Operational update

19 Oct 2022 07:00

RNS Number : 3337D
IOG PLC
19 October 2022
 

19 October 2022

 

IOG plc

 

Operational update

 

IOG plc ("IOG", or "the Company"), (AIM: IOG.L), the Net Zero UK gas and infrastructure operator focused on high return projects, provides a Phase 1 operational update.

 

Headlines:

 

- Drilling fluid losses at Southwark A1 well have continued in the Bunter Shale Formation

- A1 has been suspended to enable A2 well stimulation operations to proceed as planned for First Gas in Q4, before resuming A1

- Saturn Banks to be shut-in for a total of four weeks, including depressurising the line ahead of the Bacton terminal shutdown, to enable the final subsea connection to Southwark

- Average 2H 2022 production to date of 28.6 mmscf/d, constrained by aqueous liquids production at Blythe, at an average realised price of 258 p/therm

- Blythe H1 well ultimate recoverable gas volumes estimated at 29 BCF and Elgood at 7.5 BCF - options to optimise recovery are being evaluated

- 2H 2022 production guidance revised from 30-50 mmscf/d to 22-28 mmscf/d

 

Southwark Drilling

 

After extensive drilling fluid losses in the 12-1/4" section in the Bunter Sandstone Formation, the Southwark A1 well progressed into the Bunter Shale Formation, where further fluid losses have been encountered on drilling out of the 9-5/8" casing shoe. This has no bearing on the Southwark reservoir itself which lies well below this section.

 

The losses have not yet been sufficiently cured to drill ahead safely and the resulting delays have reduced the time available before the scheduled arrival of the hydraulic stimulation vessel. After careful consideration of the options with the relevant contractors, IOG has therefore decided to securely suspend the A1 well in order to proceed with hydraulic stimulation and commissioning of A2 to deliver Southwark first gas in Q4 as planned. Based on the current schedule and subject to further operational risks, this would be achievable by mid-December.

 

In parallel, several options to mitigate fluid losses and drill ahead at A1 are being worked through in preparation for completing and producing the well after bringing on A2.

 

Southwark Subsea, Hook-up and Commissioning

 

The Seven Atlantic Diving Support Vessel has been operating offshore to connect the outer section of the Saturn Banks Pipeline System (SBPS) from the 24" manifold to the Southwark platform, to prepare for the introduction of gas from Southwark. Due to a defective 6" offshore valve the SBPS will need to be depressurised in order to connect the outer section safely to the manifold. Saturn Banks production will therefore be suspended in late October for approximately four weeks, including the November Bacton terminal annual shutdown.

 

Blythe Field 

 

Blythe production has been constrained by liquids handling capacity at the Bacton terminal and the need for offsite storage, processing and disposal of saline aqueous liquids being produced from the H1 well. H1 was drilled into the field's southeast high, which was considered the optimal route to drain the field. Latest analysis of production and reservoir pressure data from the first six months of H1 production indicates that the well is located in a reservoir compartment which is materially baffled from the central and northwest areas of the field and will ultimately recover an estimated 29 billion cubic feet (BCF), compared to the management estimated reserves of 1P/2P/3P 25.4/42.5/55.8 BCF. The Company is evaluating options to further optimise recovery.

 

Elgood Field

 

Production and reservoir pressure data from the six months since First Gas at Elgood has also been technically assessed. The Elgood production rate recently fell below 10 mmscf/d and is expected to decline further by year end. The decline in flow rate has been faster than anticipated given the pre-production estimated reserves range of 1P/2P/3P 9.7/14.1/18.3 BCF. The latest analysis indicates that gas is not flowing across the NW-SE oriented intra-field fault to the wellbore as expected. As a result, the most likely ultimate recovery from the field is now assessed to be 7.5 BCF, of which approximately 4 BCF has been produced to date.

 

Combined flow rates from Blythe and Elgood over 2H 2022 to date have averaged 28.6 mmscf/d, at a volume weighted average price of 258 p/therm. Based on this, and noting the upcoming four-week outage, the expected average gross production rate over 2H 2022 has therefore been revised from 30-50 mmscf/d to 22-28 mmscf/d.

 

Andrew Hockey, CEO of IOG, commented:

 

"Drilling the Southwark A1 well has continued to be very challenging with further fluid losses at the base of the Bunter Shale. To preserve the opportunity to deliver first gas in this quarter, we have decided to suspend operations on A1 in order to ensure that A2 stimulation work proceeds in the scheduled window. We plan to resume, complete and produce A1 after bringing A2 onstream.

 

Final connection of the Saturn Banks Pipeline System to Southwark has been affected by a defective 6" valve at the offshore 24" manifold. To enable safe connection, the line will be depressurised ahead of the Bacton terminal November shutdown, requiring an expected overall outage of four weeks.

 

Over 2H 2022 to date, Saturn Banks production rates have been constrained to 28.6 mmscf/d by limits on aqueous liquids storage, processing and disposal routes, which we continue to work up several options to resolve. Latest analysis indicates that the Blythe H1 well will ultimately recover 29 BCF, given limited connectivity to other parts of the field and that Elgood is a smaller structure than previously estimated, with projected ultimate recovery of 7.5 BCF. In this context, we have reforecast 2H 2022 production guidance to 22-28 mmscf/d."

 

Competent Person's Statement

In accordance with the AIM Note for Mining and Oil and Gas Companies, IOG discloses that Andrew Hockey, IOG's CEO, is the qualified person that has reviewed the technical information contained in this document. Andrew Hockey has an MSc in Petroleum Geology and has been a member of the Petroleum Exploration Society of Great Britain since 1983. He has over 40 years' operating experience in the upstream oil and gas industry. Andrew Hockey consents to the inclusion of the information in the form and context in which it appears.

 

This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 ("MAR"), and is disclosed in accordance with the company's obligations under Article 17 of MAR.

 

Enquiries:

 

IOG plc

Andrew Hockey (CEO)

Rupert Newall (CFO)

James Chance (Head of Capital Markets & ESG)

 

+44 (0) 20 7036 1400

finnCap Ltd

Christopher Raggett / Simon Hicks

 

+44 (0) 20 7220 0500

Peel Hunt LLP

Richard Crichton / David McKeown 

+44 (0) 20 7418 8900

 

Vigo Consulting

Patrick d'Ancona / Finlay Thomson

 

+44 (0) 20 7390 0230

About IOG:

 

IOG is a Net Zero UK gas and infrastructure operator focused on high-return projects. The Company's operations are currently concentrated around its offshore and onshore Saturn Banks infrastructure in the UK Southern North Sea. Phase 1 of its Saturn Banks Project, which started production in March 2022, entails the commercialisation of the Blythe, Elgood and Southwark gas fields through this infrastructure. Phase 2 of the Saturn Banks Project entails the Nailsworth, Goddard and Elland gas discoveries, which are subject to future investment decisions and expected to be commercialised through the same export infrastructure. The Company also holds further licences with additional resources including the Abbeydale, Panther and Grafton gas discoveries, the Kelham North, Kelham Central, Thornbridge and Thornbridge Deep prospects, and part of the Orrell gas discovery. Currently, all IOG's licences are held 50:50 with its joint venture partner CalEnergy Resources (UK) Limited and operated by IOG. In addition, the Company continually evaluates further opportunities for accretive portfolio additions to help generate additional shareholder returns. Further details are available at www.iog.co.uk.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDLVLLFLBLBFBB
Date   Source Headline
26th Oct 20227:00 amRNSIssue of Equity and Director/PDMR Dealings
21st Oct 20224:41 pmRNSSecond Price Monitoring Extn
21st Oct 20224:35 pmRNSPrice Monitoring Extension
21st Oct 20227:00 amRNSDirector & PDMR Dealings
20th Oct 20222:06 pmRNSSecond Price Monitoring Extn
20th Oct 20222:00 pmRNSPrice Monitoring Extension
20th Oct 202212:31 pmRNSFinancial Update
20th Oct 20227:00 amRNSBoard and Executive changes
19th Oct 20229:05 amRNSSecond Price Monitoring Extn
19th Oct 20229:00 amRNSPrice Monitoring Extension
19th Oct 20227:00 amRNSOperational update
30th Sep 20227:00 amRNSProduction Update
2nd Sep 202211:45 amRNSIssue of Equity and PDMR Shareholding
25th Aug 20227:00 amRNSHalf-year Report
24th Aug 20222:24 pmRNSHolding(s) in Company
14th Jul 202210:38 amRNSIssue of Equity
4th Jul 20227:00 amRNSInvestor Presentation
27th Jun 202211:16 amRNSTR-1
22nd Jun 202212:38 pmRNSTR-1
22nd Jun 202210:48 amRNSTR-1
21st Jun 20224:40 pmRNSSecond Price Monitoring Extn
21st Jun 20224:36 pmRNSPrice Monitoring Extension
21st Jun 20222:53 pmRNSTR-1
20th Jun 20227:00 amRNSCorporate Update
6th Jun 20229:52 amRNSTR-1
1st Jun 20223:28 pmRNSDirector/PDMR Shareholding
1st Jun 20227:00 amRNSOperational Update
23rd May 20227:00 amRNSOperational Update
13th May 20227:28 amRNSIssue of Equity and PDMR Shareholding
10th May 202212:11 pmRNSTR-1
3rd May 20225:26 pmRNSResult of AGM
3rd May 20227:00 amRNSOperational Update
25th Apr 20222:37 pmRNSNotice of AGM
13th Apr 20227:00 amRNSOperational Update
8th Apr 20229:42 amRNSHolding(s) in Company
4th Apr 20227:00 amRNSOperational Update
29th Mar 20227:00 amRNSOperational Update
17th Mar 20227:05 amRNSShare Options to Incentivise Long Term Performance
17th Mar 20227:00 amRNSFinal Results for the Year Ended 31 December 2021
16th Mar 20221:33 pmRNSTR-1
16th Mar 20227:00 amRNSElgood First Gas
15th Mar 20224:41 pmRNSSecond Price Monitoring Extn
15th Mar 20224:35 pmRNSPrice Monitoring Extension
14th Mar 20227:00 amRNSPhase 1 First Gas
11th Mar 20222:00 pmRNSGas Sales Agreement
9th Mar 20225:36 pmRNSTR-1
4th Mar 20224:00 pmRNSStart of Backgassing
1st Mar 20225:48 pmRNSUpdate on gas sales arrangements
24th Feb 20224:55 pmRNSIssue of Equity
21st Feb 20227:00 amRNSPhase 1 Progress

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.