Project Review - December, 2008

10 Dec 2008 07:00

RNS Number : 8297J
Highland Gold Mining Limited
10 December 2008
 



Press-release

HIGHLAND GOLD MINING LIMITED

CORPORATE DEVELOPMENT UPDATE

10 December 2008 - As announced in the Company's interim results in September, Highland Gold's new executive management team has now undertaken an extensive review of the Company's assets. The purpose of the review has been to conserve cash and in doing this we will continue to derive maximum benefit from the Company's producing Mnogovershinnoye mine (MNV) and to maintain the required flexibility in expenditures at our development projects until such time as markets improve and project financing becomes more readily available.

At MNV we are pleased to report that we have achieved strong results in the fourth quarter as a consequence of the high-grade ore currently being mined from the B3 Zone in the open pit, an average daily mill throughput of better than 3,000 tons per day and increased equipment utilisation for both the open pit and underground fleets. We remain on target to achieve our 2008 production goal of 155,000 to 165,000 ounces of gold. 

At the development projects, the Board of Directors of Highland Gold has taken a decision to delay the commissioning of the Novoshirokinskoye mine, which was due to take place in December this year, with production starting in Q1 2009. This decision has been made jointly with Kazzinc our project partner. Under the current license terms, the Company is required to begin production at Novoshirokinskoye by 1 October 2009. Although the majority of the preparatory works for the launch of the mine have been completed, an analysis of the recent dramatic fall in world metal prices and the resulting impact upon the profitability of the project has caused the joint venture partners to conclude that a postponement in proceeding to production is prudent and appropriate. In the interim, the mine will be placed under care and maintenance. 

The Company has also undertaken a review of the ongoing activities leading to construction at its Mayskoye development project. It has been decided to defer the majority of construction work at the project site until economic conditions and financing opportunities improve. Limited construction and pre-production underground mine development work will be carried out at the site during 2009. In addition, the detailed engineering design of the hydrometallurgical plant will continue to be advanced. The Company is also in the process of updating the economic model of the entire project.

With regard to our Taseevskoye development project, it is expected that the cut-off study will be approved by the Russian State Committee for Mineral Reserves (GKZ) by the end of 2008. The bench-scale metallurgical testing programme, which has been completed recently, shows positive results that corroborate earlier pre-feasibility test work and set the stage for metallurgical pilot plant testing. However, immediate steps are also being taken at Taseevskoye to minimise project expenditures. 

Commenting on this announcement Chairman, Duncan Baxter said, -

"The world economic climate has changed dramatically since our positive interim results reported in September 2008. This has led the Board and management to take aggressive action to protect the strength of our balance sheet. Slowing down the development process of our projects is a logical decision in these circumstances. The Board considers that the actions they have taken are in the best commercial interests of Highland Gold and its shareholders."

For further information please contact:

Highland Gold - 

Dmitry Yakushkin, Head of Communications - +7 495 777 3155

Fin Public Relations - 

Alex Glover - +44 (0) 207 608 2280

Smith's - 

Dominic Palmer-Tomkinson - +44 (0) 207 239 0140

JPMorgan Cazenove (Nominated Adviser) - 

Michael Wentworth-Stanley, Managing Director 

Sam Critchlow - +44 (0) 207 588 2828

www.highlandgold.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUKONRWWRURAA
Date   Source Headline
24th May 20182:28 pmRNSResult of Annual General Meeting
4th May 20187:00 amRNSMailing of 2017 Annual Report and Notice of AGM
30th Apr 20187:00 amRNSQ1 2018 Operating Results
26th Apr 20187:00 amRNSAgreement to Purchase Gold Assets in Chukotka
17th Apr 20187:00 amRNS2017 Final Results
11th Apr 20187:38 amRNSFull Year Results Announcement Date
22nd Feb 20188:47 amRNSResources and Reserves Update as at 31 Dec 2017
7th Feb 20187:00 amRNSBelaya Gora/Blagodatnoye PFS and Resource Update
6th Feb 20187:00 amRNSKekura Feasibility Study and Resource Update
5th Feb 20187:00 amRNSBlock listing Interim Review
18th Jan 20187:00 amRNSQ4 2017 Operating Results
13th Dec 20177:00 amRNSBoard of Directors Adopts Dividend Policy
30th Nov 20174:33 pmRNSHolding(s) in Company
20th Nov 20177:00 amRNSUpdated Resource and Reserve Estimates for Novo
9th Nov 201710:17 amRNSAppointment of Chief Operating Officer
11th Oct 20177:00 amRNSQ3 2017 Operating Results
9th Oct 20178:56 amRNSAppointment of Joint Corporate Broker
18th Sep 20173:42 pmRNSHolding(s) in Company
4th Sep 20177:00 amRNSInterim Results Announcement for H1 2017
30th Aug 20177:00 amRNSInterim Results Announcement Date
3rd Aug 20177:00 amRNSBlock listing Interim Review
24th Jul 20177:00 amRNSQ2 2017 Operating Results
5th Jun 20177:00 amRNSCompany Cleared to Proceed with Kekura Development
22nd May 20177:00 amRNSNew Exploration Licences Adjacent to MNV
17th May 20171:11 pmRNSResult of AGM
5th May 20177:00 amRNSDirector/PDMR Shareholding
5th May 20177:00 amRNSUpdated Resource and Reserve Estimates for MNV
28th Apr 201710:32 amRNSMailing of 2016 Annual Report and Notice of AGM
27th Apr 20177:01 amRNSQ1 2017 Operating Results
10th Apr 20177:00 amRNS2016 Final Results
4th Apr 20177:00 amRNSNotice of Results
20th Mar 20177:04 amRNSUnkurtash Scoping Study
1st Mar 20171:25 pmRNSDirector/PDMR Shareholding
21st Feb 20174:06 pmRNSHolding(s) in Company
3rd Feb 20177:00 amRNSBlock listing Interim Review
26th Jan 20179:03 amRNSQ4 2016 Operating Results
9th Nov 20167:00 amRNSDirector/PDMR Shareholding
3rd Nov 20167:00 amRNSQ3 2016 Operating Results
26th Sep 20167:00 amRNSInterim Results Announcement for H1 2016
23rd Sep 20162:54 pmRNSInterim Results Announcement Date
5th Sep 20167:00 amRNSAgreements Signed for State Support of Kekura
9th Aug 20168:30 amRNSQ2 2016 Operating Results (Replacement)
9th Aug 20167:00 amRNSQ2 2016 Operating Results
3rd Aug 20167:00 amRNSBlock listing Interim Review
25th May 201612:00 pmRNSResult of AGM
23rd May 20167:00 amRNSQ1 2016 Operating Results
19th May 20167:00 amRNSKekura Project Update
20th Apr 20167:00 amRNS2015 Final Results
15th Apr 20162:18 pmRNSNotice of Results
3rd Feb 20167:00 amRNSBlocklisting Interim Review

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.