The next focusIR Investor Webinar takes place tomorrow with guest speakers from WS Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksKibo Energy Regulatory News (KIBO)

Share Price Information for Kibo Energy (KIBO)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.0375
Bid: 0.035
Ask: 0.04
Change: 0.00 (0.00%)
Spread: 0.005 (14.286%)
Open: 0.0375
High: 0.0375
Low: 0.0375
Prev. Close: 0.0375
KIBO Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Kibo Strategy Update

16 Jan 2024 07:00

RNS Number : 7623Z
Kibo Energy PLC
16 January 2024
 

Kibo Energy PLC (Incorporated in Ireland)

(Registration Number: 451931)

(External registration number: 2011/007371/10)

LEI Code: 635400WTCRIZB6TVGZ23

Share code on the JSE Limited: KBO

Share code on the AIM: KIBO

ISIN: IE00B97C0C31

('Kibo' or 'the Company')

 

Dated: 16 January 2024

 

Kibo Energy PLC ('Kibo' or the 'Company')

 

Kibo Strategy Update

 

Kibo Energy PLC (AIM: KIBO; AltX: KBO), the renewable energy-focused developer of sustainable energy solutions, is pleased to provide an interim strategy update in relation to its development approach. This follows the Company's 2023 operational update as announced in an RNS dated 3 July 2023. This RNS aims to outline the Company's strategic concept and, whilst progress has been limited given constraints around funding, recent advancements as part of its commitment to developing long-term sustainable energy solutions in Southern Africa, the UK and Ireland.

Kibo's strategy revolves around its commitment to being a developer of sustainable clean energy solutions by integrating both established and cutting-edge technologies in renewable energy generation, waste-to-energy and energy storage. The primary focus is to deliver enduring, low- or zero-carbon energy-generation solutions across Southern Africa, the UK and Ireland.

A number of these clean energy opportunities are in various stages of development and others still in the opportunity screening phase.

In pursuit of this objective, the Company has and continues to establish formal relationships with pivotal and leading industry entities, including sustainable technology original equipment manufacturers, specialising in energy storage, biomass production and pioneers in biofuel technologies.

Operationally, the Company: 

· is currently formulating a joint development agreement with a multinational food and beverage producer ("the Client") intended to be funded equally (i.e., 50-50) by Kibo and the Client. The objective of this collaboration is to build and operate a pilot plant that will produce bio-coal as a preliminary step towards the establishment of a comprehensive production-scale facility. This initiative, subject to a successful pilot plant and financing, will enable the Client to transition from the use of fossil coal to bio-coal in its comprehensive boiler fleet, without any reconfiguration, aligning with established Environmental, Social and Governance (ESG) compliance standards; and

 

· has received conditional preliminary approval for development funding, subject to due diligence, from a prominent development banking institution in Southern Africa for one of the Company's existing waste-to-energy projects.

 

 

 

 

 

 

 

The table below indicates the status of Kibo's project portfolio at present. Timelines beyond Q1 2024 remain as advised and the Company will advise should these change in light of the below. This does not include opportunities that are currently the subject of advanced due diligence and commercial consideration.

 

Kibo Group Project Portfolio

Entity

Kibo Equity

Strategic Domain

Projects

Development Status

Current Status

MAST Energy Developments (UK)

57.86%

Reserve Power

Pyebridge (9 MW)

In care and maintenance

- CM T-1 contract began on 1 October 2023 (see MED Unaudited Interim results for the six months ended 30 June 2023)

- Placed in care and maintenance, pending funding (see MED RNS dated 1 December 2023)

Bordesley (5 MW)

Advanced project development

Ready for construction and awaiting funding (see MED RNS dated 25 August 2023)

Rochdale (4.4 MW)

Advanced project development

- Planning consent granted in Q2 2023 (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023 and MED Unaudited Interim results for the six months ended 30 June 2023)

- Shovel ready and awaiting funding (see MED RNS dated 25 August 2023 and MED Unaudited Interim results for the six months ended 30 June 2023)

Hindlip Lane (7.5 MW)

Concept stage

- EPC and O&M contracts under review, further updates to follow (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023 and MED Unaudited Interim results for the six months ended 30 June 2023)

- Shovel ready and awaiting funding (see MED RNS dated 25 August 2023 and MED Unaudited Interim results for the six months ended 30 June 2023)

Stather Road (2.5 MW)

Concept stage

- EPC and O&M contracts under review, further updates to follow (see MED Results for the year ended 31 December 2022 as per the MED RNS dated 28 April 2023 and MED Unaudited Interim results for the six months ended 30 June 2023)

- Planning consent granted (see MED RNS dated 25 August 2023 and MED Unaudited Interim results for the six months ended 30 June 2023)

Sustineri (SA)

65%

Waste to Energy

CHP project to supply base-load electricity generation in South Africa with 4 potential revenue streams: electricity, gate fees and potentially from heat and steam output as well as the production of synthetic fuel oil and naphtha

Phase 1 (2.7 MW + study on synthetic oil production)

Advanced project development stage - financial close ready

- Technical workstream in collaboration with a potential OEM to align and integrate plant designs and specifications with feedstock supply

- Integrated Environmental Authorisation (EA) has been granted

- Advanced discussions with a development banking institution for development funding currently underway

Phase 2 (targeted 20 MW)

Pre-concept stage

Milestones TBD once Phase 1 has been executed

National Broadband Solutions (SA)

51%

Long Duration Energy Storage

 

12.3 MW in development

Simultaneous concept and commercial development

Status remains unchanged from previous update currently under review

36.32 MW target for development

Under assessment

Mbeya Power Project ('MPP') (TZ)

100%

Biofuel

300 MW short-term conversion to renewable energy biofuel

Original project. Fully permitted with Bankable Feasibility Study completed

TANESCO due diligence on Kibo ongoing as part of the MOU programme and currently underway

The Company has also entered into negotiations with potential strategic investor for the further development of the MPP

UK Portfolio

100%

Waste to Energy

Southport (10 MW, 2 MW long-duration energy storage and 5.5m m3 bio-methane)

Status remains unchanged from previous update as parties continue to seek agreement on further development plan for project

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014.

 

**ENDS**

 

For further information please visit www.kibo.energy or contact:

 

Louis Coetzee

info@kibo.energy

Kibo Energy PLC

Chief Executive Officer

James Biddle

Roland Cornish

+44 207 628 3396

Beaumont Cornish Limited

Nominated Adviser

Claire Noyce

+44 20 3764 2341

Hybridan LLP

Joint Broker

Damon Heath

+44 207 186 9952

Shard Capital Partners LLP

Joint Broker

Zainab Slemang van Rijmenant

zainab@lifacommunications.com

Lifa Communications

Investor and Media Relations Consultant

 

Johannesburg

16 January 2024

Corporate and Designated Adviser

River Group

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDBIGDBLXBDGSU
Date   Source Headline
26th May 202312:15 pmRNSWarrant Exercise
23rd May 20232:30 pmRNSKibo Subsidiary MED Issue of Shares
22nd May 20233:00 pmRNSKibo Subsidiary Issue of Shares
18th May 20237:00 amRNSMED Update, JV and Reprofiling of Loan Facilities
18th May 20237:00 amRNSMbeya Power Update
12th May 202311:45 amRNSTR-1
11th May 20237:00 amRNSNotice of Extraordinary General Meeting
4th May 20238:00 amRNSUpdate regarding Kibo Warrant Exercise and TVR
4th May 20237:00 amRNSMED Q1 Corporate Presentation and Website Update
2nd May 20237:00 amRNSBio-fuel Projects Test Work & Director Retirement
28th Apr 20237:02 amRNSMast Energy Developments PLC Annual Report
26th Apr 202312:20 pmRNSTR-1: Standard form for notification
26th Apr 20237:00 amRNSWarrant Exercise and Loan Note Conversion
12th Apr 20233:48 pmRNSTR-1: Standard notification of major holdings
11th Apr 20237:00 amRNSWarrant Repricing CLN Conversion & Bridge Loan
6th Apr 20234:45 pmRNSKibo Project Update
16th Mar 20231:35 pmRNSAdjournment of EGM
10th Mar 20237:00 amRNSGroup Business Development Executive Appointment
1st Mar 20237:00 amRNSConvertible Instrument - Redemption Date Extension
27th Feb 20239:20 amRNSMED Pyebridge Update
22nd Feb 20238:00 amRNSNotice of Extraordinary General Meeting (“EGM”)
13th Feb 20239:05 amRNSSecond Price Monitoring Extn
13th Feb 20239:00 amRNSPrice Monitoring Extension
1st Feb 20237:00 amRNSOperational Update: 2023
25th Jan 202311:07 amRNSIssue of Shares in lieu of Payment
17th Jan 20239:15 amRNSOptimization Improvement to 1st SA WTE Project
11th Jan 20237:30 amRNSRestoration - Kibo Energy plc
11th Jan 20237:00 amRNSAppointment of NOMAD & Director and General Update
15th Dec 20222:10 pmRNSSettlement Shares Sale
12th Dec 20227:30 amRNSSuspension – Kibo Energy plc
9th Dec 20221:50 pmRNSNomad Update and Suspension
5th Dec 20229:20 amRNSConvertible Instrument Redemption Date Extension
23rd Nov 20227:00 amRNSKibo Renews MOU with Tanzanian Utility, TANESCO
15th Nov 202210:00 amRNSRetirement of Director
10th Nov 20221:45 pmRNSTR1 Standard form for notification major holdings
28th Oct 20221:00 pmRNSResults of Reconvened AGM
7th Oct 20227:00 amRNSNotice of Reconvened Annual General Meeting
29th Sep 20227:00 amRNSKibo Strategic IPO Spinout
23rd Sep 20229:30 amRNSInterim results for the 6 months ended 30/06/22
21st Sep 20227:45 amRNSAcquisition of Advanced UK Waste to Energy Project
16th Sep 20221:00 pmRNSAdjournment of AGM
8th Sep 20223:20 pmRNSConvertible Instrument Update
25th Aug 20227:00 amRNSUpdate on Sustainable Energy Solutions Strategy
24th Aug 20227:41 amRNSNotice of AGM
18th Aug 20222:10 pmRNSTR-1: notification of major holdings
12th Aug 20221:45 pmRNSTR-1: Notification of major holdings
29th Jul 20222:15 pmRNSPartial Settlement of Outstanding MED Loan
14th Jul 202211:05 amRNSSecond Price Monitoring Extn
14th Jul 202211:00 amRNSPrice Monitoring Extension
14th Jul 20227:00 amRNSKibo PPA on SA W2E Project Extended to 20 Years

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.