa Limited
13 July 2009
 



ANNOUNCEMENT 13 JULY 2009

COAL PROJECTS UPDATE 

Coal of Africa Limited ('CoAL' or the 'Company'), the AIM/ASX/JSE listed coal mining and development company operating in South Africa (ticker: CZA)provides the following update on the Company's Mooiplaats thermal coal project in the Mpumalanga Province, ("Mooiplaats Project"), Vele coking coal project, near Musina in the Limpopo Province ("Vele Project") and the Makhado coking coal project, also in the Limpopo Province ("Makhado Project").

MOOIPLAATS

Following the announcement on 9 June 2009, the Company confirms that a revised mining layout for the project has been finalised following an extensive reassessment of the mine plan and geological conditions at Mooiplaats. Depending on the rate of development, export quality thermal coal is now expected to be reached in November 2009 at the earliest, or the first quarter of 2010 at the latest. Other than this, all other aspects of the original mine planning and scheduling remain the same.  Importantly, there has been no material amendment to either the anticipated tonnage schedules or the project's Life of Mine. Forecast run of mine ("ROM") production for the next 5 years is a follows:

Calendar Year

2010

2011

2012

2013

2014

ROM Production

1.7m

2.7m

3.1m

3.4m

3.2m

Operations at the Mooiplaats Project are continuing well, with mid volatile "lean" coal currently being produced at a rate of 30,000 ROM tonnes per month, whilst establishing access into the export thermal coal resource. The Company is encouraged by ongoing discussions with a number of interested parties specifically looking for mid volatile lean coal. In the event one or more of these discussions materialises into a formal off-take agreement, production of the lean coal can quickly be ramped up to over 80,000 ROM tonnes per month.   

As previously announced, the Company has already reached agreement on terms and conditions for the off-take of the export quality thermal coal to be produced at Mooiplaats.

Furthermore, discussions are proceeding with third parties requiring coal processing facilities as well as rail and port access whilst build-up at Mooiplaats continues.

VELE 

The Company is to develop its Vele Project in two phases.  Phase 1 will initially comprise the establishment of a modular coal treatment plant, which will have the ability to deliver approximately 1 million saleable tonnes (yield dependant) of coking coal per annum, expected to be delivered to ArcelorMittal for use at it steelworks in Vanderbijl Park. The capacity of the modular coal treatment plant can be doubled should ArcelorMittal seek to increase their off-take from Vele. The Letter of Intent signed with ArcelorMittal in April 2008 ("Mittal LOI") provides for potential off-take from the Company's coking coal properties of 2.5 - 5 mtpa. Phase 2 will deliver the planned full capacity of 5 million tonnes of coking coal per annum.

The Company is ready to launch Phase 1 immediately upon the granting of a New Order Mining Right ("NOMR"), currently under review by the South African Department of Minerals and Energy ("DME"), and approval is expected by the end of Q3 2009. A significant amount of preparation has already been completed for Phase 1, and capital expenditure committed to the modular plant, which will shorten the production lead time. Wet commissioning of the modular plant is scheduled for August this year. The timing of the Phase 2 expansion to deliver 5 million tonnes per annum of saleable coking coal will be dictated by market conditions.

The total capital expenditure required to complete Phase 1 is estimated at R350 million. To double the Phase 1 capacity is estimated to cost a further R200m and an additional R2.65 billion is required for Phase 2 (5 mtpa).  The Mittal LOI provides for a free on rail ("FOR") delivery in return for a free on board ("FOB") indexed price, delivering a significantly better margin that what would otherwise be enjoyed through exporting the coal. Initial mining will be by opencast methods, which is also contributing to lower initial mining establishment costs.

CoAL once again confirms that the Company has sufficient cash resources available to complete the development of the Mooiplaats Project, as well as the establishment of Phase 1 of the Vele Project.

MAKHADO

CoAL is progressing with planning of its Makhado Project.  Analysis of the coal resource quality is continuing, post the completion of additional large diameter bulk sample drilling in Q2 2009.

The full scale project plan is based on the production of 5 million tonnes of coking coal per annum. A similar phased approach to that at Vele utilising a modular coal processing plant may also be applied at Makhado, which will lower initial capital requirements and enable CoAL to self-fund the build up into a full capacity mine.  Current indications are that a modular plant based first phase, with a capacity of 1 million saleable tonnes (yield dependent) of coking per annum, will require a capital investment in the order of R500 million, compared to R2.7 billion required for the full-scale mine development. Market conditions will determine whether the development of Makhado will be based on full scale production of 5mtpa or a similar phased approach as taken at Vele.

CoAL has prepared the documentation for the Makhado Project mining right application, which is planned for submission to the DME once Section 11 approval has been obtained for the Farm swap with Rio Tinto This is expected H2 2009 as previously communicated. 

CoAL will report further details in its next quarterly report scheduled for release by the end of July 2009.

Resource Estimation: 

Resource estimations have been compiled by Mr John Sparrow (Member of the South African Council of Natural Science Professions SACNASP) 400109/03, an independent geological and technical consultant with 26 years experience in the Southern African and Australian regions. Mr Sparrow has sufficient experience relevant to the assessment of this style of mineralization to qualify as a Competent Person as defined in the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves - the JORC Code - and has compiled a number of Competent Person's reports for various organizations for the JSE, ASX and TSE. Mr Sparrow consents to the inclusion of the information in this report in the form and context in which it appears.

AUTHORISED BY:

Simon Farrell 

Managing Director

For more information contact:

Simon Farrell, Managing Director  CZA  +61 417 985 383 or  +61 8 9322 6776

Peter Bacchus/ Alastair Cochran Morgan Stanley +44(0) 20 7425 8000

Simon Edwards/ Chris Sim Evolution Securities +44(0) 20 7071 4300

Jos Simson/ Leesa Peters Conduit PR +44(0) 20 7429 6603

About CoAL:

Coal of Africa Limited ("CoAL") is primarily focused on the acquisition, exploration and development of thermal and metallurgical coal projects. The Company's key projects, along with its leading metals processing company NiMag Group (Pty) Ltd are in South Africa. The Company was incorporated in Western Australia and listed in 1980. Since 2005, the Company has also listed on both the AIM and JSE markets, allowing further growth in the Company's coal assets.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSFAFISSUSESW
Date   Source Headline
6th Jul 20202:00 pmRNSRESTRUCTURING OF THE CURRENT IDC LOAN
18th May 202010:33 amRNSMARKET UPDATE
5th May 20207:00 amRNSRECOMMENCEMENT OF COAL PRODUCTION
24th Apr 20207:22 amRNSAppendix 5B
24th Apr 20207:21 amRNSReport for the Quarter Ended 31 March 2020
26th Mar 20202:22 pmRNSLOCKDOWN AND SUSPENSION OF COAL PRODUCTION
24th Mar 20208:53 amRNSSOUTH AFRICA DECLARES 21 DAY LOCK-DOWN
13th Mar 20208:00 amRNSInterim Financial Report
13th Mar 20208:00 amRNSResults for the 6 Months Ending December 2019
13th Feb 20202:18 pmRNSISSUE OF SHARES
10th Feb 20209:51 amRNSHOLDINGS IN COMPANY
10th Feb 20209:46 amRNSAPPOINTMENT OF ACTING CHIEF EXECUTIVE OFFICER
31st Jan 20209:45 amRNSResignation of Chief Executive Officer
28th Jan 20207:00 amRNSAppendix 5B
28th Jan 20207:00 amRNSReport For The Quarter Ended 31 December 2019
2nd Jan 20207:00 amRNSDirector Resignation
18th Dec 20197:10 amRNSGrant of Performance Rights to Executive Directors
18th Dec 20197:09 amRNSAppendix 3B
3rd Dec 201912:00 pmRNSDirector Retirement
25th Nov 20197:00 amRNSFinal Director's Interest Notice
22nd Nov 201910:35 amRNSResult of AGM
5th Nov 20197:00 amRNSGeneraal Mining Right Granted
31st Oct 20197:01 amRNSAppendix 5B
31st Oct 20197:00 amRNSReport for the Quarter Ended 30 September 2019
23rd Oct 20192:30 pmRNSDespatch of Annual Report and Notice of AGM
30th Sep 20198:05 amRNSANNUAL CONSOLIDATED FINANCIAL STATEMENTS
30th Sep 20198:00 amRNSFull Year Results
30th Jul 20197:01 amRNSAppendix 5B
30th Jul 20197:00 amRNSReport for the Quarter Ended 30 June 2019
15th Jul 20197:00 amRNSDebt Funding Secured for Phase 1 of Makhado
21st Jun 20197:00 amRNSAgreement Signed with Haohua Energy International
19th Jun 20197:00 amRNSMakhado Phase 1 Hard Coking Coal Off-Take Signed
29th Apr 20197:01 amRNSAppendix 5B
29th Apr 20197:00 amRNSReport for the Quarter Ended 31 March 2019
17th Apr 20197:00 amRNSMakhado EA Appeal Dismissed
16th Apr 20197:00 amRNSMakhado Thermal Coal Off-Take Signed
29th Mar 20197:00 amRNSAppointment Of Independent Non-Executive Director
27th Mar 20197:00 amRNSAdditional Makhado Project Phase 1 Information
14th Mar 20197:01 amRNSPhase 1 of the Makhado Project Approved
14th Mar 20197:00 amRNSInterim Financial Report
14th Mar 20197:00 amRNSResults for the 6 Months Ending December 2018
25th Jan 20197:01 amRNSAppendix 5B
25th Jan 20197:00 amRNSReport For The Quarter Ended 31 December 2018
14th Jan 20197:00 amRNSPurchase Of Key Makhado Surface Rights Completed
14th Dec 20187:00 amRNSUpdated dealing code/trading policy
12th Dec 20187:00 amRNSGrant of Performance Rights to Executive Directors
11th Dec 20187:05 amRNSChapudi Project - Mining Right Granted
23rd Nov 201810:56 amRNSResults of Annual General Meeting
21st Nov 20184:40 pmRNSSecond Price Monitoring Extn
21st Nov 20184:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.