Trading Update

 

Interserve, the international support services and construction group, provides an update on current trading, progress on its Energy from Waste contracts and net debt position.

Further to our 14th September trading update, our trading in the third quarter has seen a slowdown from that reported in the first half. In UK support services, this was driven by the continued employment cost pressures in the business, the cost of contract mobilisations, margin deterioration driven by a cost base which has not been flexible enough and contract performance in the justice business. Our UK construction business has seen further deterioration in operating profit as challenging market conditions and cost pressures as well as operational delivery issues have continued to impact performance. Our equipment services business is performing well and as anticipated, the international support services business has started to improve versus the first half performance and in international construction we have maintained a stable performance.

We now expect operating profit for the overall group in the second half to be approximately half the level of that which was reported in the second half of last year.

Additionally, further progress has been made on the Energy from Waste contracts in the quarter, but we have seen a slippage in the anticipated completion date for some of the contracts and we now anticipate, in addition to the ÂŁ160m provided in 2016, an additional ÂŁ35m provision is required and significant uncertainty remains on the timing of commissioning. Based on this provision, our additional net cash outflow for the rest of the programme is expected to be ÂŁ35m. The attached schedule provides more clarity on the scope of our exited Energy from Waste business.

Taking all of these factors into account, we now believe there is a realistic prospect that we will not meet the net debt to EBITDA test contained in our financial covenants for 31st December 2017. As previously announced, we are engaged in constructive and ongoing discussions with our lenders. We have engaged a financial advisor to assist us in these discussions, as well as looking at options to maximise the short and medium term cash generation from the business.

The company is launching a group wide performance improvement plan, Fit for Growth, aimed at improving margin performance to industry norms. As part of this, we have initiated a series of work streams to address our operating model and the cost base of our operations, as well as ensuring that we are operating in market segments which are both profitable and offer opportunity for growth. We have also initiated a comprehensive contract review across both the support services and construction businesses.

Work winning in the quarter has been strong with the order book standing at ÂŁ7.4bn. Recent contract wins include: Department of Work and Pensions, Magnox, Department for Transport, Ministry of Justice, Durham University, Dandara and Liwa Plastics (Oman). Retention also remains strong providing a stable platform for 2018.

Debbie White, Chief Executive, said, "Despite our challenges, Interserve has a strong client base and many strengths as an organisation and I believe there is considerable potential for business improvement across the company. My team will focus on improving our margin performance in UK support services and ensuring good contract selection in UK construction, while reducing our cost base across the company".

ENDS

 

Interserve chief executive Debbie White and chief financial officer Mark Whiteling are hosting a call for analysts and investors at 08.30am this morning to discuss today's announcement. Participant dial in details:Dial in number: +44 3333000804PIN: 95717429#URL for international dial in numbers: http://events.arkadin.com/ev/docs/NE_W2_TF_Events_International_Access_List.pdf 

For further information please contact:

Robin O'Kelly, Group Director of Communications +44 (0) 7786 702526

Michael Kinirons, CNC Communications +44 (0) 203 219 8816

 

This announcement contains inside information.

 

LEI: 549300MVYY4EZCRFHZ09.

Classification: Inside information

www.interserve.com

For news follow @interservenews

 

SCHEDULE:

LOCATION

CLIENT

INTERSERVE ROLE

PROCESS TECHNOLOGY

ANTICIPATED COMPLETION DATE *

INTERSERVE PROJECT SCOPE

Glasgow

Viridor

EPC Contractor

Gasification

N/A

Full EPC inc process

 

 

 

 

 

 

Derby

Derby City & County Councils

EPC Contractor

Gasification

H1 2018

Full EPC inc process

 

 

 

 

 

 

Peterborough

Viridor

EPC Contractor in joint venture

Mass Burn

Completed (2015)

Building & civils

 

 

 

 

 

 

Margam

Margam Green Energy Limited

EPC Contractor in joint venture

Biomass

H1 2018

Building & civils

 

 

 

 

 

 

Templeborough

Templeborough Biomass Power Plant Limited

EPC Contractor in joint venture

Biomass

H1 2018

Building & civils

 

 

 

 

 

 

Dunbar

Viridor

EPC Contractor in joint venture

Mass Burn

H1 2018

Building & civils

 

* Defined as completion of construction activity by Interserve Construction Limited. 

 

Commissioning activities may continue beyond these dates.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTGGGGPUUPMPGR
Date   Source Headline
30th Sep 20092:59 pmPRNDirector/PDMR Shareholding
25th Sep 200911:09 amPRNHolding(s) in Company
22nd Sep 20097:30 amPRNBlock Listing
10th Sep 20099:13 amPRNHolding(s) in Company
4th Sep 20094:13 pmPRNDirector/PDMR Shareholding
1st Sep 200910:34 amPRNDoc re Half-Year Report 30 June 2009
1st Sep 20098:25 amPRNDoc re Half-Year Report 30 June 2009
17th Aug 200910:57 amPRNHolding(s) in Company
13th Aug 200910:35 amPRNHolding(s) in Company
13th Aug 20097:00 amPRNRe Contract
11th Aug 20097:00 amPRNContract win
11th Aug 20097:00 amPRNHalf-yearly Report
10th Aug 200911:23 amPRNDirector/PDMR Shareholding
3rd Aug 20097:00 amPRNRe Contract
31st Jul 200910:16 amPRNRe Contract
28th Jul 20092:48 pmPRNChange of Adviser
20th Jul 20097:00 amPRNContract win
10th Jul 20097:00 amPRNInterim Management Statement
10th Jul 20097:00 amPRNRe Contract
2nd Jul 20099:28 amPRNHolding(s) in Company
1st Jul 20099:00 amPRNBlocklisting - Interim Review
30th Jun 20093:32 pmPRNTotal Voting Rights
25th Jun 200910:31 amPRNDirector/PDMR Shareholding
24th Jun 20094:21 pmPRNDirector/PDMR Shareholding
10th Jun 20099:36 amPRNRe Contract
1st Jun 20097:00 amPRNRe Contract
22nd May 20097:00 amPRNENNISKILLEN HOSPITAL PFI £270m FINANCIAL CLOSE
19th May 20097:00 amPRNRe Contract
14th May 200911:25 amPRNHolding(s) in Company
12th May 20091:07 pmPRNResult of AGM
12th May 20097:00 amPRNInterim Management Statement
30th Apr 20098:55 amPRNAnnual Information Update
22nd Apr 20091:57 pmPRNDirector/PDMR Shareholding
21st Apr 20097:00 amPRNRe Contract
21st Apr 20097:00 amPRNInvestor Seminar
17th Apr 20094:11 pmPRNHolding(s) in Company
16th Apr 20097:00 amPRNPFI Cash Generation
8th Apr 20094:16 pmPRNDirector/PDMR Shareholding
8th Apr 20094:14 pmPRNHolding(s) in Company
8th Apr 20098:59 amPRNAnnual Financial Report
30th Mar 20091:22 pmPRNDirector/PDMR Shareholding
24th Mar 20094:21 pmPRNDirector/PDMR Shareholding
23rd Mar 20094:42 pmPRNDirector/PDMR Shareholding
17th Mar 200912:51 pmPRNDirector/PDMR Shareholding
16th Mar 200911:07 amPRNHolding(s) in Company
16th Mar 20097:00 amPRNRe Contract win
11th Mar 20097:01 amPRNRe Contract
11th Mar 20097:00 amPRNFinal Results
5th Feb 20097:00 amPRNContract Win
26th Jan 20097:00 amPRNRe Contract

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.