1st Quarter Operating Update

9 May 2019 07:00

RNS Number : 4432Y
Sibanye-Stillwater
09 May 2019
 

 

 

 

SIBANYE-STILLWATER: OPERATING UPDATE FOR THE QUARTER ENDED 31 MARCH 2019

 

 

Johannesburg, 9 May 2019: Sibanye Gold Limited trading as Sibanye-Stillwater (Sibanye-Stillwater or the Group) (JSE: SGL & NYSE: SBGL) is pleased to present an operating update for the quarter ended 31 March 2019. Financial results are only provided on a six-monthly basis.

 

SALIENT FEATURES FOR THE QUARTER ENDED 31 MARCH 2019

· Maintained solid H2 2018 safety performance - numerous historic safety milestones achieved

· The transition to a Toll processing arrangement at Rustenburg adds both strategic and commercial value - direct access to end users and margin enhancing relative to the PoC arrangement

· The improved financial performance from the combined PGM operations more than offset strike related losses at SA gold operations

Adjusted EBITDA of R1,819 million (excl. Rustenburg) from the combined PGM operations resulted in positive Group adjusted EBITDA of R176 million

Including Rustenburg, pro-forma adjusted EBITDA from the combined PGM operations would have been R2,574 million

· Strike at SA gold operations brought to a successful conclusion post quarter end

· Section 189 restructuring process at SA gold operations well advance and expected conclusion by mid May 2019

· Five year wage agreement reached for the Stillwater mine and Columbus metallurgical complex post quarter end

· Strategic balance sheet management through equity placing and gold prepayment

Appropriately positioned with R10 billion available facilities and reduced leverage

Net debt: adjusted EBITDA at 3.0x at 31 March 2019- reduced to 2.54x on a pro-forma basis (excl. Rustenburg)

US Dollar

SA Rand

Quarter ended

Quarter ended

Mar 2018

Dec 2018

Mar 2019

KEY STATISTICS

Mar 2019

Dec 2018

Mar 2018

SOUTHERN AFRICA (SA) OPERATIONS

PGM operations

 286,194

 301,279

 263,508

oz

4E PGM1 production

kg

 8,196

 9,371

 8,902

 1,073

 1,078

 1,221

US$/4Eoz

Average basket price

R/4Eoz

 17,104

 15,427

 12,839

 21.6

 82.9

 25.2

US$m

Adjusted EBITDA2

Rm

 353.0

 1,185.8

 258.3

 9

 27

 21

%

Adjusted EBITDA margin2

%

 21

 27

 9

 851

 739

 909

US$/4Eoz

All-in sustaining cost3

R/4Eoz

 12,741

 10,576

 10,186

Gold operations4

 291,500

 270,025

 143,278

oz

Gold production

kg

 4,456

 8,399

 9,068

 1,320

 1,221

 1,306

US$/oz

Average gold price

R/kg

 588,040

 561,788

 507,719

 31.3

 7.1

 (115.0)

US$m

Adjusted EBITDA2

Rm

 (1,611.4)

 101.4

 374.2

 8

 2

 (63)

%

Adjusted EBITDA margin2

%

 (63)

2

8

 1,336

 1,328

 2,030

US$/oz

All-in sustaining cost3

R/kg

 914,590

 610,883

 513,829

Jan 1900

UNITED STATES (US) OPERATIONS

PGM operations5

 148,549

 159,471

 130,899

oz

2E PGM1 production

kg

 4,071

 4,960

 4,620

 191,404

 181,761

 201,289

oz

PGM recycling5

kg

 6,261

 5,653

 5,953

 1,027

 1,076

 1,305

US$/2Eoz

Average basket price

R/2Eoz

 18,283

 15,394

 12,289

 78.8

 110.4

 104.6

US$m

Adjusted EBITDA2

Rm

 1,465.9

 1,578.9

 942.4

 26

 31

 27

%

Adjusted EBITDA margin2

%

 27

 31

 26

 632

 642

 833

US$/2Eoz

All-in sustaining cost3

R/2Eoz

 11,671

 9,180

 7,559

GROUP

 131.7

 198.5

 12.5

US$m

Adjusted EBITDA2

Rm

 175.8

 2,839.5

 1,574.9

 11.96

 14.31

 14.01

R/US$

Average exchange rate

1 The Platinum Group Metals (PGM) production from the SA operations (including attributable production from Mimosa) is primarily platinum, palladium, rhodium and gold, referred to as 4E (3PGM+Au). The US operations primrily produce palladium and platinum, referred to as 2E (2PGM)

2 The Group reports adjusted earnings before interest, taxes, depreciation and amortisation (EBITDA) based on the formula included in the facility agreements for compliance with the debt covenant formula. Adjusted EBITDA may not be comparable to similarly titled measures of other companies. Adjusted EBITDA is not a measure of performance under IFRS and should be considered in addition to and not as a substitute for, other measures of financial performance and liquidity

3 See "salient features and cost benchmarks for the quarters" for the definition of All-in sustaining cost

4 The SA gold operations' results for the quarters ended 31 March 2019 and 31 December 2018 include DRDGOLD Limited (DRDGOLD)

5 The US PGM operations' underground production is converted to metric tonnes and kilograms, and performance is translated to SA rand. In addition to the US PGM operations' underground production, the operation treats recycling material which is excluded from the 2E PGM production, average basket price and All-in sustaining cost statistics shown. PGM recycling represents palladium, platinum, and rhodium ounces fed to the furnace

Stock data for the quarter ended 31 March 2019

JSE Limited - (SGL)

Number of shares in issue

Price range per ordinary share

R9.66 to R17.51

- at 31 March 2019

 2,271,760,491

Average daily volume

12,980,355

- weighted average

 2,266,384,087

NYSE - (SBGL); one ADR represents four ordinary shares

Free Float

80%

Price range per ADR

US$2.73 to US$4.83

Bloomberg/Reuters

SGLS/SGLJ.J

Average daily volume

4,583,116

 

 

 

OVERVIEW AND UPDATE FOR THE QUARTER ENDED 31 MARCH 2019

Q1 2019 was an important period for Sibanye-Stillwater, with the Group successfully navigating complex operational and financial challenges and achieving some significant milestones which, we believe, have positioned us to sustainably benefit from higher prevailing precious metal prices and to better withstand any challenges that may occur during the year.

The notable improvement in safety across during H2 2018 was maintained in Q1 2019, with the Group achieving improvements in most safety measures across the operations and achieving a record seven million fatality free shifts on 7 March 2019. This was sadly curtailed by a fatal fall of ground incident at the SA PGM operations on 20 March 2019. The SA gold operations recorded a second successive quarter without any fatalities and continued to improve on other safety measures. Safe production continues to be the highest priority across the Group and we remain focused on maintaining and improving on our safe production performance at all of our operations.

The Association of Mineworkers and Construction Union (AMCU) strike which began at the SA gold operations on 21 November 2018 continued throughout Q1 2019, concluding after almost five months on 17 April 2019. The operational and financial impact of this extended strike at the SA gold operations, was mitigated by another solid operational performance from the SA PGM operations enhanced by significantly higher palladium and rhodium prices, which, combined with a 17% depreciation in the average rand:dollar exchange rate, boosted earnings and cash flow from both the SA and US PGM operations. A slower than anticipated start to the year at the US PGM underground operations and temporary flexibility constraints resulted in lower than anticipated mined underground production which resulted in elevated unit costs for this reporting period. The commissioning of the second electric furnace (EF2), enabled an increase in recycling processing volumes and a reduction in metal inventory, resulting in higher sales volumes .

Average unit commodity prices were higher across the Group operations for Q1 2019 relative to Q1 2018. The 27% increase in the average 2E PGM basket price to US$1,305/oz in Q1 2019, resulted in adjusted EBITDA from the US PGM operations increasing by 33% to US$105 million. In rand terms, this amounted to R1,466 million, a 56% year-on-year increase.

The gearing of the SA PGM operations to the higher rand PGM basket price was similarly evident, with the 33% higher average 4E basket price of R17,104/oz significantly boosting earnings and cash flow. Reported adjusted EBITDA of R353 million from the SA PGM operations was 38% higher than for Q1 2018. This result was achieved despite the change in the contractual processing arrangement with Anglo American Platinum from a Purchase of Concentrate (PoC) to Toll processing arrangement (discussed in more detail in the operations section below). From an accounting perspective this contractual change resulted in zero revenue recognition of 4E production from the Rustenburg operations. Cash flow due to the contractual change was not affected and on a normalised basis, the pro-forma adjusted EBITDA (including Rustenburg), would have been R1,108 million (US$79 million), which is a 330% increase relative to Q1 2018. Attributable adjusted EBITDA from Mimosa, of approximately R198 million (US$14 million) generated during Q1 2019 is equity accounted and also excluded from Group adjusted EBITDA.

The combined adjusted EBITDA from the PGM operations (US and SA) of R1,819 million (US$130 million) for Q1 2019, more than offset the R1,661 million adjusted EBITDA loss from the SA gold operations due to the strike action, resulting in Group adjusted EBITDA of R176 million for Q1 2019. Including the deferred adjusted EBITDA from the Rustenburg operations, normalised adjusted EBITDA from the combined PGM operations would have been 131% higher at R2,574 million (US$184 million) with normalised Group adjusted EBITDA higher at R931 million (US$66 million). We remain focused on deleveraging the Group balance sheet with net debt to adjusted EBITDA at the end of Q1 2019 of 3.00x, was below the Group's 3.5x covenant ceiling for 2019. Following the 5% share placing of approximately R1,700 million (US$120 million) and gold prepayment (announced on 10 and 11 April 2019) of approximately R1,750 million (US$125 million), pro-forma net debt to adjusted EBITDA would be approximately 2.54x.

Whilst the strike action and the gradual build-up post the strike will continue to negatively impact the SA gold operations during Q2 2019, unit revenues for both the gold and PGM operations are expected to exceed those in the comparative period in 2018 and further deleveraging is anticipated during the course of the year.

Industrial relations

SA gold operations

On 17 April 2019, the five month long strike, which was called by AMCU at our SA gold operations on 21 November 2018, was resolved. Our ongoing attempts to end the strike both through legal means and through ongoing engagement with AMCU, were frustrated by ongoing legal challenges and significant intimidation and violence at the operations and in surrounding communities. Despite these vexing actions, we remained resolute and committed to honouring the collective agreement we had reached with the National Union of Mineworkers (the NUM), Solidarity and UASA in respect of wages and conditions of service for the period 1 July 2018 to 30 June 2021. It was therefore pleasing to ultimately resolve the strike in a sustainable manner which did not undermine our values and other stakeholders.

Under the terms of the agreement reached with AMCU, its members will be subject to the same conditions of the original collective wage agreement reached with the other three unions on 15 November 2018. Furthermore, the union committed to concluding a peace pact with the company and the other unions within 30 days as well as engaging in future on a constructive basis across the entire South African segment. .

In recognition of the difficulties experienced by employees during the strike, the Group has agreed to an ex-gratia 'return to work' payment of R4,000 for all employees (not just AMCU members) at the SA gold operations. In addition the Company has offered a cash advance to AMCU members up to a maximum of R5,000 which will be repayable over a 12- month period. Debt consolidation and counselling as part of the existing 'Care for iMali' program will also be freely available. Furthermore, the Company waived its rights to reclaim costs incurred on behalf of employees during the strike, including contributions made to medical aid and pension/provident funds, accommodation and meal costs.

SA PGM operations

The PGM sector wage negotiations will commence in the next few months at the Rustenburg operations, with the three year Kroondal wage agreement up for renewal only in July 2020.

US PGM operations

Wage negotiations with the United Steelworkers Union at the Stillwater mine and Columbus metallurgical complex were successfully concluded during April 2019. The new five-year agreement is on similar terms to the previous agreement with minor revisions, and pay increases broadly in line with other industrial and mining operations. The four-year contract for East Boulder mine, which was agreed in December 2015, remains in place until December 2020.

Safe PRODUCTION

It is extremely pleasing to note that there have been no fatalities at the SA gold operations since August 2018, with a significant milestone of four million fatality free shifts achieved on 8 April 2019. This is a record for these operations.

A safe build up to normalised production levels following the extended strike will be the primary focus for the SA gold operations during Q2 2019. Ensuring that the work places, many of which have been dormant for almost five months, are safe and conducive to mining and re-integrating the teams will require a measured and gradual approach, with normalised production rates expected to be achieved during Q3 2019.

The Total Reportable Injury Frequency Rate (TRIFR) (measured per million hours) for the US PGM operations of 16.0 for Q1 2019 improved from 17.8 for Q1 2018. There was a notable improvement in the safety performance during the quarter, which started poorly with 60% of the reportable injuries occurring in January 2019.

A fall of ground incident at the SA PGM operations on 20 March 2019 tragically claimed the life of Madodana Manzenze, a rock drill operator at Thembelani shaft in Rustenburg. The Board and management of Sibanye-Stillwater extend their sincere condolences to the family and friends of Mr Manzenze. Prior to this incident, the SA PGM operations achieved 4.4 million fatality free shifts over a six month period.

OPERATING REVIEW

US PGM operations

Mined PGM production from the underground operations of 130,899 2Eoz for Q1 2019, was 12% lower than the comparable period in 2018 primarily due to flexibility constraints caused by sequencing challenges at both the Stillwater and East Boulder mines. This temporarily restricted access to higher grade production stopes. Whilst total operating costs and capital expenditure were in line with expectations, lower production resulted in elevated All-in Sustaining Cost (AISC) per unit for the quarter. Production is expected to ramp up over the balance of the year and annual production and cost guidance remains unchanged.

Following the re-commissioning of EF2 in February 2019, the Columbus Metallurgical Complex, increased throughput of mined and recycled material resulting in a record throughput for the quarter. During the period the recycling operation fed an average of 25.6 tonnes of material per day (tpd), enabling a reduction in metal inventory of approximately 32,000oz during the quarter.

Tax changes

The US PGM operations renegotiated its refining and certain sales agreements during Q1 2019, resulting in the reversal of the Group deferred tax charge of R1,545 million (US$108 million), recognised in December 2018. The 2019 effective combined federal and state cash tax rate for the US operations/segment are expected to be between 5 and 10%. The change of tax is a result of sales moving to a different tax jurisdiction.

SA PGM operations

The financial implications of the transition from a PoC to a Toll processing arrangement with Anglo American Platinum effective from 1 January 2019 were discussed in detail in the operating and financial results for the six-months and year-ended 31 December 2018, which were released on 21 February 2019.

In terms of the Toll arrangement, Sibanye-Stillwater pays an agreed toll fee to Anglo American Platinum to smelt and refine concentrate from the Rustenburg operations, but retains ownership of the refined metal produced. From a financial reporting perspective, Sibanye-Stillwater will receive and recognise all the recovered metal at the full average 4E PGM basket price once sold and no longer reflect a discount in its revenue, though costs and unit costs will be higher than under the PoC arrangement, reflecting the additional tolling costs.

At the current spot 4E PGM basket price, the net financial impact of this contractual change is positive, with the increased revenue more than offsetting the additional toll cost and as a result is beneficial both commercially and strategically. The change in the arrangement however results in a delay in the recognition of 4E PGM revenue, due to the point of sale being extended to the end of the processing pipeline, which resulted in no 4E PGM revenue or adjusted EBITDA being recognised from the Rustenburg operations in Q1 2019 (as discussed in the introduction).

Attributable 4E PGM production from the SA PGM operations (including Mimosa) of 263,508 4Eoz and AISC (excluding Mimosa) of R12,741/4Eoz (US$909/4Eoz) are in line with annual guidance. Production guidance for 2019 was lower relative to 2018 due to a reduction in lower grade surface material processed, which is uneconomical under the toll arrangement. In order to further optimise margins by managing tolling costs and revenue, a revised mass pull strategy was implemented at Rustenburg to reduce the volume of underground concentrate sent for processing (causing a slight decline in recoveries), with processing of lower grade surface material also significantly reduced. Kroondal continued its strong performance, with production marginally higher and AISC 4% higher at R10,916/4Eoz, reflecting a real reduction in unit costs.

Q1 2019 chrome sales of 199,343 tonnes were significantly higher than the 94,140 tonnes in Q1 2018 due to a greater availability of cargo vessels relative to early 2018. Chrome revenue of R304 million for Q1 2019 was therefore higher than the Q1 2018 chrome revenue of R117 million despite lower chrome prices in Q1 2019.

SA gold operations

Total gold production from the SA gold operations for Q1 2019 of 4,456 kg (143,278oz), includes 1,130kg (36,330oz) of production from DRDGOLD. Like-for-like, production from the SA gold operations, excluding DRDGOLD, declined 63% to 3,326kg (106,948oz) for Q1 2019 quarter compared with Q1 2018, reflecting the impact of the AMCU industrial action.

Implementation of strike mitigation plans at the SA gold operations and the "no work no pay principle", resulted in a significant reduction in operating costs in absolute terms during the quarter. Unit costs were however negatively affected by the lower production volumes, resulting in AISC (excluding DRDGOLD) of R1,002,350/kg (US$2,225/oz), significantly higher than expected ASIC of around R550,000/kg, at more normalized production levels.

Striking employees began to report for work at the SA gold operations from 24 April 2019, following the conclusion of the five month AMCU industrial action on 17 April 2019. As a result of the extended period that large sections of the SA gold operations stood dormant during the strike and in order to ensure the safety of employees, the buildup in production will be measured and gradual, with normalised production rates only anticipated during Q3 2019. A full review of all the workplaces is currently underway and following any necessary re-planning, production guidance will be provided to the market.

Section 189 consultations

On 14 February 2019 notice was given to relevant stakeholders regarding the possible restructuring of the SA gold operations, in terms of Section 189A (Section 189A) of the Labour Relations Act, 66 of 1995 (LRA and associated services) (S189).

Despite an attempt by AMCU to interdict the S189 process, consultations proceeded and the process is expected to be concluded in mid May 2019. Subject to the outcome of the S189 process, approximately 5,870 employees and 800 contractors may be directly impacted. The outcome of the S189 consultation process will be communicated to all stakeholders once concluded.

CORPORATE ACTION

The proposed Lonmin acquisition

On 25 April 2019, it was announced that the Boards of Sibanye-Stillwater and Lonmin had reached agreement on the terms of an increased recommended all-share offer to be made by Sibanye-Stillwater for the entire issued and to be issued ordinary share capital of Lonmin (the Increased Offer). Under the terms of the Increased Offer, Lonmin shareholders will be entitled to receive one new Sibanye-Stillwater share for each Lonmin share that they hold (the Revised Exchange Ratio). The Increased Offer is proposed to be effected by means of a UK scheme of arrangement (the Scheme) and remains subject to a number of conditions, including the relevant approvals of Lonmin shareholders and Sibanye-Stillwater shareholders and of the High Court of Justice of England & Wales.

On 25 April, Sibanye-Stillwater advised that a circular (Circular) containing, inter alia, an ordinary resolution regarding the issuance and allotment of shares as the consideration payable by Sibanye-Stillwater to Lonmin shareholders in respect of the Increased Offer (Ordinary Resolution), a notice convening the general meeting (General Meeting) and a form of proxy, had been posted to Sibanye-Stillwater Shareholders.

The Circular is available, subject to certain restrictions relating to persons in certain restricted jurisdictions, on Sibanye-Stillwater's website at www.sibanyestillwater.com/investors/transactions/lonmin.

The outcome from the Competition Appeal Court of South Africa, which was heard on 2 April 2019, is expected to be provided in due course.

The General Meeting of Shareholders will be held at the Sibanye-Stillwater Academy, Rietkloof 349, Glenharvie, 1786, South Africa, on Tuesday, 28 May 2019 at 08:30 a.m. (South African time), immediately before the Sibanye-Stillwater annual general meeting, to consider and, if deemed fit, pass, with or without amendment, the Ordinary Resolution set out in the Circular. Sibanye-Stillwater also notes that a circular in relation to the Increased Offer and the Scheme (the Lonmin Scheme Circular) was published by Lonmin on 25 April 2019 and is available, subject to certain restrictions relating to persons in certain restricted jurisdictions, on Lonmin's website at www.lonmin.com/investors/sibanyestillwater-offer and on Sibanye-Stillwater's website at the address noted above.

Share placing and gold prepayment

On 9 April 2019 the Group announced that it would be raising equity capital through a non pre-emptive cash placing of new Sibanye-Stillwater shares through an accelerated book build process with new and existing institutional investors. On 15 April 2019, Sibanye-Stillwater announced that a total of 108,932,356 new ordinary no par value shares, representing approximately 5% of Sibanye-Stillwater's then in issue ordinary share capital, had been placed with new and existing institutional investors. The cash placing closed at a price of R15.50 per share to raise gross proceeds of approximately ZAR1,700 million (US$120 million). The new shares were admitted to listing on the Main Board of the Johannesburg Stock Exchange on 15 April 2019. On 11 April 2019, it was further announced that US$125 million (approximately R1,750 million) had been raised through a forward gold sale arrangement (gold prepayment) in terms of which, 105,906oz (3,294kg) of gold would be delivered during Q4 2019, subject to a floor price of US$1,200/oz and a cap price of US$1,323/oz.

The equity raise and the gold prepay significantly enhanced the Group balance sheet flexibility and liquidity position, providing the Company with approximately R10 billion (US$700 million) of undrawn available facilities.

OUTLOOK

Mined 2E PGM production guidance from the US PGM operations for 2019 of between 645,000oz and 675,000oz and AISC guidance of between US$690/2Eoz and US$730/2Eoz remains unchanged. Total capital expenditure for the year is guided at between US$235 million and US$245 million for the year. Approximately half of this anticipated spend is growth capital in nature, including expenditure on the Fill the mill project.

4E PGM production from the SA PGM operations for 2019 is unchanged at between 1,000,000oz and 1,100,000oz with AISC between R12,500/4Eoz and R13,200/4Eoz (US$922/4Eoz and US$974/4Eoz), reflecting the transition to the Toll processing arrangement. Capital expenditure is forecast at R1,400 million (US$103 million), which includes approximately R230 million (US$17 million) of project capital. The dollar costs are based on an average exchange rate of R13.55/US$.

Guidance for the SA gold operations will be provided once we have sufficient clarity of the production build up.

Precious metals prices remain significantly elevated and at current spot prices further deleveraging towards an anticipated target of 1.8x net debt to adjusted EBITDA is expected by year-end.

 

Neal Froneman

Chief Executive Officer

 

SALIENT FEATURES AND COST BENCHMARKS FOR THE QUARTERS ENDED 31 MARCH 2019, 31 DECEMBER 2018 AND 31 MARCH 2018

SA and US PGM operations

GROUP

SA OPERATIONS

US OPERATIONS

Total SA and US PGM operations

Total SA PGM

Kroondal

Plat Mile

Rustenburg

Mimosa

Total US PGMStillwater

Attributable

Total

Under-ground

Surface

Attributable

Surface

Under-ground

Surface

Attributable

Under- ground1

Production

Tonnes milled/treated

000't

Mar 2019

 6,047

 5,725

 2,883

 2,842

 877

 1,820

 1,667

 1,022

 339

 322

Dec 2018

 7,001

 6,639

 3,147

 3,492

 1,030

 2,077

 1,764

 1,415

 353

 362

Mar 2018

 6,128

 5,803

 2,890

 2,913

 874

 1,678

 1,678

 1,235

 338

 325

Plant head grade

g/t

Mar 2019

 2.67

 2.05

 3.19

 0.89

 2.48

 0.72

 3.49

 1.21

 3.56

 13.76

Dec 2018

 2.68

 2.02

 3.26

 0.90

 2.53

 0.65

 3.62

 1.27

 3.59

 14.81

Mar 2018

 2.80

 2.09

 3.30

 0.89

 2.47

 0.58

 3.68

 1.31

 3.56

 15.52

Plant recoveries

%

Mar 2019

 75.93

 69.82

 82.83

 22.64

 82.89

 11.65

 84.32

 34.24

 75.53

 91.80

Dec 2018

 76.38

 69.92

 83.91

 24.38

 83.24

 11.53

 85.50

 34.05

 77.27

 91.89

Mar 2018

 78.74

 73.51

 84.94

 31.41

 81.92

 11.94

 87.32

 43.09

 78.15

 91.38

Yield

g/t

Mar 2019

 2.03

 1.43

 2.64

 0.20

 2.05

 0.08

 2.95

 0.41

 2.69

 12.64

Dec 2018

 2.05

 1.41

 2.73

 0.22

 2.10

 0.08

 3.09

 0.43

 2.77

 13.70

Mar 2018

 2.21

 1.53

 2.80

 0.28

 2.02

 0.07

 3.21

 0.56

 2.77

 14.22

PGM production2

4Eoz - 2Eoz

Mar 2019

 394,407

 263,508

 245,041

 18,467

 57,823

 4,878

 157,924

 13,589

 29,294

 130,899

Dec 2018

 460,750

 301,279

 276,590

 24,690

 69,666

 5,009

 175,473

 19,681

 31,451

 159,471

Mar 2018

 434,743

 286,194

 260,069

 26,125

 56,764

 3,723

 173,176

 22,402

 30,129

 148,549

PGM sold

4Eoz - 2Eoz

Mar 2019

 219,449

 91,995

 87,117

 4,878

 57,823

 4,878

 -

 -

 29,294

 127,454

Dec 2018

 516,279

 301,279

 276,590

 24,690

 69,666

 5,009

 175,473

 19,681

 31,451

 215,000

Mar 2018

 420,856

 286,194

 260,069

 26,125

 56,764

 3,723

 173,176

 22,402

 30,129

 134,662

Price and costs3

Average PGM basket price4

R/4Eoz - R/2Eoz

Mar 2019

 17,281

 17,104

 16,874

 14,943

 17,182

 16,182

 16,761

 14,498

 16,453

 18,283

Dec 2018

 15,415

 15,427

 15,536

 14,348

 15,901

 14,440

 15,391

 14,324

 15,053

 15,394

Mar 2018

 12,637

 12,839

 12,871

 12,643

 12,955

 12,962

 12,830

 12,590

 12,655

 12,289

US$/4Eoz - US$/2Eoz

Mar 2019

 1,234

 1,221

 1,204

 1,067

 1,226

 1,155

 1,196

 1,035

 1,174

 1,305

Dec 2018

 1,077

 1,078

 1,086

 1,003

 1,111

 1,009

 1,076

 1,001

 1,052

 1,076

Mar 2018

 1,058

 1,073

 1,076

 1,057

 1,083

 1,083

 1,073

 1,053

 1,058

 1,027

Operating cost5

R/t

Mar 2019

 777

 580

 1,095

 119

 748

 26

 1,278

 284

 978

 4,080

Dec 2018

 753

 484

 998

 72

 717

 22

 1,163

 144

 927

 3,443

Mar 2018

 626

 502

 994

 72

 714

 18

 1,140

 145

 769

 2,708

US$/t

Mar 2019

 55

 41

 78

 8

 53

 2

 91

 20

 70

 291

Dec 2018

 53

 34

 70

 5

 50

 2

 81

 10

 65

 241

Mar 2018

 52

 42

 83

 6

 60

 2

 95

 12

 64

 226

R/4Eoz - R/2Eoz

Mar 2019

 12,153

 13,335

 12,909

 18,309

 11,335

 9,717

 13,485

 21,394

 11,320

 10,038

Dec 2018

 11,658

 11,265

 11,377

 10,154

 10,595

 9,263

 11,687

 10,381

 10,410

 7,816

Mar 2018

 6,785

 10,722

 11,032

 7,996

 10,986

 8,165

 11,044

 7,968

 8,620

 5,921

US$/4Eoz - US$/2Eoz

Mar 2019

 867

 952

 921

 1,307

 809

 694

 963

 1,527

 808

 716

Dec 2018

 815

 787

 795

 710

 741

 647

 817

 726

 728

 546

Mar 2018

 567

 896

 922

 669

 919

 683

 923

 666

 721

 495

All-in sustaining cost6

R/4Eoz - R/2Eoz

Mar 2019

 12,358

 12,741

 10,916

 9,779

13,441

 11,857

 11,671

Dec 2018

 10,058

 10,576

 8,997

 9,423

11,170

 10,582

 9,180

Mar 2018

 9,310

 10,186

 10,477

 10,341

9,990

 8,706

 7,559

US$/4Eoz - US$/2Eoz

Mar 2019

 882

 909

 779

 698

959

846

 833

Dec 2018

 703

 739

 629

 659

781

740

 642

Mar 2018

 778

 852

 876

 864

835

728

 632

All-in cost6

R/4Eoz - R/2Eoz

Mar 2019

 13,479

 12,751

 10,916

 10,250

13,441

 11,857

 14,781

Dec 2018

 11,326

 10,596

 8,997

 10,501

11,170

 10,582

 12,560

Mar 2018

 10,152

 10,186

 10,477

 10,341

9,990

 8,706

 9,695

US$/4Eoz - US$/2Eoz

Mar 2019

 962

 910

 779

 732

959

 846

 1,054

Dec 2018

 792

 741

 629

 734

781

 740

 878

Mar 2018

 849

 852

 876

 864

835

 728

 811

Capital expenditure

Ore reserve development

Rm

Mar 2019

 432.9

 120.6

 -

 -

120.6

 -

 312.3

Dec 2018

 425.9

 119.9

 -

 -

119.9

 -

 306.0

Mar 2018

 327.8

 110.4

 -

 -

110.4

 -

 217.4

Sustaining capital

Mar 2019

 85.0

 56.0

 25.2

 3.5

27.3

 72.5

 29.0

Dec 2018

 283.5

 219.3

 59.6

 3.4

156.3

 56.0

 64.2

Mar 2018

 98.6

 77.1

 20.9

 10.2

46.0

 72.3

 21.5

Corporate and projects7

Mar 2019

 409.4

 2.3

 -

 2.3

-

 -

 407.1

Dec 2018

 544.4

 5.4

 -

 5.4

-

 -

 539.0

Mar 2018

 335.9

 -

 -

 -

-

 -

 335.9

Total capital expenditure

Rm

Mar 2019

 927.3

 178.9

 25.2

 5.8

147.9

 72.5

 748.4

Dec 2018

 1,253.8

 344.6

 59.6

 8.8

276.2

 56.0

 909.2

Mar 2018

 762.2

 187.4

 20.9

 10.2

156.3

 72.3

 574.8

US$m

Mar 2019

 66.2

 12.8

 1.8

 0.4

10.6

 5.2

 53.4

Dec 2018

 87.6

 24.1

 4.2

 0.6

19.3

 3.9

 63.6

Mar 2018

 64.0

 16.0

 2.0

 1.0

13.0

 6.0

 48.0

Average exchange rates for the quarters ended 31 March 2019, 31 December 2018 and 31 March 2018 were R14.01/US, R14.31/US$ and R11.96/US$, respectively

Figures may not add as they are rounded independently

1 The US PGM operations' underground production is converted to metric tonnes and performance is translated into SA rand. In addition to the US PGM operations' underground production, the operation treats various recycling material which is excluded from the underground statistics shown and is detailed in the PGM recycling table below

2 Production per product - see prill split in the table below

3 The Group and total SA PGM operations' unit cost benchmarks exclude the financial results of Mimosa, which is equity accounted and excluded from revenue and cost of sales

4 The average PGM basket price is the PGM revenue per 4E/2E ounce, prior to a purchase of concentrate adjustment

5 Operating cost is the average cost of production and operating cost per tonne is calculated by dividing the cost of sales, before amortisation and depreciation and change in inventory in a period by the tonnes milled/treated in the same period, and operating cost per ounce and kilogram is calculated by dividing the cost of sales, before amortisation and depreciation and change in inventory in a period by the PGM produced in the same period

6 All-in costs exclude income tax, costs associated with merger and acquisition activities, working capital, impairments, financing costs, one-time severance charges and items needed to normalise earnings. All-in costs is made up of All-in sustaining costs, being the cost to sustain current operations, given as a sub-total in the All-in costs calculation, together with corporate and major capital expenditure associated with growth. All-in sustaining cost per ounce (and kilogram) and All-in cost per ounce (and kilogram) are calculated by dividing the All-in sustaining costs and All-in costs, respectively, in a period by the total 4E/2E PGM produced in the same period

The US operations All-in cost, excluding the corporate project expenditure (on the Altar and Marathon projects), for the quarters ended 31 March 2019, 31 December 2018 and 31 March 2018 was US$1,053/2Eoz, US$876/2Eoz and US$811/2Eoz, respectively

7 The US operations corporate expenditure for the quarter ended 31 March 2019 includes R1.6 million (US$0.1 million) related to the Marathon project, and quarters ended 31 December 2018 and 31 March 2018 R4.2 million (US$0.3 million) and R16.5 million (US$1.4 million), respectively, related to the Altar and Marathon projects

Mining - Prill split excuding recycling operations

GROUP

SA OPERATIONS

US OPERATIONS

Mar 2019

Dec 2018

Mar 2018

Mar 2019

Dec 2018

Mar 2018

Mar 2019

Dec 2018

Mar 2018

4Eoz /2Eoz

%

4Eoz /2Eoz

%

4Eoz /2Eoz

%

4Eoz

%

4Eoz

%

2Eoz

%

2Eoz

%

2Eoz

%

Platinum

 182,573

46%

 212,055

46%

 199,629

46%

 153,109

58%

175,975

58%

166,440

58%

 29,464

23%

 36,080

23%

 33,189

22%

Palladium

 183,665

47%

 216,516

47%

 204,269

47%

 82,231

31%

93,125

31%

88,909

31%

 101,435

77%

 123,391

77%

 115,360

78%

Rhodium

 22,533

6%

 25,524

6%

 24,156

6%

 22,533

9%

25,524

9%

24,156

9%

Gold

 5,634

1%

 6,655

1%

 6,690

2%

 5,634

2%

6,655

2%

6,690

2%

PGM production

 394,407

100%

 460,750

100%

 434,743

100%

 263,508

100%

301,279

100%

286,194

100%

 130,899

100%

 159,471

100%

 148,549

100%

Ruthenium

 35,604

 40,098

 37,964

 35,604

40,098

37,964

Iridium

 8,169

 9,158

 7,249

 8,169

9,158

7,249

Total

 438,180

 510,006

 479,956

 307,281

350,535

331,407

 130,899

 159,471

 148,549

Recycling operation

Unit

Mar 2019

Dec 2018

Mar 2018

Average catalyst fed/day

Tonne

 25.6

 22.1

 25.8

Total processed

Tonne

 2,303

 2,032

 2,323

Tolled

Tonne

 581

 280

 365

Purchased

Tonne

 1,722

 1,752

 1,958

PGM fed

3Eoz

 201,289

 181,761

 191,404

PGM sold

3Eoz

 183,795

 110,476

 155,455

PGM tolled returned

3Eoz

 15,761

 35,441

 38,260

 

 

 

 

 

 

 

SA gold operations

SA OPERATIONS

Total SA gold1

Driefontein

Kloof

Beatrix

Cooke

DRDGOLD

Total

Under-ground

Surface

Under-ground

Surface

Under-ground

Surface

Under-ground

Surface

Under-ground

Surface

Surface

Production

Tonnes milled/treated

000't

Mar 2019

 9,329

 411

 8,918

 30

 8

 190

 1,627

 174

 456

 17

 1,153

 5,674

Dec 2018

 9,634

 1,138

 8,496

 282

 126

 393

 1,151

 421

 292

 42

 1,172

 5,755

Mar 2018

 4,283

 1,525

 2,758

 500

 815

 478

 1,075

 547

 173

 -

 695

Yield

g/t

Mar 2019

 0.48

 5.29

 0.26

 3.01

 0.38

 7.95

 0.37

 3.26

 0.50

 0.35

 0.28

 0.20

Dec 2018

 0.87

 5.37

 0.27

 5.11

 0.56

 7.19

 0.50

 4.26

 0.37

 1.05

 0.36

 0.19

Mar 2018

 2.12

 5.25

 0.39

 5.67

 0.29

 6.95

 0.49

 3.37

 0.37

 -

 0.35

Gold produced

kg

Mar 2019

 4,456

 2,174

 2,282

 90

 3

 1,510

 600

 567

 227

 6

 323

 1,130

Dec 2018

 8,399

 6,106

 2,293

 1,441

 70

 2,827

 576

 1,794

 108

 44

 428

 1,111

Mar 2018

 9,068

 8,002

 1,066

 2,833

 238

 3,323

 524

 1,846

 64

 -

 240

oz

Mar 2019

 143,278

 69,896

 73,382

 2,905

 96

 48,558

 19,278

 18,240

 7,295

 193

 10,383

 36,330

Dec 2018

 270,025

 196,313

 73,712

 46,329

 2,251

 90,891

 18,522

 57,678

 3,472

 1,415

 13,748

 35,719

Mar 2018

 291,543

 257,270

 34,273

 91,083

 7,652

 106,837

 16,847

 59,350

 2,058

 -

 7,716

Gold sold

kg

Mar 2019

 4,373

 2,130

 2,243

 88

 3

 1,482

 585

 554

 195

 6

 341

 1,119

Dec 2018

 8,288

 6,099

 2,189

 1,441

 70

 2,820

 494

 1,794

 108

 44

 380

 1,137

Mar 2018

 9,068

 8,002

 1,066

 2,833

 238

 3,323

 524

 1,846

 64

 -

 240

-

oz

Mar 2019

 140,593

 68,480

 72,113

 2,829

 96

 47,647

 18,808

 17,811

 6,269

 193

 10,963

 35,977

Dec 2018

 266,464

 196,087

 70,377

 46,329

 2,251

 90,665

 15,882

 57,678

 3,472

 1,415

 12,217

 36,555

Mar 2018

 291,543

 257,270

 34,273

 91,083

 7,652

 106,837

 16,847

 59,350

 2,058

 -

 7,716

Price and costs

Gold price received

R/kg

Mar 2019

 588,040

582,418

571,505

572,630

593,372

 588,114

Dec 2018

 561,788

557,909

560,260

563,197

564,623

 564,820

Mar 2018

 507,719

511,918

511,152

510,157

529,583

US$/oz

Mar 2019

 1,306

1,293

1,269

1,271

1,317

 1,306

Dec 2018

 1,221

1,213

1,218

1,224

1,228

 1,228

Mar 2018

 1,320

1,331

1,329

1,326

1,377

Operating cost2

R/t

Mar 2019

 421

 6,883

 123

 27,157

 1,138

 6,649

 176

 4,301

 154

 159

 121

 104

Dec 2018

 461

 3,001

 160

 4,303

 148

 3,331

 174

 2,103

 100

 186

 229

 107

Mar 2018

 934

 2,314

 182

 2,661

 208

 2,668

 182

 1,680

 97

 -

 172

US$/t

Mar 2019

 30

 491

 9

 1,938

 81

 475

 13

 307

 11

 11

 9

 7

Dec 2018

 32

 210

 11

 301

 10

 233

 12

 147

 7

 13

 16

 7

Mar 2018

 78

 193

 15

 222

 17

 223

 15

 140

 8

 -

 14

R/kg

Mar 2019

 881,009

 1,301,321

 480,665

 9,016,257

 3,033,333

 836,440

 477,476

 1,319,155

 309,835

 450,000

 431,949

523,009

Dec 2018

 539,451

 558,382

 489,033

 842,054

 267,143

 460,835

 347,688

 493,590

 269,444

 177,273

 606,177

 552,565

Mar 2018

 444,387

 440,890

 470,638

 469,714

 710,924

 383,720

 374,237

 497,941

 262,500

 -

 498,333

US$/oz

Mar 2019

 1,956

 2,889

 1,067

 20,017

 6,734

 1,857

 1,060

 2,929

 688

 999

 959

 1,161

Dec 2018

 1,173

 1,214

 1,063

 1,831

 581

 1,002

 756

 1,073

 586

 385

 1,318

 1,201

Mar 2018

 1,155

 1,146

 1,224

 1,221

 1,848

 998

 973

 1,295

 682

 -

 1,296

All-in sustaining cost3

R/kg

Mar 2019

 914,590

9,242,857

761,877

1,104,806

444,669

 546,023

Dec 2018

 610,883

989,014

526,433

537,066

406,132

 569,217

Mar 2018

 513,829

565,093

447,777

557,958

560,417

US$/oz

Mar 2019

 2,030

20,520

1,691

2,453

987

 1,212

Dec 2018

 1,328

2,150

1,144

1,168

883

 1,238

Mar 2018

 1,336

1,469

1,165

1,451

1,457

All-in cost3

R/kg

Mar 2019

 935,925

9,242,857

762,119

1,105,340

444,669

 556,390

Dec 2018

 651,267

989,014

538,413

537,802

406,132

 734,916

Mar 2018

 535,851

565,093

456,408

558,010

560,417

US$/oz

Mar 2019

 2,078

20,520

1,692

2,454

987

 1,235

Dec 2018

 1,416

2,150

1,171

1,169

883

 1,598

Mar 2018

 1,393

1,469

1,187

1,451

1,457

Capital expenditure

Ore reserve development

Rm

Mar 2019

 28.8

1.4

25.3

2.1

 -

 -

Dec 2018

 432.0

165.7

199.1

67.2

 -

 -

Mar 2018

 498.2

198.8

194.1

105.3

 -

 -

Sustaining capital

Mar 2019

 34.5

6.5

14.4

10.6

 -

 3.0

Dec 2018

 218.6

96.6

80.4

31.8

 -

 9.8

Mar 2018

 77.9

28.2

40.2

9.5

 -

Corporate and projects4

Mar 2019

 13.9

 -

0.5

0.4

 -

 11.6

Dec 2018

 256.2

 -

39.7

1.4

 -

 188.4

Mar 2018

 123.2

 -

33.2

0.1

 -

Total capital expenditure

Rm

Mar 2019

 77.4

7.9

40.2

13.1

 -

 14.6

Dec 2018

 906.8

262.3

319.2

100.4

 -

 198.2

Mar 2018

 699.2

227.0

267.5

114.9

 -

US$m

Mar 2019

 5.5

0.6

2.9

0.9

 -

 1.0

Dec 2018

 63.4

18.3

22.3

7.0

 -

 13.9

Mar 2018

 58.5

19.0

22.4

9.6

 -

Average exchange rates for the quarters ended 31 March 2019, 31 December 2018 and 31 March 2018 were R14.01/US, R14.31/US$ and R11.96/US$, respectively

Figures may not add as they are rounded independently

1 The SA gold operations' results for the quarters ended 31 March 2019 and 31 December 2018 include DRDGOLD. Gold produced and gold sold excludes 149kg (4,790oz) and 131kg (4,212oz), respectively from the Far West Gold Recoveries (FWGR) project which was capitalised in accordance with IFRS

2 Operating cost is the average cost of production and operating cost per tonne is calculated by dividing the cost of sales, before amortisation and depreciation and change in inventory in a period by the tonnes milled/treated in the same period, and operating cost per kilogram (and ounce) is calculated by dividing the cost of sales, before amortisation and depreciation in a period by the gold produced in the same period

3 All-in costs excludes income tax, costs associated with merger and acquisition activities, working capital, impairments, financing costs, one time severance charges and items needed to normalise earnings. All-in costs is made up of All-in sustaining costs, being the cost to sustain current operations, given as a sub-total in the All-in costs calculation, together with corporate and major capital expenditure associated with growth. All-in sustaining cost per kilogram (and ounce) and All-in cost per kilogram (and ounce) is calculated by dividing the All-in sustaining costs and All-in costs, respectively, in a period by the total gold sold over the same period

 

4 Corporate project expenditure for the quarters ended 31 March 2019, 31 December 2018 and 31 March 2018 was R1.3 million (US$0.1 million), R26.7 million (US$1.9 million), and R89.8 million (US$7.5 million), respectively. The majority of this expenditure was on the Burnstone project

DEVELOPMENT RESULTS

Development values represent the actual results of sampling and no allowance has been made for any adjustments which may be necessary when estimating ore reserves. All figures below exclude shaft sinking metres, which are reported separately where appropriate.

 

SA gold operations

Quarter ended

31 Mar 2019

31 Dec 2018

31 Mar 2018

Reef

Black Reef

Carbonleader

Main

VCR

Black Reef

Carbonleader

Main

VCR

Black Reef

Carbonleader

Main

VCR

Driefontein

Unit

Advanced

(m)

 7

 64

 2

1,043

 564

 847

 66

1,441

 660

 992

Advanced on reef

(m)

 7

 285

 44

 49

 293

 228

 128

Channel width

(cm)

 87

 48

 42

 36

 46

 35

 62

 56

Average value

(g/t)

 7.9

 24.5

 13.4

 86.1

 4.7

 30.0

 8.6

 85.8

(cm.g/t)

 684

1,183

 569

3,091

 214

1,041

 534

4,774

 

Quarter ended

31 Mar 2019

31 Dec 2018

31 Mar 2018

Reef

Cobble

Kloof

Main

Libanon

VCR

Cobble

Kloof

Main

Libanon

VCR

Cobble

Kloof

Main

Libanon

VCR

Kloof

Unit

Advanced

(m)

 575

 266

 236

1,145

 619

1,245

1,158

 605

 9

1,148

Advanced on reef

(m)

 330

 104

 84

 316

 202

 223

 373

 81

 9

 255

Channel width

(cm)

 151

 113

 85

 129

 131

 120

 129

 126

 99

 104

Average value

(g/t)

 8.7

 12.7

 18.7

 8.4

 11.6

 20.7

 9.6

 6.6

 11.3

 20.5

(cm.g/t)

1,314

1,435

1,591

1,091

1,526

2,485

1,244

 832

1,120

2,139

 

Quarter ended

31 Mar 2019

31 Dec 2018

31 Mar 2018

Reef

Beatrix

Kalkoen-krans

Beatrix

Kalkoen-krans

Beatrix

Kalkoen-krans

Beatrix

Unit

Advanced

(m)

 536

3,223

 38

3,909

 64

Advanced on reef

(m)

 421

1,016

 20

1,234

 21

Channel width

(cm)

 127

 106

 183

 118

 168

Average value

(g/t)

 10.3

 9.1

 4.6

 5.8

 9.6

(cm.g/t)

1,314

 966

 850

 688

1,619

 

 

Quarter ended

31 Mar 2019

31 Dec 2018

31 Mar 2018

Reef

KimberleyReefs

KimberleyReefs

KimberleyReefs

Burnstone

Unit

Advanced

(m)

1,266

Advanced on reef

(m)

 193

Channel width

(cm)

 69

Average value

(g/t)

 9.2

(cm.g/t)

 634

 

SA PGM operations

Quarter ended

31 Mar 2019

31 Dec 2018

31 Mar 2018

Reef

Kopan-eng

Simunye

Bamban-ani

Kwezi

K6

Kopan-eng

Simunye

Bamban-ani

Kwezi

K6

Kopan-eng

Simunye

Bamban-ani

Kwezi

K6

Kroondal

Unit

Advanced

(m)

 556

 386

 520

 734

 577

 651

 598

 707

 662

 592

 428

 481

 578

 609

 802

Advanced on reef

(m)

 556

 368

 484

 554

 577

 651

 598

 707

 662

 592

 409

 362

 402

 535

 657

Height

(cm)

 238

 219

 209

 241

 240

 247

 219

 224

 240

 241

 236

 229

 217

 245

 246

Average value

(g/t)

 2.0

 2.7

 2.7

 2.0

 2.5

 1.8

 2.2

 2.1

 2.1

 2.3

 2.2

 2.2

 2.0

 2.2

 2.2

(cm.g/t)

 469

 594

 563

 479

 587

 455

 486

 478

 501

 546

 520

 494

 429

 543

 536

 

Quarter ended

31 Mar 2019

31 Dec 2018

31 Mar 2018

Reef

Bathopele

Thembe-lani

Khuseleka

Siphume-lele

Bathopele

Thembe-lani

Khuseleka

Siphume-lele

Bathopele

Thembe-lani

Khuseleka

Siphume-lele

Rustenburg

Unit

Advanced

(m)

 245

1,401

2,355

 849

 943

2,017

2,617

1,177

 302

1,466

2,190

1,057

Advanced on reef

(m)

 245

 433

 751

 455

 943

 679

 912

 668

 302

 502

 596

 340

Height

(cm)

 221

 281

 288

 289

 216

 287

 285

 282

 209

 281

 288

 296

Average value

(g/t)

 1.3

 2.4

 2.4

 3.0

 2.8

 2.4

 2.3

 3.1

 2.7

 2.1

 2.1

 3.1

(cm.g/t)

 293

 676

 704

 879

 596

 692

 647

 872

 559

 582

 614

 932

 

US PGM operations

 

Quarter ended

31 Mar 2019

31 Dec 2018

31 Mar 2018

Reef

Stillwater incl Blitz

EastBoulder

Stillwater incl Blitz

EastBoulder

Stillwater incl Blitz

EastBoulder

Stillwater

Unit

Primary development (off reef)

(m)

 2,267

 843

2,659

 275

3,019

 657

Secondary development

(m)

 2,773

 916

2,557

1,538

2,038

1,451

 

 

 

 

ADMINISTRATION AND CORPORATE INFORMATION

 

SIBANYE GOLD LIMITED

Trading as SIBANYE-STILLWATER

Incorporated in the Republic of South Africa

Registration number 2002/031431/06

Share code: SGL

Issuer code: SGL

ISIN: ZAE E000173951

 

LISTINGS

JSE: SGL

NYSE: SBGL

 

WEBSITE

www.sibanyestillwater.com

 

REGISTERED OFFICE

Constantia Office Park

Cnr 14th Avenue & Hendrik Potgieter Road

Bridgeview House, Ground Floor

Weltevreden Park 1709

South Africa

 

Private Bag X5

Westonaria 1780

South Africa

 

Tel: +27 11 278 9600

Fax: +27 11 278 9863

 

CORPORATE SECRETARY

Lerato Matlosa

Tel: +27 10 493 6921

Email:

lerato.matlosa@sibanyestillwater.com

 

DIRECTORS

Sello Moloko1 (Chairman)

Neal Froneman (CEO)

Charl Keyter (CFO)

Timothy Cumming1

Savannah Danson1

Barry Davison1,2

Harry Kenyon-Slaney1

Richard Menell1

Nkosemntu Nika1

Keith Rayner1

Susan van der Merwe1

Jerry Vilakazi1

1 Independent non-executive

2 Retiring on 28 May 2019

INVESTOR ENQUIRIES

James Wellsted

Senior Vice President: Investor Relations

Cell: +27 83 453 4014

Tel: +27 10 493 6923

Email:

james.wellsted@sibanyestillwater.com or ir@sibanyestillwater.com

 

JSE SPONSOR

JP Morgan Equities South Africa Proprietary Limited

Registration number 1995/011815/07

1 Fricker Road

Illovo

Johannesburg 2196

South Africa

 

Private Bag X9936

Sandton 2196

South Africa

 

OFFICE OF THE UNITED KINGDOM SECRETARIES LONDON

St James's Corporate Services Limited

107 Cheapside

Suite 31, Second Floor

London EC2V 6DN

United Kingdom

Tel: +44 20 7796 8644

Fax: +44 20 7796 8645

 

AUDITORS

Ernst & Young Inc. (EY)

102 Rivonia Road

Sandton 2146

 

Private Bag X14

Sandton 2146

South Africa

Tel: +27 11 772 3000

AMERICAN DEPOSITORY

RECEIPTS TRANSFER AGENT

BNY Mellon Shareowner Services

PO Box 358516

Pittsburgh

PA15252-8516

 

US toll-free: +1 888 269 2377

Tel: +1 201 680 6825

Email:

shrrelations@bnymellon.com

 

Tatyana Vesselovskaya

Relationship Manager

BNY Mellon

Depositary Receipts

Direct Line: +1 212 815 2867

Mobile: +1 203 609 5159

Fax: +1 212 571 3050

Email:

tatyana.vesselovskaya@bnymellon.com

 

TRANSFER SECRETARIES

SOUTH AFRICA

Computershare Investor Services Proprietary Limited

Rosebank Towers

15 Biermann Avenue

Rosebank 2196

 

PO Box 61051

Marshalltown 2107

South Africa

 

Tel: +27 11 370 5000

Fax: +27 11 688 5248

 

TRANSFER SECRETARIES

UNITED KINGDOM

Capita Asset Services

The Registry

34 Beckenham Road

Beckenham

Kent BR3 4TU

England

Tel: 0871 664 0300 (calls cost 10p a minute plus network extras, lines are open 8.30am - 5pm Mon-Fri) or +44 20 8639 3399 (from overseas)

Fax: +44 20 8658 3430

Email:

ssd@capitaregistrars.com

 

FORWARD-LOOKING STATEMENTS

This announcement contains "forward-looking statements" within the meaning of the "safe harbour" provisions of the United States Private Securities Litigation Reform Act of 1995. Forward-looking statements may be identified by the use of words such as "target", "will", "would", "expect", "can", "potential", "could" and other similar expressions that predict or indicate future events or trends or that are not statements of historical matters. These forward-looking statements, including among others, those relating to our future business prospects, financial positions, debt position and our ability to reduce debt leverage, plans and objectives of management for future operations, our ability to obtain the benefits of any streaming arrangements or pipeline financing, our ability to service our Bond Instruments (High Yield Bonds and Convertible Bonds), our ability to achieve steady state production at the Blitz project and the anticipated benefits and synergies of our acquisitions are necessarily estimates reflecting the best judgement of our senior management and involve a number of known and unknown risks, uncertainties and other factors, many of which are difficult to predict and generally beyond the control of Sibanye-Stillwater, that could cause Sibanye-Stillwater's actual results and outcomes to be materially different from historical results or from any future results expressed or implied by such forward-looking statements. As a consequence, these forward-looking statements should be considered in light of various important factors, including those set forth in the Group's Annual Integrated Report and Annual Financial Report, published on 29 March 2019, and the Group's Annual Report on Form 20-F filed by Sibanye-Stillwater with the Securities and Exchange Commission on 9 April 2019 (SEC File no. 001-35785). These forward-looking statements speak only as of the date of this announcement. Sibanye-Stillwater undertakes no obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after the date of this announcement or to reflect the occurrence of unanticipated events, save as required by applicable law.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
QRFDBGDUGXGBGCI
Date   Source Headline
12th Jun 20192:46 pmBUSForm 8.3 - Lonmin
11th Jun 20193:36 pmBUSForm 8.3 - LONMIN AMENDMENT
11th Jun 201912:13 pmBUSForm 8.3 - LONMIN PLC
11th Jun 201911:35 amRNSForm 8.5 (EPT/RI)- Lonmin plc
10th Jun 20193:24 pmBUSForm 8.3 - Lonmin plc
10th Jun 20193:20 pmRNSForm 8.3 - Lonmin plc
10th Jun 20193:02 pmRNSForm 8.3 - Lonmin Plc
10th Jun 20193:00 pmRNSForm 8.3 - Lonmin PLC
10th Jun 20193:00 pmBUSForm 8.3 - LONMIN PLC
10th Jun 20192:00 pmRNSForm 8.3 - Lonmin Plc
10th Jun 20191:22 pmRNSForm 8.3 - Lonmin Plc
10th Jun 201912:45 pmBUSForm 8.3 - LONMIN PLC
10th Jun 201911:44 amRNSForm 8.5 (EPT/RI) - Lonmin plc
10th Jun 201911:40 amRNSForm 8.5 (EPT/NON-RI) - Sibanye Gold Ltd
10th Jun 201911:38 amRNSForm 8.5 (EPT/NON-RI) - Sibanye Gold Ltd
10th Jun 201911:37 amRNSForm 8.5 (EPT/RI) - Sibanye Gold Ltd
10th Jun 201911:30 amRNSForm 8.5 (EPT/RI) - Lonmin plc
10th Jun 20197:30 amRNSSuspension of Listing and Trading of Lonmin Shares
10th Jun 20197:00 amRNSScheme Becomes Effective
10th Jun 20197:00 amRNSForm 8.3 - Lonmin plc
7th Jun 20193:17 pmBUSForm 8.3 - Lonmin plc
7th Jun 20193:16 pmRNSForm 8.3 - Lonmin Plc
7th Jun 20193:00 pmRNSForm 8.3 - Lonmin PLC
7th Jun 20192:41 pmBUSForm 8.3 - LONMIN PLC - AMENDMENT
7th Jun 20192:35 pmRNSLonmin Plc Details Tailings Storage Facilities
7th Jun 20192:03 pmEQSForm 8.3 - The Vanguard Group, Inc.: Lonmin plc
7th Jun 20191:33 pmRNSForm 8.3 - Lonmin Plc
7th Jun 201912:37 pmBUSForm 8.3 - LONMIN PLC
7th Jun 201912:05 pmRNSScheme Sanctioned by Court and Timetable
7th Jun 201911:50 amRNSForm 8.5 (EPT/RI) - Sibanye Gold Ltd replacement
7th Jun 201911:47 amRNSForm 8.5 (EPT/NON-RI) - Sibanye Gold Ltd
7th Jun 201911:46 amRNSForm 8.5 (EPT/RI) - Sibanye Gold Ltd
7th Jun 201911:43 amRNSForm 8.5 (EPT/RI) - Lonmin plc
7th Jun 201911:32 amRNSForm 8.3 - Lonmin Plc
7th Jun 201910:49 amRNSForm 8.5 (EPT/RI)- Lonmin plc
7th Jun 201910:30 amGNWHSBC BANK PLC - Form 8.5 (EPT/RI) - Lonmin Plc
7th Jun 20197:00 amRNSForm 8.3 - Lonmin plc
6th Jun 20193:21 pmBUSForm 8.3 - Lonmin plc
6th Jun 20193:15 pmRNSForm 8.3 - Lonmin Plc
6th Jun 20193:00 pmRNSForm 8.3 - Lonmin PLC
6th Jun 20192:39 pmRNSForm 8.3 - Sibanye Gold Limited
6th Jun 20192:26 pmEQSForm 8.3 - The Vanguard Group, Inc.: Lonmin plc
6th Jun 20191:09 pmRNSForm 8.3 - Lonmin Plc
6th Jun 201912:18 pmBUSForm 8.3 - Lonmin plc
6th Jun 201911:36 amRNSForm 8.5 (EPT/NON-RI) - Sibanye Gold Ltd
6th Jun 201911:34 amGNWDimensional Fund Advisors Ltd. : Form 8.3 - Lonmin plc - Ordinary shares
6th Jun 201911:34 amRNSForm 8.5 (EPT/NON-RI) - Sibanye Gold Ltd
6th Jun 201911:33 amRNSForm 8.5 (EPT/RI) - Sibanye Gold Ltd
6th Jun 201911:22 amRNSForm 8.5 (EPT/RI)- Lonmin plc
6th Jun 201911:21 amRNSForm 8.3 - Lonmin Plc

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.