Islandmagee Gas Storage Project Update

6 Aug 2018 07:00

RNS Number : 8529W
Infrastrata PLC
06 August 2018
 

 

 

6 August 2018

 

InfraStrata plc

("InfraStrata" or the "Company")

 

Islandmagee Gas Storage Project Update

 

InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to provide an update on FEED (Front End Engineering Design) progress having now achieved over 50% of the pre-established milestones.

 

The FEED commenced in May 2018 and is scheduled to be delivered in accordance with the EU Grant provisions by no later than December 2018. The FEED is being delivered on time and on budget by our world class supply chain partners. To date there have been no significant design issues that will prevent the Project being constructed as planned in order to meet its key objectives.

 

Further information is also provided below in respect of our commercial endeavours including in respect of potential funding partners to enable construction of the Project and the potential for the Company to secure an offtake partner.

 

 

John Wood, Chief Operating Officer, who is leading the FEED works on behalf of InfraStrata stated:

 

'Since I commenced working with InfraStrata in February we have made tremendous progress in terms of contracting and progressing the FEED, which is being undertaken by global experts in their field.

 

Reaching the EOI (Expression of Interest) stage is a significant milestone for InfraStrata as we move towards the funding and construction stage of the Project. 

 

As FEED has progressed, I have been spending time in conjunction with the rest of the Board to realign our processes and procedures to be ready for the construction phase of the Project.'

 

 

Set out below is a list of the key milestones and their progress (of notable interest is that milestone 9 has been completed several weeks ahead of schedule):

 

Current Milestone Progress

 

Milestone

Month

Description

Responsibility

Status

1

April

Contract Award Costain

InfraStrata

√ - Completed

2

May

Contract Award DEEP

InfraStrata

√ - Completed

3

May

Appointment of Subsurface Expert

InfraStrata

√ - Completed

4

May

Issue FEED schedule, project and quality plans

Costain

√ - Completed

5

May

Current Design Agreed

Costain

√ - Completed

6

June

Current Design Agreed

DEEP KBB

√ - Completed

7

June

Appoint Owners Engineer for FEED

InfraStrata

√ - Completed

8

July

Issue Process Flow Diagrams

Costain

√ - Completed

9

August

Gas & Leaching layout review

Costain

√ - Completed

10

August

All Process & Instrumentation Diagrams

Costain

11

Oct.

Engineering Design Complete

Costain

12

Oct.

All Investigation work on samples complete

DEEP KBB

13

Oct.

Cavern Design & Rock Mechanics Complete

DEEP KBB

14

Nov.

Surface FEED Deliverables & Estimates

Costain

15

Nov.

Subsurface FEED Deliverables & Estimates

DEEP KBB

16

Dec.

Submit Reports To EU

InfraStrata

 

 

During the course of the FEED, the HAZOP (Hazard and Operability Study), HAZID (Hazard Identification Study) and ENVID (Environmental Impact Identification) reviews have been undertaken. These have been chaired by independent industry subject matter experts. Results and actions from these studies were consistent with FEED projects at similar levels of maturity in design. Whilst progressing through FEED, the Company has undertaken a plethora of further studies (as required by the EU grant); the objective of which is to substantially reduce the 'Project Risk' as it proceeds through to 'construction ready' status.

 

Regular and positive engagement sessions have, and continue, to be held with the regulatory authorities and Stakeholders (such as the network operator). This is helping to shape the design of the Project to maximise the connectivity and market share from the known and future gas infrastructure network.

 

The FEED works are being undertaken to account for the Project's phased approach. This will ensure it facilitates a simple integration of Phase Two (Caverns 3-8) after the Phase One caverns (1 and 2) are in operation.

 

A further study has been commissioned by the Company to review the remaining options and market demand for a potential Phase Three to this project. This is predicated on the impact of other gas storage facilities being closed and the potential for increased demand for hydrocarbon storage. Further investigative work is being undertaken, in conjunction with other stakeholders, to ensure additional infrastructure is developed to fully exploit the full potential of the Islandmagee site in the future.

 

Project Commercial

 

The EU grant is being drawn down monthly to pay 50% of all FEED services eligible for payment under the grant. All grant monies that can be advanced to the Company have now been received. The final grant claim is expected to be made in December 2018 upon completion of the FEED.

 

The contractor loan notes have also been utilised to make payment against the requisite FEED services for which they were provided.

 

The Company has also been in contact with the EU to seek opportunities for further grant funding towards the cost of the construction works by virtue of its "Project of Common Interest" status. Should the Company be able to take advantage of any other EU grants, further announcements will be made as applicable.

 

In advance of the Final Investment Decision (FID) before the construction phase can begin, the Company has commenced discussions with a number of major EPC (Engineering Procurement and Contracting) organisations and will be inviting those organisations to issue an EOI (Expression of Interest) for Phase one of the construction project which focuses on the initial two caverns. The chosen contractor will then work on preparing a priced contract in the coming months. This process is being undertaken in compliance with the procurement process stipulated by the Company's EU grant.

 

 

Discussions are ongoing with several potential funding partners within the UK, Europe and internationally. The Board considers that the broad range of potential funding partners and their geographic spread demonstrates the global need for and attraction of gas storage. Such funds would complement the funds available under the UK Guarantee Scheme and the Company continues to utilise the services of CBRE Capital Advisors which has a proven track record of raising capital and working for major financial institutions as financial advisor on large infrastructure projects.  

 

As previously announced, the Company has held detailed discussions with major gas storage and trading companies with a view to securing an offtake partner for the facility, once it has been constructed, and these discussions continue to progress well with the investment decisions, commercial returns and duration of the relationship being clearly understood by all parties. Further updates will be made as appropriate.

 

 

 

For further information, please contact:

 

InfraStrata plc

Adrian Pocock, Chief Executive

 

c/o Yellow Jersey

+44 (0)20 3735 8825

Allenby Capital Limited (AIM Nominated Adviser & Joint Broker)

Jeremy Porter / Alex Brearley / Liz Kirchner

 

+44 (0)20 3328 5656

SI Capital Limited (Joint Broker)

Nick Emerson

 

+44 (0) 20 3871 4038

Yellow Jersey

Tim Thomson  

+44 (0)20 3735 8825

 

 

-ENDS-

 

Notes to editors:

 

InfraStrata is an independent gas storage company focused on the UK and Ireland. Further information is available on the Company's website: www.infrastrata.co.uk.

 

Background on the Islandmagee Storage Project

The Islandmagee gas storage project is a proposed salt cavern gas storage facility located on Islandmagee in County Antrim, Northern Ireland. The Board of InfraStrata believes that the proposed 500 million cubic metres Natural Gas Cavern Storage facility will provide over 25% of the UK's Natural Gas Storage once constructed, and will be situated adjacent to the Scotland Northern Ireland (gas) Pipeline (SNIP) and the Moyle 500 Megawatt Electricity Interconnector. Work commenced in 2007 with the acquisition of 3D seismic data to image the Permian salt in the Larne Lough area. During 2012, planning permission was granted for the project and a gas storage licence was issued by the Utility Regulator. In 2015 a well was drilled to core the salt and confirm the technical feasibility of the project, supported in part by the European Commission. The Front End Engineering and Design (FEED) element of the Project is scheduled for completion by the end of 2018. To date approximately £11.5m has been invested in the Project.

 

Further information is available on the company's website: www.infrastrata.co.uk

 

 

 

The Front End Engineering & Design (FEED) and Insitu Downhole Testing programme for the Islandmagee gas storage project is co-financed by the European Union's Connecting Europe Facility.

 

Disclaimer releasing the European Union from any liability in terms of the content of the dissemination materials:

 

"The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein."

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDSSSFUIFASEFA
Date   Source Headline
30th Jun 201611:50 amRNSIslandmagee signs new EU Grant Agreement
16th Jun 20163:45 pmRNSWoodburn Forest-1 well - completion of drilling
25th May 20162:45 pmRNSIslandmagee-receipt of final EUR1.75m grant monies
16th May 20167:00 amRNSWoodburn Forest-1 well - commencement of drilling
13th May 20161:00 pmRNSRe Press Comment on Woodburn Forest
22nd Mar 20167:00 amRNSHalf Yearly Report
16th Mar 20167:00 amRNSNotice of Interim Results
11th Mar 20167:00 amRNSWoodburn Forest-1 well-site construction commenced
2nd Mar 20167:01 amRNSAdvisers' appointment for Islandmagee monetisation
2nd Mar 20167:00 amRNSChange of Broker
1st Feb 201612:43 pmRNSData sharing agreement signed
29th Jan 20165:00 pmRNSTotal Voting Rights
29th Jan 201610:11 amRNSHolding(s) in Company
28th Jan 20163:56 pmRNSHolding(s) in Company
27th Jan 20169:19 amRNSHolding(s) in Company
26th Jan 201612:45 pmRNSResult of AGM, Placing update, total voting rights
22nd Jan 20163:05 pmRNSIslandmagee receives further EU Grant Funding
19th Jan 20167:00 amRNSUpdate on Woodburn Forest-1 well and its funding
31st Dec 201512:33 pmRNSTotal Voting Rights
23rd Dec 20154:40 pmRNSSecond Price Monitoring Extn
23rd Dec 20154:35 pmRNSPrice Monitoring Extension
18th Dec 20157:37 amRNSProposed placing to raise up to £450,000
17th Dec 201511:12 amRNSPosting of annual report
8th Dec 20157:00 amRNSFinal Results
30th Nov 20157:00 amRNSNotice of Final Results
27th Nov 20157:00 amRNSUpdate on Islandmagee gas storage project
16th Nov 20157:00 amRNSDivestment of Exploration Assets
10th Nov 20154:13 pmRNSDirectorate Change
4th Sep 20157:00 amRNSUpdate on the post Islandmagee-1 well
27th Aug 20158:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
25th Aug 20157:00 amRNSNorthern Ireland Exploration Update
18th Jun 20157:30 amRNSResults of Islandmagee-1 Well
18th Jun 20157:05 amRNSResults of Islandmagee-1 well
18th Jun 20157:00 amRNSLicence P1918 Update
17th Jun 20157:00 amRNSAppointment of Nominated Adviser and Joint Broker
15th Jun 20158:00 amRNSNotification of Major Interest in Shares
22nd May 20158:00 amRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
18th May 20157:00 amRNSCommencement of drilling: Islandmagee-1
1st May 20157:00 amRNSConvertible Loan Facility with Baron Oil Plc
28th Apr 20157:00 amRNSInterim Results
24th Apr 20153:27 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
2nd Apr 20157:00 amRNSNotification of Interim Results
5th Mar 20152:43 pmRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
3rd Mar 20155:21 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
27th Feb 20154:36 pmRNSTotal Voting Rights
25th Feb 20153:06 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
23rd Feb 201511:46 amRNSResult of GM and Completion of Placing
5th Feb 20157:00 amRNSPlacing to raise £2.1million
30th Jan 20157:00 amRNSData release agreement signed
21st Jan 201512:46 pmRNSBoard Changes

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.