Quarterly Operations Update Q2 2018

19 Jul 2018 07:00

RNS Number : 0745V
Jubilee Metals Group PLC
19 July 2018
 

Jubilee Metals Group PLC

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

("Jubilee" or "the Company")

 

Quarterly Operations Update

Q2 2018

 

Projects Highlights

 

· Hernic operational earnings increased 41 % to GBP 1.61 million (ZAR 27.69 million)

· Hernic project revenue up 25 % to GBP 3.31 million (ZAR 56.76 million)

· Hernic PGM* production up 18 % to 5 800 ounces

· Project earnings up 31 % to GBP 1.65 million (ZAR 28.32 million) which include GBP 0.082 million (ZAR 1.44 million) plant refurbishment expenditure at DCM

· Project revenue up 12 % to GBP 4.37 million (ZAR 75.06 million)

* 6 Element Platinum Group Metals

 

Leon Coetzer, Chief Executive Officer, says:

 

"The Hernic project continues to perform well. The increase in PGM ounces produced had a significant impact on the earnings soaring by more than 40 %. This jump in earnings reflects the low variable cost base for the project per PGM ounce produced. The lower feed supplies which hampered production in June has been overcome and the project is poised to break through 6 000 ounces per quarter.

 

Our operational footprint is rapidly expanding. The construction of the fines chrome recovery plant at DCM is underway and we have commenced with our PGM PlatCro project which targets to double our PGM processing rate by February 2019. We have also commenced with the construction of the zinc recovery circuit at Kabwe while the design of the lead recovery circuit is being concluded."

 

 

Hernic Platinum and Chrome Project (South Africa)

 

The Hernic operation performed well during Q2 2018 continuing to deliver increased PGM ounces at 5 800 PGM ounces delivered resembling an increase of 18 % quarter on quarter. Project earnings increased by 41 % quarter on quarter which reflects the low variable cost base per PGM ounce produced of the project. Q2 included a record production of 2100 PGM ounces in a single month. We expect to further increase this production rate in line with the increase in reclaimed surface material delivered by Hernic.

 

 

The table below presents the comparative quarterly performance of the Hernic project:

Tailings processed tonnes

PGM ounces delivered

Project revenue (GBP'000)1

Project revenue (ZAR'000)2

Project earnings3 (GBP'000)

Project earnings (ZAR'000)

Jubilee attributable earnings (GBP'000)

Jubilee attributable earnings (ZAR'000)

Unit cost / PGM oz (USD)4

Total Q3 2017

105 673

2 874

1.539

26.581

496

8.592

496

8.592

476

Total Q4

2017

121 644

3 755

2.047

37.011

965

17.466

965

17.466

382

Total Q1 2018

110 409

4 897

2.651

44.013

1.141

18.908

1.141

18.908

434

Total Q2 2018

119 479

5 800

3.308

56.761

1.612

27.686

1.612

27.686

397

Project to date

538 032

18 133

10.005

171.970

4.104

70.724

4.104

70.724

439

 

1= Revenue from the current project phase - 100% attributable to Jubilee until full capital recovery. Revenue is projected based on latest average PGM market prices and USD exchange rates and results are only final once final Quotational Period has passed

2= Average monthly conversion rates used

3= Project Earnings include all incurred operational costs including management services and mineral royalties

4= Unit cost includes provision for utility overhead.

 

 

 

DCM Project (South Africa)

The construction of the fine chrome recovery project is currently underway at DCM. The project targets to commission the new expanded fine chrome recovery circuit during Q4 2018. During this period we also increased our investment into the upgrade of the existing DCM chrome beneficiation plant as reflected in the financial numbers below. We are targeting to complete the fines chrome recovery plant during Q4 2018 which holds the potential to dramatically enhance the production of chrome at DCM.

 

Chrome production at DCM is expected to remain at current levels during the construction of the fine chrome recovery plant with the existing DCM material containing mostly fine chrome and enriched PGMs. Jubilee continues to have positive engagements with the Department of Mineral Resources to accelerate the approvals required to conclude the construction of the PGM recovery plant.

The table below presents the operational quarterly performance of the DCM project:

 

Chromite concentrate produced

tonnes

Project revenue (GBP'000)2

Project revenue (ZAR'000)

Project earnings3 (GBP'000)

Project earnings (ZAR'000)

Jubilee attributable earnings (GBP'000)

Jubilee attributable earnings (ZAR'000)

Total Q3 2017

15 134

1.129

19.526

184

3.173

356

6.139

Total Q4 2017

11 788

1.254

22.858

508

9.307

254

4.654

Total Q1 2018

 9 810

 1.240

 20.628

 245

 4.080

 123

 2.040

Total Q2 20181

9 461

1.066

18.297

741

1.2641

371

6321

Project to date4

139 920

15.241

263.388

7.860

135.669

2.818

49.193

 

1 = Includes GBP 82 000 (ZAR 1.44 million) plant refurbishment expenditure

2 = Average monthly conversion rates used

3 = Project earnings include project expenditure on plant and equipment

4= Since April 2017

 

 

PlatCro Platinum Project (South Africa)

 

Jubilee commenced delivering PGM material from its PlatCro project to Northam Platinum's Eland Platinum operation in June with 31 000 tonnes of material delivered during June. Jubilee has commenced with the expansion of the material sorting and de-watering plant at PlatCro to support the targeted ramp-up of material delivery to 50 000 tonnes per month. The target is to build a stockpile in excess of 200 000 tonnes of PGM rich material at the Eland Platinum concentrator prior to commencing platinum recovery in February 2019.

 

Kabwe Zinc, Lead and Vanadium Project (Zambia)

 

As announced previously the initial construction focus of the Kabwe project is on the zinc primary leach recovery circuit.

 

The enhanced process flow sheet for the Kabwe project includes a separated zinc and lead recovery circuit which significantly improves the flexibility of the metals recovery plant. This allows the project team to independently execute the zinc and lead metals recovery strategy. The decision was taken to commence with the construction of the zinc recovery circuit ahead of concluding the final design for the lead recovery circuit which is under design review. The circuit design review and optimisation test work includes work to determine the commercially optimal product purity specifications.

 

This enhanced process flowsheet has been presented to the Zambian department of mines who welcomed the significant progress made towards executing the Kabwe project.

 

We expect to conclude the final design parameters for the project during Q3 of 2018.

 

 

United Kingdom

19 July 2018

 Contacts

Jubilee Metals Group PLC

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913

Nominated Adviser

SPARK Advisory Partners LimitedMark Brady/Andrew EmmottTel: +44 (0) 203 368 3555

Broker

Shard Capital Partners LLPDamon Heath/Erik WoolgarTel +44 (0) 20 7 186 9900

JSE Sponsor

Sasfin Capital (a member of the Sasfin group)

Sharon OwensTel +27 (0) 11 809 7500

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDKMGMNDRZGRZM
Date   Source Headline
21st Jan 20257:00 amRNSAdditional power supply secured for Roan re-start
13th Jan 20257:00 amRNSOperational Update H1 FY2025
24th Dec 20247:00 amRNSHolding(s) in Company
16th Dec 20247:00 amRNSZambia Operations Update and Exercise of Options
21st Nov 20247:00 amRNSTR-1: notification of major holdings
20th Nov 20243:15 pmRNSExercise of Warrants
12th Nov 20242:20 pmRNSResult of AGM
7th Nov 20247:00 amRNSOperational Update Q1 FY2025
6th Nov 20242:30 pmRNSTR-1: Notification of major holdings
5th Nov 20247:00 amRNSAppointment of Remuneration Committee Chairperson
31st Oct 20247:00 amRNSBoard changes
16th Oct 20247:00 amRNSIntegrated Annual Report FY2024 & Notice of AGM
7th Oct 20247:00 amRNSNotice of Full Year Results Investor Presentation
7th Oct 20247:00 amRNSProject G Acquisition and Power Update
3rd Oct 20247:00 amRNSAudited Results for the year ended 30 June 2024
23rd Sep 20247:00 amRNSCopper Projects Update
19th Sep 20247:00 amRNSManagement changes
27th Aug 20247:00 amRNSPrivate Power Purchase Agreement in Zambia
21st Aug 20247:00 amRNSOperational Update Q4 FY2024
13th Aug 20247:00 amRNSRoan Front-End Module’s First Copper Concentrate
8th Aug 20247:30 amRNSRoan Upgrade Project Commences Operations
24th Jul 20241:00 pmRNSDirector/PDMR Shareholding
23rd Jul 20247:00 amRNSDirector/PDMR Shareholding
15th Jul 20247:00 amRNSChange of Broker
24th Jun 20247:00 amRNSRoll-out of Integrated Copper Strategy in Zambia
10th Jun 20242:10 pmRNSTR-1: Notification of major holdings
3rd Jun 20248:00 amRNSExercise of Warrants and Options
23rd Apr 20247:00 amRNSAppointment of Joint Corporate Broker
18th Apr 20247:00 amRNSOperational Update Q3 FY2024
28th Mar 20247:00 amRNSProjects Update
6th Mar 20243:00 pmRNSExercise of Options
6th Mar 20247:00 amRNSChanges to the Board & New Dedicated Exec Boards
29th Feb 20247:00 amRNSInterim Results 2023 Presentation
28th Feb 20249:31 amRNSInterim Results 2023 Presentation Re-scheduled
26th Feb 20247:00 amRNSInterim Financial Report 6 months to December 2023
8th Feb 20247:00 amRNSZambia Copper Expansion Update
23rd Jan 20247:00 amRNSOperational and Projects Update Q2 FY2024
4th Jan 20243:00 pmRNSTR-1: Notification of major holdings
3rd Jan 202412:00 pmRNSResults of General Meeting
15th Dec 20231:53 pmRNSResults of Placing and Notice of General Meeting
15th Dec 20237:00 amRNSProposed Placing
13th Dec 20232:30 pmRNSReply to Shareholder Correspondence Regarding a GM
12th Dec 20237:00 amRNSInvestment in Historical Waste Rock Dump in Zambia
21st Nov 20233:30 pmRNSInvestor Webcast
17th Nov 20237:00 amRNSNew Corporate Presentation
3rd Nov 20231:30 pmRNSResult of AGM
1st Nov 20237:05 amRNSQ1 Operational Report to 30 September 2023
17th Oct 20237:00 amRNSAward of New Slag Project with Mopani Copper Mines
11th Oct 20237:00 amRNSFinal Results and Notice of AGM
5th Oct 20237:00 amRNSNotice of Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.