Final FEED Milestone & Additional Concept Studies

5 Dec 2018 07:00

RNS Number : 4547J
Infrastrata PLC
05 December 2018
 

 

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR"). With the publication of this announcement, this information is now considered to be in the public domain.

 

5 December 2018

 

InfraStrata plc

("InfraStrata" or the "Company")

 

Islandmagee Gas Storage Project - Completion of Final Milestone and Additional Concept Studies

 

InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to provide an update on the final milestone for the FEED (Front End Engineering Design) of its Islandmagee gas storage project (the "Project").  Milestones 1 through to 16 have been completed on time and on budget and accordingly, the FEED report has now been submitted to the European Union in accordance with the Company's grant conditions.

 

The report will, in due course, be reviewed and audited by the European Union and other related parties to ensure it complies with all of the conditions appertaining to the grant. It is likely that InfraStrata will receive its final payment from the EU in Q2 2019 after this verification process has been completed.

 

Milestone Progress

 

Milestone

Month

Description

 

Status

1

April

Contract Award Costain

InfraStrata

√ - Completed

2

May

Contract Award DEEP

InfraStrata

√ - Completed

3

May

Appointment of Subsurface Expert

InfraStrata

√ - Completed

4

May

Issue FEED schedule, project and quality plans

Costain

√ - Completed

5

May

Current Design Agreed

Costain

√ - Completed

6

June

Current Design Agreed

DEEP KBB

√ - Completed

7

June

Appoint Owners Engineer

InfraStrata

√ - Completed

8

July

Issue Process Flow Diagrams

Costain

√ - Completed

9

August

Gas & Leaching layout review

Costain

√ - Completed

10

August

All Process & Instrumentation Diagrams

Costain

√ - Completed

11

Oct.

Engineering Design Complete

Costain

√ - Completed

12

Oct.

All Investigation work on samples complete

DEEP KBB

√ - Completed

13

Oct.

Cavern Design & Rock Mechanics Complete

DEEP KBB

√ - Completed

14

Nov.

Surface FEED Deliverables & Estimates

Costain

√ - Completed

15

Nov.

Subsurface FEED Deliverables & Estimates

DEEP KBB

√ - Completed

16

Dec.

Submit FEED Report to EU

InfraStrata

√ - Completed

 

Completing this final milestone allows the team to concentrate on completing the negotiations that are underway with three potential equity providers that have provided the Company with term sheets for equity funding (at Project or subsidiary level). The term sheets are not binding and at this stage it is not guaranteed that InfraStrata will enter into a binding equity agreement. However, discussions are detailed and advanced and InfraStrata is still on track to provide a full update in Q4 2018 as previously stated.

 

Enabling works have been planned as the next phase of the Project, ahead of a final investment decision, and are scheduled to start in January 2019.

 

In addition, InfraStrata has engaged Costain to undertake a Concept Development Study to consider the technical implications of twinning the pipeline that runs between Northern Ireland and Scotland including the restrictions of connecting any new pipeline into the existing network and regulatory framework. There are no guarantees that it will be possible to twin the interconnecting pipeline at this stage and further details will be provided when possible.

 

Further, Atkins has been engaged to further investigate and provide a Concept Development Study on developing additional caverns on Islandmagee, as previous advice received indicated that an additional 15 caverns could be possible on top of the 8 already planned. However, there are no guarantees that it will be possible to develop any further caverns at this stage and further details will be provided when appropriate.

 

 

John Wood, Chief Executive Officer, commented: "It is testament to the team that we are building at InfraStrata that we have managed to deliver these milestones in a timely manner. As we progress through to the end of 2018, we are working hard to close out the equity funding for the Project. We are working through the process methodically to ensure we create maximum shareholder value. We are working to ensure we hit the ground running in 2019 with many work streams in progress"

 

 

 

For further information, please contact:

 

InfraStrata plc

John Wood, Chief Executive

 

c/o Yellow Jersey

+44 (0)20 3735 8825

Allenby Capital Limited (AIM Nominated Adviser & Joint Broker)

Jeremy Porter / Liz Kirchner

 

+44 (0)20 3328 5656

SI Capital Limited (Joint Broker)

Nick Emerson

 

+44 (0) 20 3871 4038

Yellow Jersey

Tim Thompson  

+44 (0)20 3735 8825

 

 

-ENDS-

 

Notes to editors:

 

InfraStrata is an independent gas storage company focused on the UK and Ireland. Further information is available on the Company's website: www.infrastrataplc.com 

 

Background on the Islandmagee Storage Project

The Islandmagee gas storage project is a proposed salt cavern gas storage facility located on Islandmagee in County Antrim, Northern Ireland. The Board of InfraStrata believes that the proposed 500 million cubic metres Natural Gas Cavern Storage facility will provide over 25% of the UK's Natural Gas Storage once constructed, and will be situated adjacent to the Scotland Northern Ireland (gas) Pipeline (SNIP) and the Moyle 500 Megawatt Electricity Interconnector. Work commenced in 2007 with the acquisition of 3D seismic data to image the Permian salt in the Larne Lough area. During 2012, planning permission was granted for the project and a gas storage licence was issued by the Utility Regulator. In 2015 a well was drilled to core the salt and confirm the technical feasibility of the project, supported in part by the European Commission. The Front End Engineering and Design (FEED) element of the Project was completed in November 2018 and the FEED report was submitted to the European Union in December 2018 in accordance with the Company's grant conditions. . To date approximately £13.5m has been invested in the project.

 

Further information is available on the company's website: www.infrastrata.co.uk

 

 

 

The Front End Engineering & Design (FEED) and Insitu Downhole Testing programme for the Islandmagee gas storage project is co-financed by the European Union's Connecting Europe Facility.

 

Disclaimer releasing the European Union from any liability in terms of the content of the dissemination materials:

 

"The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein."

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCLFFVVFRLSIIT
Date   Source Headline
31st Oct 20195:00 pmRNSTotal Voting Rights
21st Oct 20197:00 amRNSFSRU Project Update
8th Oct 20195:16 pmRNSHolding(s) in Company
4th Oct 20194:28 pmRNSIssuance of loan conversion shares
2nd Oct 20197:00 amRNSIslandmagee Gas Storage Project Update
1st Oct 20197:00 amRNSHarland and Wolff Agreement
23rd Sep 20197:00 amRNSIslandmagee Gas Storage Project Update
9th Sep 20197:00 amRNSIslandmagee Gas Storage Project Update
30th Aug 20195:00 pmRNSTotal Voting Rights
1st Aug 20198:10 amRNSREPLACEMENT: Placing of shares to raise £700,000
1st Aug 20197:00 amRNSPlacing of shares to raise £700,000
9th Jul 20197:00 amRNSExclusivity agreement for an offshore FSRU
4th Jul 20197:00 amRNSHolding(s) in Company
4th Jul 20197:00 amRNSStrategy Update
3rd Jul 20197:00 amRNSIslandmagee Project Update
14th Jun 20197:00 amRNSSNIP Reverse Flow -EU FEED Study Grant application
11th Jun 20197:00 amRNSBinding Term Sheet - storage capacity offtake
31st May 20195:00 pmRNSTotal Voting Rights
16th May 20192:05 pmRNSSecond Price Monitoring Extn
16th May 20192:00 pmRNSPrice Monitoring Extension
16th May 201911:05 amRNSSecond Price Monitoring Extn
16th May 201911:00 amRNSPrice Monitoring Extension
15th May 20194:40 pmRNSSecond Price Monitoring Extn
15th May 20194:35 pmRNSPrice Monitoring Extension
14th May 20197:00 amRNSLeeds Shareholder Evening
9th May 20195:56 pmRNSProject Update
8th May 20197:00 amRNSLondon Shareholder Evening
3rd May 20197:00 amRNSIssue of shares, director shareholding & TVR
30th Apr 20195:00 pmRNSTotal Voting Rights
17th Apr 20197:00 amRNSHalf-year Report
11th Apr 20197:00 amRNSLondon and Leeds Shareholder Evenings
10th Apr 20197:00 amRNSIslandmagee Gas Storage Project Update
5th Apr 201912:50 pmRNSChange of Advisers
29th Mar 20193:56 pmRNSExercise of warrants and change to TVR
28th Mar 20197:00 amRNSIssuance of contractual fee shares and TVR
25th Mar 20197:00 amRNSBoard Changes
25th Mar 20197:00 amRNSProject Update - Pipeline Easement Options
22nd Mar 20196:23 pmRNSChange of Registered Office
19th Mar 20197:00 amRNSEngineering Design Works Contract Award
11th Mar 20197:00 amRNSLondon South East Oil & Gas Investor Evening
8th Mar 20197:00 amRNSDirectorate Change
7th Mar 20193:04 pmRNSProject Update
28th Feb 20195:00 pmRNSTotal Voting Rights
7th Feb 20197:00 amRNSIssue of Invitation to Tender Owner's Engineer
6th Feb 20197:00 amRNSExercise of warrants and total voting rights
31st Jan 20195:00 pmRNSTotal Voting Rights
30th Jan 201910:48 amRNSHolding(s) in Company
29th Jan 20191:49 pmRNSIslandmagee Gas Storage Project-EU Funding Update
29th Jan 20197:00 amRNSOil Capital Conference Presentation
29th Jan 20197:00 amRNSExercise of warrants and total voting rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.