The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksKibo Energy Regulatory News (KIBO)

Share Price Information for Kibo Energy (KIBO)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.0375
Bid: 0.035
Ask: 0.04
Change: 0.00 (0.00%)
Spread: 0.005 (14.286%)
Open: 0.0375
High: 0.0375
Low: 0.0375
Prev. Close: 0.0375
KIBO Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Update on the Mozambique Power Project Portfolio

26 Aug 2020 10:10

RNS Number : 2097X
Kibo Energy PLC
26 August 2020
 

Kibo Energy PLC (Incorporated in Ireland)

(Registration Number: 451931)

(External registration number: 2011/007371/10)

Share code on the JSE Limited: KBO

Share code on the AIM: KIBO

ISIN: IE00B97C0C31

("Kibo" or "the Company")

 

Dated: 26 August 2020

Kibo Energy PLC ('Kibo' or the 'Company')

Update on the Mozambique Power Project Portfolio

 

Kibo Energy PLC, the multi-asset, Africa focused, energy company, is pleased to provide an update on its Mozambique projects, notably the Benga Power Plant Project ('BPPP') and the Baobab Power Station Project ('Baobab Project'). Further to the RNS's of May 11 and 18, respectively, significant progress has been made as Kibo looks to deliver 350 MW to 400 MW; a supply agreement is being targeted for BPPP that would deliver a total of c.150 MW to Mozambique utility Electricidade de Moçambique ('EDM'), whilst the Company has a binding term sheet with Baobab Resources Ltd ('Baobab') to supply c. 200MW energy to Baobab's Tete Steel and Vanadium Project in Mozambique from the proposed Baobab Project.

 

Highlights

· Grid Impact Assessment and Integration Study on BPPP completed, reviewed and submitted to EDM - this forms an important part of the DFS optimisation and financial model integration for BPPP

· Technical and Financial Feasibility review of the Baobab Project completed

· Integration study to assess feasibility of 400 MW combined project for the Baobab Project and BPPP commissioned, based on positive findings from technical and financial review of the Baobab Project

· PPA discussions / negotiations with both EDM and Baobab on schedule for completion by the end of this year and the beginning of Q4 respectively

 

Louis Coetzee, CEO of Kibo Energy, commented, "We are extremely pleased with the progress being made in Mozambique, which will eventually culminate in at least two Power Purchase Agreements totalling c.350 - 400 MW. Our development options currently remain open as to whether we construct one power plant to fulfil both supply agreements or two separate plants to service Baobab and EDM independently and we look forward to finalizing the integration study to better assess and define the optimal approach in this regard. Either way both agreements will continue to progress at pace, unencumbered by the other, so that we can realise meaningful value for our shareholders and our power clients."

 

**ENDS**

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ('MAR').

For further information please visit www.kibo.energy or contact:

 

Louis Coetzee

info@kibo.energy

Kibo Energy PLC

Chief Executive Officer

Andreas Lianos

+27 (0) 83 4408365

River Group

Corporate and Designated

Adviser on JSE

Philip Adler

+44 (0) 20 7392 1494

ETX Capital Limited

Joint Broker

Bhavesh Patel / Stephen Allen

+44 20 3440 6800

RFC Ambrian Limited

NOMAD on AIM

Charlotte Page /

Beth Melluish

+44 (0) 20 7236 1177

St Brides Partners Ltd

Investor and Media Relations Adviser

 

Notes

Kibo Energy PLC is a multi-asset, Africa focused, energy company positioned to address the acute power deficit, which is one of the primary impediments to economic development in Sub-Saharan Africa. To this end, it is the Company's objective to become a leading independent power producer in the region.

 

Kibo is simultaneously developing three similar coal-fuelled power projects: the Mbeya Coal to Power Project ('MCPP') in Tanzania; the Mabesekwa Coal Independent Power Project ('MCIPP') in Botswana; and the Benga Independent Power Project ('BIPP') in Mozambique. By developing these projects in parallel, the Company intends to leverage considerable economies of scale and timing in respect of strategic partnerships, procurement, equipment, human capital, execution capability / capacity and project finance.

 

Additionally, the Company has a 60% interest in MAST Energy Developments Limited ('MED'), a private UK registered company targeting the development and operation of flexible power plants to service the UK Reserve Power generation market.

 

Johannesburg

26 August 2020

Corporate and Designated Adviser

River Group

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCSEWSAMESSEIA
Date   Source Headline
23rd May 20232:30 pmRNSKibo Subsidiary MED Issue of Shares
22nd May 20233:00 pmRNSKibo Subsidiary Issue of Shares
18th May 20237:00 amRNSMED Update, JV and Reprofiling of Loan Facilities
18th May 20237:00 amRNSMbeya Power Update
12th May 202311:45 amRNSTR-1
11th May 20237:00 amRNSNotice of Extraordinary General Meeting
4th May 20238:00 amRNSUpdate regarding Kibo Warrant Exercise and TVR
4th May 20237:00 amRNSMED Q1 Corporate Presentation and Website Update
2nd May 20237:00 amRNSBio-fuel Projects Test Work & Director Retirement
28th Apr 20237:02 amRNSMast Energy Developments PLC Annual Report
26th Apr 202312:20 pmRNSTR-1: Standard form for notification
26th Apr 20237:00 amRNSWarrant Exercise and Loan Note Conversion
12th Apr 20233:48 pmRNSTR-1: Standard notification of major holdings
11th Apr 20237:00 amRNSWarrant Repricing CLN Conversion & Bridge Loan
6th Apr 20234:45 pmRNSKibo Project Update
16th Mar 20231:35 pmRNSAdjournment of EGM
10th Mar 20237:00 amRNSGroup Business Development Executive Appointment
1st Mar 20237:00 amRNSConvertible Instrument - Redemption Date Extension
27th Feb 20239:20 amRNSMED Pyebridge Update
22nd Feb 20238:00 amRNSNotice of Extraordinary General Meeting (“EGM”)
13th Feb 20239:05 amRNSSecond Price Monitoring Extn
13th Feb 20239:00 amRNSPrice Monitoring Extension
1st Feb 20237:00 amRNSOperational Update: 2023
25th Jan 202311:07 amRNSIssue of Shares in lieu of Payment
17th Jan 20239:15 amRNSOptimization Improvement to 1st SA WTE Project
11th Jan 20237:30 amRNSRestoration - Kibo Energy plc
11th Jan 20237:00 amRNSAppointment of NOMAD & Director and General Update
15th Dec 20222:10 pmRNSSettlement Shares Sale
12th Dec 20227:30 amRNSSuspension – Kibo Energy plc
9th Dec 20221:50 pmRNSNomad Update and Suspension
5th Dec 20229:20 amRNSConvertible Instrument Redemption Date Extension
23rd Nov 20227:00 amRNSKibo Renews MOU with Tanzanian Utility, TANESCO
15th Nov 202210:00 amRNSRetirement of Director
10th Nov 20221:45 pmRNSTR1 Standard form for notification major holdings
28th Oct 20221:00 pmRNSResults of Reconvened AGM
7th Oct 20227:00 amRNSNotice of Reconvened Annual General Meeting
29th Sep 20227:00 amRNSKibo Strategic IPO Spinout
23rd Sep 20229:30 amRNSInterim results for the 6 months ended 30/06/22
21st Sep 20227:45 amRNSAcquisition of Advanced UK Waste to Energy Project
16th Sep 20221:00 pmRNSAdjournment of AGM
8th Sep 20223:20 pmRNSConvertible Instrument Update
25th Aug 20227:00 amRNSUpdate on Sustainable Energy Solutions Strategy
24th Aug 20227:41 amRNSNotice of AGM
18th Aug 20222:10 pmRNSTR-1: notification of major holdings
12th Aug 20221:45 pmRNSTR-1: Notification of major holdings
29th Jul 20222:15 pmRNSPartial Settlement of Outstanding MED Loan
14th Jul 202211:05 amRNSSecond Price Monitoring Extn
14th Jul 202211:00 amRNSPrice Monitoring Extension
14th Jul 20227:00 amRNSKibo PPA on SA W2E Project Extended to 20 Years
7th Jul 20227:00 amRNSFramework Agreement - Long Duration ESS

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.