The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksKefi Gold Regulatory News (KEFI)

Share Price Information for Kefi Gold (KEFI)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.544
Bid: 0.538
Ask: 0.544
Change: 0.002 (0.37%)
Spread: 0.006 (1.115%)
Open: 0.538
High: 0.544
Low: 0.538
Prev. Close: 0.539
KEFI Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Projections for Expanded Production

31 Oct 2017 07:00

RNS Number : 0145V
KEFI Minerals plc
31 October 2017
 

31 October 2017

 

KEFI Minerals plc

("KEFI" or the "Company")

 

 Tulu Kapi Gold Project - PROJECTIONS FOR EXPANDED PRODUCTION

Incorporating refinements since the 2017 Update Definitive Feasibility Study

 

KEFI Minerals (AIM: KEFI), the gold exploration and development company with projects in the Kingdom of Saudi Arabia and the Federal Democratic Republic of Ethiopia, is pleased to announce updated financial projections reflecting the recently announced plans to expand production. In the meantime, we continue to prepare for finance closing with mandated financier Oryx Management Limited ("Oryx") and the other consortium members the Government of Ethiopia, Ausdrill and Lycopodium.

 

Production plans have been re-cast and the average annual gold production in years 1-3 is estimated to expand from c. 115,000 ounces to c. 145,000 ounces per annum. At a flat $1,250/oz gold price, the payback period is about 3 years. This forecast is derived by management in consultation with its advisers and will continue to be refined as we approach start-up, during the 2018 operational readiness phase along with detailed engineering and procurement.

 

Set out below are comparisons with the key outputs of the 2015 Definitive Feasibility Study ("DFS") and the 2017 DFS Update which were on an unleveraged basis. The latest estimates build in the impact of the planned finance structure and its leverage, reflecting the specifics of the Oryx detailed Heads of Terms (see announcement 17 July 2017). The latest estimates also reflect the strategy agreed with Oryx to install greater processing capacity from the outset with a view to achieving:

 

a)

quicker cash flow from the open pit and capacity to process additional ore from targeted satellite deposits, and

b)

greater protection against downside risks by facilitating faster processing of lower grade ore from the open pit.

 

Key planning assumptions which have been introduced since the 2017 DFS Update include:

 

·

Plant expanded from 1.5-1.7Mtpa to 1.9-2.1Mtpa, depending on the hardness of the ore.

·

Refining the Engineering, Procurement and Construction ("EPC") contract into a hybrid of EPC and an Engineering, Procurement and Construction Management ("EPCM") contract whereby the client has the protection of certain performance guarantees, along with the transparency of open-book access to all costs along with tighter alignment with owner-management via incentivised target schedule and cost for the contractor (Lycopodium). This style is also preferred by Oryx's Finance SPV, which will own the plant and lease it to KEFI's project company.

·

The additional c. $12 million funding required for plant and infrastructure expansion has been offset by expected savings of capital expenditure and by Oryx offering to expand its facility from US$135 million to US$140 million.

·

Mine plans re-cast to allow faster mining, intensified grade-control drilling and enhanced flexibility to switch between bulk mining and selective mining as most appropriate.

 

KEFI's Executive Chairman, Mr Harry Anagnostaras-Adams, said:

 

"The Tulu Kapi Gold Project consortium is implementing its finance closing procedures and the refined financial projections announced today reflect recently resolved expansion plans.

 

"Projected annual gold production has been expanded from approximately 115,000 ounces to 144,000 ounces per annum for the first three years. Measures of return have improved accordingly and indicate significant targeted value up-lift for shareholders under any modelled scenario."

 

Key Points of the Tulu Kapi Expansion Plan (100% of Tulu Kapi Gold Project - Open Pit only)

 

2017 2Mt Expansion

Leveraged

2017 DFS Update

Unleveraged

2015 DFS

Unleveraged

Average head grade

2.1g/t gold

2.1g/t gold

2.1g/t gold

Total gold production

980K oz

980K oz

961K oz

Ore processing rate

1.9-2.1Mtpa

1.5-1.7Mtpa

1.2Mtpa

Annual gold production (1st 3 years)

144K oz pa

115K oz pa

98K oz pa

 

 

 

 

Cash Operating Costs

US$685/oz

US$684/oz

US$661/oz

All-in Sustaining Costs (excluding initial capex & debt service)

US$773/oz

US$777/oz

US$780/oz

All-in Costs (excluding debt service)

US$948/oz

US$933/oz

US$906/oz

All-in Costs (including debt service)

US$1,051/oz

N.A

N.A

IRR

60%

22%

28%

NPV at start of construction(8% real after tax discount rate)

US$74M

US$97M

US$125M

NPV at start of production(8% real after tax discount rate)

US$131M

US$272M

US$256M

Payback

3 years

3 years

2.5 years

Net Operating Cash Flow (same as EBITDA)(average for first 3 years)

US$74M p.a.

US$62M p.a.

US$50M p.a.

The economic metrics tabulated above are for contract mining of the open pit only, based on a gold price of US$1,250/ounce flat over life-of-mine and are on an after-tax basis.

 

·

Summary: since assuming control of the Project in 2014, KEFI has continually improved its outlook based on plans developed with leading industry specialists. The improvements announced today have the effect of reducing operational and financial risks as well as increasing potential returns. 

·

All-in Sustaining Costs: estimates remain relatively unchanged at c. US$800/oz despite the faster-track mining and processing, because of an assumption (pending more detailed work during the operational readiness phase in 2018) of higher unit costs for mining (increased grade-control drilling). All-in sustaining costs includes all operating costs, royalties, sustaining capital and closure costs, but excludes initial capital, financing costs and income taxes. This ranks Tulu Kapi in the best (lowest) quartile of gold producers globally.

·

All-in costs (excluding debt service): estimates remain relatively unchanged at c. US$930/oz for the reasons set out above as regards All-in Sustaining Costs. All-in costs also includes all initial capital expenditure. This measure also ranks Tulu Kapi in the best (lowest) quartile of gold producers globally.

·

Net operating cash flow for first 3 years: increased to US$74M p.a., from US$62M p.a. in the 2017 DFS Update.

·

Project IRR: IRR has increased materially from 22% (unleveraged) to 60% (leveraged).

·

Project NPV (leveraged after tax): the Open Pit NPV estimates c. $74 million at start of construction and of c. US$131 million at start of production indicate material value up-lift for current and new equity investors. If one adds a risk-adjusted 50% of the NPV for the underground project (based on Preliminary Economic Assessment), it adds in the order of US$20 million to the NPV i.e. US$94 million at start of construction and US$151 million at start of production.

·

Project funding requirements: KEFI's planned project structure involves the following funding components for all but a residual amount which remains in the order of US$20 million:

o

funding of mining equipment by Ausdrill as part of the proposed mine services agreement whereby they receive payment per tonne of material mined.

o

off-site infrastructure funded by the Government of Ethiopia, for project level equity

o

funding of on-site infrastructure by Oryx (for debt-style returns along with a potential gold-linked extra interest that has the potential to elevate its returns from the coupon of c. 8% to a potential 15% at a gold price of US$1,700/oz throughout the repayment term). Yield to maturity would be c. 10% if gold does not exceed US$1,100/oz and it rises proportionately up to c. 15% at a gold price of US$1,700/oz.

·

Residual funding requirement: consistent with KEFI's recent guidance, the residual requirement is c. US$20M to be raised preferably at project level (Tulu Kapi Gold Mines Share Company Limited, "TKGM") or intermediate company level (KEFI Minerals (Ethiopia) Limited, "KME"). The financial forecasts reported herein also reaffirm that the transaction is expected to be materially value-enhancing for current and new equity investors regardless of how the equity investment is structured.

·

Financial sensitivity testing: has been conducted, the principal conclusions being that:

o

On the upside, as a small indicator of the leverage being targeted by KEFI:

§

A gold price of US1,400/oz or a throughput lift of 10% pa lift Project IRR rises to c. 80% and the potential value-lift for existing and new equity investors is lifted commensurately.

o

On the downside, as a stress test:

§

all financial commitments are well covered even:

·

at a flat gold price of US$1,100/oz for the next 10 years, or

·

if bulk mining is utilised exclusively without any reliance on the planned application of targeted limited selective mining. This would result in the head grade being only 1.7g/t instead of 2.1g/t gold

§

NPV and other valuation measures show value-lift for current and new equity investors even under these downside cases.

     

 

 

Market Abuse Regulation (MAR) Disclosure

 

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement.

 

ENQUIRIES

 

KEFI Minerals plc

 

Harry Anagnostaras-Adams (Executive Chairman)

+357 99457843

John Leach (Finance Director)

 

+357 99208130

SP Angel Corporate Finance LLP (Nominated Adviser)

 

Ewan Leggat, Jeff Keating

+44 20 3470 0470

 

 

Brandon Hill Capital Ltd (Joint Broker)

 

Oliver Stansfield, Alex Walker, Jonathan Evans

+44 20 7936 5200

 

 

RFC Ambrian Ltd (Joint Broker)

Jonathan Williams

+44 20 3440 6817

 

Beaufort Securities Ltd (Joint Broker)

Elliot Hance

 

+44 20 7382 8300

 

 

IFC Advisory Ltd (Financial PR and IR)

 

Tim Metcalfe, Heather Armstrong

+44 20 3053 8671

 

NOTES TO EDITORS

 

KEFI Minerals plc

KEFI is the operator of two advanced gold development projects within the highly prospective Arabian-Nubian Shield, with an attributable 1.93Moz (100% of Tulu Kapi's 1.72Moz and 40% of Jibal Qutman's 0.73Moz) gold Mineral Resources (JORC 2012) plus significant resource growth potential. KEFI targets that production at these projects generates cash flows for further exploration and expansion as warranted, recoupment of development costs and, when appropriate, dividends to shareholders.

 

KEFI Minerals in Ethiopia

The Tulu Kapi gold project in western Ethiopia is being progressed towards development, following a grant of a Mining Licence in April 2015.

Following completion of KEFI's Definitive Feasibility Study for Tulu Kapi, the Company is now refining contractual terms for project construction and operation. Latest estimates are that gold production may be brought forward by increasing processing capacity, as compared with the DFS estimates of c. 100,000oz pa for a 10-year period. All-in Sustaining Cost estimates (including operating, sustaining capital and closure but not including leasing and other financing charges) remain

All aspects of the Tulu Kapi (open pit) gold project have been reported in compliance with the JORC Code (2012) and subjected to reviews by appropriate independent experts. These plans now also reflect the agreed construction and operating terms with project contractors, and have been independently reviewed by experts appointed for the project finance syndicate.

A Preliminary Economic Assessment has been published that indicates the economic attractiveness of mining the underground deposit adjacent to the Tulu Kapi open pit, after the start-up of the open pit and after positive cash flows have begun to repay project debts.

KEFI Minerals in the Kingdom of Saudi Arabia

In 2009, KEFI formed G&M in Saudi Arabia with local Saudi partner, Abdul Rahman Saad Al Rashid & Sons Company Limited ("ARTAR"), to explore for gold and associated metals in the Arabian-Nubian Shield. KEFI has a 40% interest in G&M and is the operating partner. To date, G&M has conducted preliminary regional reconnaissance and has had five exploration licences ("ELs") granted, including Jibal Qutman and the more recently granted Hawiah EL that contains over 6km strike length of outcropping gossans developed on altered and mineralised rocks with all the hallmarks of a copper-gold-zinc VHMS deposit.

At Jibal Qutman, G&M's flagship project, Mineral Resources are estimated to total 28.4Mt at 0.80g/t gold for 733,045 contained ounces. The shallow oxide portion of this resource is being evaluated as a low capital expenditure heap-leach mine development.

ARTAR, on behalf of G&M, holds over 20 EL applications. ELs are renewable for up to three years and bestow the exclusive right to explore and to obtain a 30-year exploitation (mining) lease within the area. The Kingdom of Saudi Arabia has instituted, and is further overhauling, policies to encourage minerals exploration and development, and KEFI Minerals supports this priority by serving as the technical partner within G&M. ARTAR also serves this government policy as the major partner in G&M, which is one of the early movers in the modern resurgence of the Kingdom's minerals sector.

-end-

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLOKKDNABDDNKN
Date   Source Headline
29th Jun 201711:06 amRNSAGM Statement
15th Jun 20174:18 pmRNSHolding(s) in Company
6th Jun 201712:14 pmRNSNotice of AGM and Publication of Annual Report
6th Jun 20177:00 amRNSFull Year Results 2016
24th May 20177:00 amRNS2017 DFS Update for Tulu Kapi Gold Project
5th May 20177:00 amRNSUpdate on Tulu Kapi Project-Shareholder Agreement
3rd May 201710:34 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
2nd May 20177:01 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
2nd May 20177:00 amRNSUPDATE ON LEGAL PROCEEDINGS
28th Apr 201710:38 amRNSHolding(s) in Company
27th Apr 20177:00 amRNSUpdate on Tulu Kapi Project
26th Apr 20177:00 amRNSUpdate on Tulu Kapi Project and Site Visit
31st Mar 201712:40 pmRNSTotal Voting Rights
31st Mar 20177:00 amRNSQuarterly Operational Report
22nd Mar 201712:46 pmRNSGrant of Share Options
8th Mar 20179:23 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
7th Mar 201712:51 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
7th Mar 20179:13 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
1st Mar 201712:18 pmRNSResults of General Meeting
1st Mar 20177:00 amRNSChairman's GM Statement
13th Feb 20177:00 amRNSConditional Fundraising to Raise £5.62 Million
2nd Feb 20171:25 pmRNSKEFI presenting at Mining Indaba
20th Dec 20167:00 amRNSDecember 2016 Quarterly Operational Report
9th Nov 20167:00 amRNSTulu Kapi Update Following Financiers' Site Visit
25th Oct 20167:00 amRNSUpdate on Discussions with Government of Ethiopia
20th Oct 201610:48 amRNSQuarterly Update Webinar
18th Oct 20167:00 amRNSThird Quarter Update
10th Oct 201610:20 amRNSUpdate on Ethiopia
26th Sep 20167:00 amRNSHalf-year Report
5th Sep 20167:00 amRNSOperational Update
10th Aug 20168:05 amRNSAppointment of Joint Broker
8th Aug 20167:00 amRNSDirectorate Change and Grant of Options
1st Aug 201612:04 pmRNSHolding(s) in Company
29th Jul 20169:39 amRNSTotal Voting Rights
28th Jul 20169:54 amRNSHolding(s) in Company
27th Jul 201610:28 amRNSReplacement - Conditional Placing
26th Jul 201610:04 amRNSHolding(s) in Company
26th Jul 20169:02 amRNSConditional Placing to Raise Approx. £3.8 million
13th Jul 20167:00 amRNSRestructure for Development of Tulu Kapi
30th Jun 201612:39 pmRNSResult of AGM
30th Jun 20167:00 amRNSAGM Statement
7th Jun 20163:25 pmRNSNotice of AGM and Publication of Annual Report
7th Jun 20167:00 amRNSFull Year Results 2015
7th Jun 20167:00 amRNSAppointment of preferred EPC contractor
2nd Jun 20162:51 pmRNSReduced Tulu Kapi Funding Requirements Replacement
2nd Jun 20167:00 amRNSReduced Tulu Kapi funding requirements
16th May 20167:00 amRNSGovernment of Ethiopia to invest $20m in Tulu Kapi
25th Apr 20161:06 pmRNSKEFI Minerals presenting at UK Investor Show 2016
14th Apr 20169:29 amRNSElectronic Communications
11th Apr 20167:00 amRNSFIRST QUARTER 2016 OPERATIONAL UPDATE

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.