Independent Oil and Gas plc ("IOG" or the "Company"), the development and production focused Oil and Gas Company, is pleased to provide an operational update on its Southern North Sea dual hub development project, the Thames Pipeline Intelligent Pigging Programme ("IPP"), and Harvey.

Highlights

· Contract with Subsea7 signed to provide a Diving Support Vessel ("DSV") to execute the offshore scope of work for the IPP.

· 3D seismic reprocessing to Pre-Stack Depth Migration underway over the Harvey structure to optimise the appraisal well location.

· New Drilling Manager appointed, Gordon McCaig, who will become IOG's Well Integrity Authority for the Harvey well and the ten development wells that IOG will drill on the Blythe Hub and Vulcan Satellites Hub.

· Environmental Impact Assessment for the Vulcan Satellites Hub was submitted to the Department of Energy and Industrial Strategy ("BEIS") on 24 April 2018.

 

Ahead of the IPP commencing, the DSV mobilised to location on 26 April 2018 and has commenced work. The IPP will include pressure tests of the Thames Pipeline before and after pigging operations. The Initial IPP and pressure test results are expected by early June 2018.

 

In addition to the IPP, the Front End Engineering and Design ("FEED") contract has been awarded to Wood, a reputable international engineering house, for the subsea and pipelines scope of work on the dual hub development. Platform fabrication FEED was completed by Heerema Fabrication Group on 30 April 2018 and design notification will be submitted to the UK Health and Safety Executive ("HSE") shortly.

 

The Company remains on schedule for Field Development Plan ("FDP") approvals for the Blythe and Vulcan Satellites Hubs by the end of August 2018, with first gas planned in Q4 2019.

Andrew Hockey, CEO of IOG commented:

"We are pleased to have progressed from the onshore mechanical preparation stage of the Thames Pipeline Intelligent Pigging Programme, which commenced in February, to the crucial offshore stage of operations. This pigging is an essential step in confirming to all stakeholders that our proven and fully-licensed 2P reserves of over 300 BCF can be produced safely and efficiently via the recommissioned Thames Pipeline. Owning high-capacity export infrastructure is a major strategic advantage in further developing our UK Southern North Sea portfolio.

 

In parallel with the Intelligent Pigging Programme we continue to make good progress toward completing the necessary engineering and technical studies and submissions to the regulatory bodies to support our Final Investment Decision ("FID") for which we remain on track by the end of August. We look forward to providing further updates on the pigging programme, progress toward final investment decision and the appraisal well at Harvey at the earliest opportunity.

 

In addition to unlocking the value from our development and appraisal assets, the Company continues to seek opportunities for further portfolio expansion through selective asset acquisitions and licensing rounds."

 

-ENDS-

 

Certain information communicated in this announcement was, prior to its publication, inside information for the purposes of Article 7 of Regulation 596/2014.

 

Enquiries:

Independent Oil and Gas plc

Andrew Hockey (CEO)

James Chance (CFO)

+44 (0) 20 3879 0510

finnCap Ltd

Christopher Raggett / Anthony Adams

(Corporate Finance)

Emily Morris / Camille Gochez

(Corporate Broking)

+44 (0) 20 7220 0500

Camarco

Georgia Edmonds / Tom Huddart / Monique Perks

+44 (0) 20 3757 4980

 

 

Notes

About Independent Oil and Gas:

IOG owns substantial low risk, high value gas Reserves in the UK Southern North Sea. The Company is targeting a 2P peak production rate in excess of 200 MMcfd (c. 35,000 Boe/d) from its substantial current portfolio (2P Reserves of 303 bcf) via an efficient hub strategy. Alongside this it continues to pursue value accretive acquisitions, to generate significant shareholder returns. All IOG's licences are owned 100% and operated by IOG.

Further information can be found on www.independentoilandgas.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDWGUCACUPRPWU
Date   Source Headline
25th Jan 20227:00 amRNSOperational Update
10th Jan 20227:00 amRNSUpdate on Southwark drilling operations
31st Dec 20217:00 amRNSSouthwark Development Well Spud
29th Dec 20217:00 amRNSSouthwark drilling update
14th Dec 20217:00 amRNSOperational Update
22nd Nov 20217:00 amRNSCorporate and Operational Update
22nd Oct 202112:02 pmRNSTR-1
11th Oct 20213:46 pmRNSUpdate on Southwark drilling operations
8th Oct 20212:25 pmRNSTR-1
30th Sep 202111:54 amRNSIssue of Equity
29th Sep 20214:38 pmRNSTR-1
29th Sep 20217:00 amRNSSuccessful Blythe Development Well Flow Test
28th Sep 20215:13 pmRNSTR-1
28th Sep 20212:19 pmRNSTR-1
28th Sep 202111:08 amRNSTR-1
28th Sep 20218:20 amRNSDirector/PDMR Shareholding
27th Sep 20213:05 pmRNSTR-1
23rd Sep 202111:31 amRNSResult of Oversubscribed Placing & Subscription
23rd Sep 20217:00 amRNSProposed Placing and Subscription
26th Aug 20217:00 amRNSInterim Results
17th Aug 20213:58 pmRNSIssue of Equity
16th Aug 20218:53 amRNSIssue of Equity
4th Aug 20217:00 amRNSCommitment to Net Zero from 2021
3rd Aug 20217:04 amRNSBlythe Development Well Spud
29th Jul 20217:00 amRNSSigning of Gas Sales Agreement
19th Jul 20219:05 amRNSSecond Price Monitoring Extn
19th Jul 20219:00 amRNSPrice Monitoring Extension
19th Jul 20217:00 amRNSElgood Development Well 48/22c-7 Flow Test Results
7th Jun 20217:11 amRNSInstallation of Blythe and Southwark platforms
1st Jun 20215:43 pmRNSIssue of Equity
17th May 20217:00 amRNSPhase 1 Duty Holder and Operations Contract Award
14th May 20215:21 pmRNSShare Options to Incentivise Long Term Performance
14th May 20217:00 amRNSCollaboration Agreement with GeoNetZero CDT
27th Apr 20216:03 pmRNSResult of AGM and Change of Name
26th Apr 20217:00 amRNSCompletion of Phase 1 Platforms
22nd Apr 20212:09 pmRNSTR-1
21st Apr 202110:13 amRNSTR-1
15th Apr 202112:41 pmRNSTR-1
12th Apr 20212:35 pmRNSTR-1
12th Apr 20217:00 amRNSStart of Phase 1 Development Drilling Campaign
29th Mar 20215:47 pmRNSTR-1
29th Mar 20214:12 pmRNSTR-1
26th Mar 20219:46 amRNSIssue of Equity / PDMR Shareholding
25th Mar 202112:25 pmRNSConversion of Salaries/Fees into Share Options
18th Mar 20217:00 amRNSFinal Results for the Year Ended 31 December 2020
15th Mar 20217:00 amRNSGoddard and Abbeydale Area Technical Update
18th Feb 20215:56 pmRNSIssue of New Shares
8th Feb 20217:00 amRNSAppointment of New Chief Operating Officer
3rd Feb 202112:00 pmRNSDirector/PDMR Shareholding
28th Jan 20217:00 amRNSShare Options to Incentivise Long Term Performance

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.