Islandmagee Gas Storage Project Update

6 Aug 2018 07:00

RNS Number : 8529W
Infrastrata PLC
06 August 2018
 

 

 

6 August 2018

 

InfraStrata plc

("InfraStrata" or the "Company")

 

Islandmagee Gas Storage Project Update

 

InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to provide an update on FEED (Front End Engineering Design) progress having now achieved over 50% of the pre-established milestones.

 

The FEED commenced in May 2018 and is scheduled to be delivered in accordance with the EU Grant provisions by no later than December 2018. The FEED is being delivered on time and on budget by our world class supply chain partners. To date there have been no significant design issues that will prevent the Project being constructed as planned in order to meet its key objectives.

 

Further information is also provided below in respect of our commercial endeavours including in respect of potential funding partners to enable construction of the Project and the potential for the Company to secure an offtake partner.

 

 

John Wood, Chief Operating Officer, who is leading the FEED works on behalf of InfraStrata stated:

 

'Since I commenced working with InfraStrata in February we have made tremendous progress in terms of contracting and progressing the FEED, which is being undertaken by global experts in their field.

 

Reaching the EOI (Expression of Interest) stage is a significant milestone for InfraStrata as we move towards the funding and construction stage of the Project. 

 

As FEED has progressed, I have been spending time in conjunction with the rest of the Board to realign our processes and procedures to be ready for the construction phase of the Project.'

 

 

Set out below is a list of the key milestones and their progress (of notable interest is that milestone 9 has been completed several weeks ahead of schedule):

 

Current Milestone Progress

 

Milestone

Month

Description

Responsibility

Status

1

April

Contract Award Costain

InfraStrata

√ - Completed

2

May

Contract Award DEEP

InfraStrata

√ - Completed

3

May

Appointment of Subsurface Expert

InfraStrata

√ - Completed

4

May

Issue FEED schedule, project and quality plans

Costain

√ - Completed

5

May

Current Design Agreed

Costain

√ - Completed

6

June

Current Design Agreed

DEEP KBB

√ - Completed

7

June

Appoint Owners Engineer for FEED

InfraStrata

√ - Completed

8

July

Issue Process Flow Diagrams

Costain

√ - Completed

9

August

Gas & Leaching layout review

Costain

√ - Completed

10

August

All Process & Instrumentation Diagrams

Costain

11

Oct.

Engineering Design Complete

Costain

12

Oct.

All Investigation work on samples complete

DEEP KBB

13

Oct.

Cavern Design & Rock Mechanics Complete

DEEP KBB

14

Nov.

Surface FEED Deliverables & Estimates

Costain

15

Nov.

Subsurface FEED Deliverables & Estimates

DEEP KBB

16

Dec.

Submit Reports To EU

InfraStrata

 

 

During the course of the FEED, the HAZOP (Hazard and Operability Study), HAZID (Hazard Identification Study) and ENVID (Environmental Impact Identification) reviews have been undertaken. These have been chaired by independent industry subject matter experts. Results and actions from these studies were consistent with FEED projects at similar levels of maturity in design. Whilst progressing through FEED, the Company has undertaken a plethora of further studies (as required by the EU grant); the objective of which is to substantially reduce the 'Project Risk' as it proceeds through to 'construction ready' status.

 

Regular and positive engagement sessions have, and continue, to be held with the regulatory authorities and Stakeholders (such as the network operator). This is helping to shape the design of the Project to maximise the connectivity and market share from the known and future gas infrastructure network.

 

The FEED works are being undertaken to account for the Project's phased approach. This will ensure it facilitates a simple integration of Phase Two (Caverns 3-8) after the Phase One caverns (1 and 2) are in operation.

 

A further study has been commissioned by the Company to review the remaining options and market demand for a potential Phase Three to this project. This is predicated on the impact of other gas storage facilities being closed and the potential for increased demand for hydrocarbon storage. Further investigative work is being undertaken, in conjunction with other stakeholders, to ensure additional infrastructure is developed to fully exploit the full potential of the Islandmagee site in the future.

 

Project Commercial

 

The EU grant is being drawn down monthly to pay 50% of all FEED services eligible for payment under the grant. All grant monies that can be advanced to the Company have now been received. The final grant claim is expected to be made in December 2018 upon completion of the FEED.

 

The contractor loan notes have also been utilised to make payment against the requisite FEED services for which they were provided.

 

The Company has also been in contact with the EU to seek opportunities for further grant funding towards the cost of the construction works by virtue of its "Project of Common Interest" status. Should the Company be able to take advantage of any other EU grants, further announcements will be made as applicable.

 

In advance of the Final Investment Decision (FID) before the construction phase can begin, the Company has commenced discussions with a number of major EPC (Engineering Procurement and Contracting) organisations and will be inviting those organisations to issue an EOI (Expression of Interest) for Phase one of the construction project which focuses on the initial two caverns. The chosen contractor will then work on preparing a priced contract in the coming months. This process is being undertaken in compliance with the procurement process stipulated by the Company's EU grant.

 

 

Discussions are ongoing with several potential funding partners within the UK, Europe and internationally. The Board considers that the broad range of potential funding partners and their geographic spread demonstrates the global need for and attraction of gas storage. Such funds would complement the funds available under the UK Guarantee Scheme and the Company continues to utilise the services of CBRE Capital Advisors which has a proven track record of raising capital and working for major financial institutions as financial advisor on large infrastructure projects.  

 

As previously announced, the Company has held detailed discussions with major gas storage and trading companies with a view to securing an offtake partner for the facility, once it has been constructed, and these discussions continue to progress well with the investment decisions, commercial returns and duration of the relationship being clearly understood by all parties. Further updates will be made as appropriate.

 

 

 

For further information, please contact:

 

InfraStrata plc

Adrian Pocock, Chief Executive

 

c/o Yellow Jersey

+44 (0)20 3735 8825

Allenby Capital Limited (AIM Nominated Adviser & Joint Broker)

Jeremy Porter / Alex Brearley / Liz Kirchner

 

+44 (0)20 3328 5656

SI Capital Limited (Joint Broker)

Nick Emerson

 

+44 (0) 20 3871 4038

Yellow Jersey

Tim Thomson  

+44 (0)20 3735 8825

 

 

-ENDS-

 

Notes to editors:

 

InfraStrata is an independent gas storage company focused on the UK and Ireland. Further information is available on the Company's website: www.infrastrata.co.uk.

 

Background on the Islandmagee Storage Project

The Islandmagee gas storage project is a proposed salt cavern gas storage facility located on Islandmagee in County Antrim, Northern Ireland. The Board of InfraStrata believes that the proposed 500 million cubic metres Natural Gas Cavern Storage facility will provide over 25% of the UK's Natural Gas Storage once constructed, and will be situated adjacent to the Scotland Northern Ireland (gas) Pipeline (SNIP) and the Moyle 500 Megawatt Electricity Interconnector. Work commenced in 2007 with the acquisition of 3D seismic data to image the Permian salt in the Larne Lough area. During 2012, planning permission was granted for the project and a gas storage licence was issued by the Utility Regulator. In 2015 a well was drilled to core the salt and confirm the technical feasibility of the project, supported in part by the European Commission. The Front End Engineering and Design (FEED) element of the Project is scheduled for completion by the end of 2018. To date approximately £11.5m has been invested in the Project.

 

Further information is available on the company's website: www.infrastrata.co.uk

 

 

 

The Front End Engineering & Design (FEED) and Insitu Downhole Testing programme for the Islandmagee gas storage project is co-financed by the European Union's Connecting Europe Facility.

 

Disclaimer releasing the European Union from any liability in terms of the content of the dissemination materials:

 

"The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein."

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDSSSFUIFASEFA
Date   Source Headline
31st Oct 20195:00 pmRNSTotal Voting Rights
21st Oct 20197:00 amRNSFSRU Project Update
8th Oct 20195:16 pmRNSHolding(s) in Company
4th Oct 20194:28 pmRNSIssuance of loan conversion shares
2nd Oct 20197:00 amRNSIslandmagee Gas Storage Project Update
1st Oct 20197:00 amRNSHarland and Wolff Agreement
23rd Sep 20197:00 amRNSIslandmagee Gas Storage Project Update
9th Sep 20197:00 amRNSIslandmagee Gas Storage Project Update
30th Aug 20195:00 pmRNSTotal Voting Rights
1st Aug 20198:10 amRNSREPLACEMENT: Placing of shares to raise £700,000
1st Aug 20197:00 amRNSPlacing of shares to raise £700,000
9th Jul 20197:00 amRNSExclusivity agreement for an offshore FSRU
4th Jul 20197:00 amRNSHolding(s) in Company
4th Jul 20197:00 amRNSStrategy Update
3rd Jul 20197:00 amRNSIslandmagee Project Update
14th Jun 20197:00 amRNSSNIP Reverse Flow -EU FEED Study Grant application
11th Jun 20197:00 amRNSBinding Term Sheet - storage capacity offtake
31st May 20195:00 pmRNSTotal Voting Rights
16th May 20192:05 pmRNSSecond Price Monitoring Extn
16th May 20192:00 pmRNSPrice Monitoring Extension
16th May 201911:05 amRNSSecond Price Monitoring Extn
16th May 201911:00 amRNSPrice Monitoring Extension
15th May 20194:40 pmRNSSecond Price Monitoring Extn
15th May 20194:35 pmRNSPrice Monitoring Extension
14th May 20197:00 amRNSLeeds Shareholder Evening
9th May 20195:56 pmRNSProject Update
8th May 20197:00 amRNSLondon Shareholder Evening
3rd May 20197:00 amRNSIssue of shares, director shareholding & TVR
30th Apr 20195:00 pmRNSTotal Voting Rights
17th Apr 20197:00 amRNSHalf-year Report
11th Apr 20197:00 amRNSLondon and Leeds Shareholder Evenings
10th Apr 20197:00 amRNSIslandmagee Gas Storage Project Update
5th Apr 201912:50 pmRNSChange of Advisers
29th Mar 20193:56 pmRNSExercise of warrants and change to TVR
28th Mar 20197:00 amRNSIssuance of contractual fee shares and TVR
25th Mar 20197:00 amRNSBoard Changes
25th Mar 20197:00 amRNSProject Update - Pipeline Easement Options
22nd Mar 20196:23 pmRNSChange of Registered Office
19th Mar 20197:00 amRNSEngineering Design Works Contract Award
11th Mar 20197:00 amRNSLondon South East Oil & Gas Investor Evening
8th Mar 20197:00 amRNSDirectorate Change
7th Mar 20193:04 pmRNSProject Update
28th Feb 20195:00 pmRNSTotal Voting Rights
7th Feb 20197:00 amRNSIssue of Invitation to Tender Owner's Engineer
6th Feb 20197:00 amRNSExercise of warrants and total voting rights
31st Jan 20195:00 pmRNSTotal Voting Rights
30th Jan 201910:48 amRNSHolding(s) in Company
29th Jan 20191:49 pmRNSIslandmagee Gas Storage Project-EU Funding Update
29th Jan 20197:00 amRNSOil Capital Conference Presentation
29th Jan 20197:00 amRNSExercise of warrants and total voting rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.