Project Update

9 May 2019 17:56

RNS Number : 5827Y
Infrastrata PLC
09 May 2019
 

 

9 May 2019

 

InfraStrata plc

("InfraStrata" or the "Company")

 

Project Update

 

InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to provide an update on recent progress with the Company's Islandmagee gas storage project (the "Project").

 

The Company is at an advanced stage in negotiations with the final two potential offtake partners and the board of InfraStrata believes these negotiations will reach a conclusion in the near future. It may be that InfraStrata is able to secure an offtake deal for all seven caverns (phase 1 &2) rather than just the two caverns originally planned for in phase 1. If this is the case, FID (final investment decision) for phase 2 (five caverns) may be advanced by approximately 12 months from Q4 2020 to Q4 2019, with the knock-on effect of this that FID for phase 1 is delayed by six months to end 2019 due to phases 1 and 2 being addressed together. However, overall this would represent a six month improvement on phase 2 FID and bring the benefits of a larger project than phase 1 alone. However, this is still only another indicative scenario and the final terms and timing of any offtake agreement cannot be guaranteed at this stage. Once an offtake agreement has been signed the Company will be able to provide details of the final agreement and an update on dates for FID.

 

If the scenario materialises where further up front work is required to undertake FID on all 7 caverns (phase 1 & 2), a convertible loan facility may be provided by a potential equity partner to seek to ensure that the first gas date is not effected and the Project is further de-risked.

 

In relation to the draft marine license, InfraStrata has now provided the relevant authorities with the final draft reports requested and following feedback received, the Company is currently in the process of updating these reports and will re-submit them to the relevant authorities shortly. As previously mentioned, the Company sees no reason that a full marine license will not be issued for the Project in due course.

 

The Company has now submitted the final EU application for the FEED study that was completed last year and the sum of EUR1.6 million is expected to be received in the next 8 weeks from the EU. In addition, the Company is looking to submit applications for additional grants for circa EUR8 million in relation to FEED studies for the reverse flow of the existing Scottish Northern Ireland Pipeline (SNIP) (in conjunction with Mutual Energy) and twinning of that pipeline.

 

InfraStrata continues advancing its studies for future project development opportunities on the potential FSRU (floating storage regasification unit) opportunity and additional caverns, moving from the concept development stage to a feasibility study in the near future. In addition, as previously advised, we continue to evaluate other potential energy related infrastructure projects, one of which is other potential salt storage opportunities in the UK.

 

All land purchases and easements have been completed apart from purchasing plots 1 and 1.1, which were delayed after a request from the land owner to provide a further extension. The cost of these lots is agreed and they are due to complete by the end of June.

 

John Wood, Chief Executive Officer, commented: "As we reach the final stage of our offtake negotiations an additional scenario has arisen that may see FID taken for phases 1 and 2 at the same point in time, which may affect our previously advised FID date of H1 2019 for phase 1 (2 caverns). We are extremely pleased with the rate of progress of all the negotiations that are ongoing and are confident of reaching a conclusion on our offtake negotiations in the near future, which will in turn drive the other workstreams in the Project ".

 

 

For further information, please contact:

 

InfraStrata plc

John Wood, Chief Executive

 

c/o Yellow Jersey

+44 (0)20 3735 8825

Allenby Capital Limited (AIM Nominated Adviser & Joint Broker)

Jeremy Porter / Liz Kirchner

 

+44 (0)20 3328 5656

SI Capital Limited (Joint Broker)

Nick Emerson

 

+44 (0) 20 3871 4038

Yellow Jersey

Tim Thompson  

+44 (0)20 3735 8825

 

 

-ENDS-

 

Notes to editors:

 

InfraStrata is an independent gas storage company focused on the UK and Ireland. Further information is available on the Company's website: www.infrastrataplc.com 

 

Background on the Islandmagee Storage Project

 

The Islandmagee gas storage project is a proposed salt cavern gas storage facility located on Islandmagee in County Antrim, Northern Ireland. The Board of InfraStrata believes that the proposed 500 million cubic metres natural gas cavern storage facility will provide over 25% of the UK's natural gas storage once constructed. The facility will be situated adjacent to the Scotland Northern Ireland (gas) Pipeline (SNIP) and the Moyle 500 megawatt electricity interconnector. Work commenced in 2007 with the acquisition of 3D seismic data to image the Permian salt in the Larne Lough area. During 2012, planning permission was granted for the project and a gas storage licence was issued by the Utility Regulator. In 2015 a well was drilled to core the salt and confirm the technical feasibility of the project, supported in part by the European Commission. The Front End Engineering and Design (FEED) element of the project was completed in November 2018 and the FEED report was submitted to the European Union in December 2018 in accordance with the Company's grant conditions. To date approximately £14.5m has been invested in the project.

 

Further information is available on the company's website: www.infrastrataplc.com 

 

 

 

The Front End Engineering & Design (FEED) and Insitu Downhole Testing programme for the Islandmagee gas storage project is co-financed by the European Union's Connecting Europe Facility.

 

Disclaimer releasing the European Union from any liability in terms of the content of the dissemination materials:

 

"The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein."

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDALMFTMBAMBJL
Date   Source Headline
25th Jan 201912:16 pmRNSHolding(s) in Company
24th Jan 20193:25 pmRNSHolding(s) in Company
24th Jan 20197:00 amRNSPlacing to raise £1.5 million
21st Jan 20197:00 amRNSReplacement - Exercise of warrants & change to TVR
18th Jan 20194:44 pmRNSExercise of warrants and change to TVR
17th Jan 20197:00 amRNSApplication for inclusion on the 4th PCI List
16th Jan 20196:24 pmRNSPDMR/PCA Notification
15th Jan 201911:00 amRNSPrice Monitoring Extension
15th Jan 20199:05 amRNSSecond Price Monitoring Extn
15th Jan 20199:00 amRNSPrice Monitoring Extension
14th Jan 20197:00 amRNSGrant of options
10th Jan 20195:27 pmRNSExercise of warrants and change to TVR
10th Jan 20197:00 amRNSExercise of warrants and change to TVR
8th Jan 20195:28 pmRNSIssuance of contractual fee shares
7th Jan 20197:00 amRNSFinal results and notice of annual general meeting
7th Jan 20197:00 amRNSExercise of warrants and total voting rights
3rd Jan 20192:00 pmRNSPrice Monitoring Extension
31st Dec 201812:30 pmRNSTotal Voting Rights
27th Dec 20187:00 amRNSIslandmagee - Project Funding Update
21st Dec 20184:58 pmRNSIslandmagee Gas Storage Project - Land Update
21st Dec 20187:00 amRNSIslandmagee - Issue of Invitation to Tender
19th Dec 20187:00 amRNSBoard Change
18th Dec 201810:12 amRNSExercise of warrants and total voting rights
18th Dec 20187:00 amRNSIslandmagee - Application for additional Licence
17th Dec 20182:51 pmRNSExercise of warrants and total voting rights
13th Dec 20187:00 amRNSExercise of warrants and total voting rights
7th Dec 20184:28 pmRNSExercise of warrants & total voting rights
5th Dec 20187:00 amRNSFinal FEED Milestone & Additional Concept Studies
5th Dec 20187:00 amRNSShareholder update meeting and presentation
30th Nov 20185:00 pmRNSTotal Voting Rights
30th Nov 20187:00 amRNSExercise of warrants and total voting rights
27th Nov 20187:00 amRNSReplacement - Completion of FEED & P90 Estimate
22nd Nov 201812:42 pmRNSCompletion of FEED & P90 Estimate
19th Nov 20185:30 pmRNSIssuance of fee shares and Total Voting Rights
8th Nov 20182:54 pmRNSIslandmagee Gas Storage Project - Offtake Update
31st Oct 20187:00 amRNSShareholder update meeting and presentation
30th Oct 20185:55 pmRNSHolding(s) in Company
29th Oct 20181:38 pmRNSIslandmagee Gas Storage Project - Land Options
29th Oct 20187:00 amRNSHolding(s) in Company
25th Oct 20187:00 amRNSLaunch of new website & change of website address
22nd Oct 201811:38 amRNSIslandmagee - Subsurface Milestones Completed
15th Oct 20187:00 amRNSIslandmagee Project - New EU Grant Application
11th Oct 20187:00 amRNSIslandmagee Update: Major FEED Milestone Completed
8th Oct 201812:12 pmRNSDirector Shareholding
5th Oct 20189:36 amRNSDirector shareholding
5th Oct 20187:00 amRNSDirector shareholding
3rd Oct 201811:31 amRNSDirector Shareholding
2nd Oct 201812:00 pmRNSDirector Shareholding
2nd Oct 20187:00 amRNSDisposal-Legacy Hydrocarbon Exploration Interests
28th Sep 20185:00 pmRNSTotal Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.