Project Progress Update

27 Jul 2011 07:00

RNS Number : 1013L
Highland Gold Mining Limited
27 July 2011
 



BELAYA GORA PROJECT PROGRESS UPDATE

27 July 2011 - Highland Gold Mining Limited ("Highland Gold" or the "Company" (AIM: HGM)) is pleased to announce that it has submitted the final design documents for approval for the second stage of development of the Belaya Gora Project. First phase mining at the Belaya Gora project was started in November 2010 with delivery of select oxide ore to the MNV processing plant. Progressing to the second important stage in accordance with previously declared timelines underpins the Company's commitment to launch the stand-alone gold processing plant at Belaya Gora during H2 2012.

The design documentation for the second stage of the Belaya Gora Project development was prepared by Zabaikalzolotoproekt (ZZP) Institute (Highland's in-house engineering group), in conjunction with selected consultants. It was submitted for review to the Federal GlavGosExpertise Agency. The anticipated design process capacity averages 1.5 million tonnes of ore per annum with an associated expected gold production ranging from 75,000 to 110,000 oz per annum. Project capex spent to date is approximately US$11.0 million out of a total budget of US $101.1 million planned over the period 2011/12.

Based on comprehensive metallurgical studies completed by the consultancy firm TOMS Research Institute (author of the design process regulation) conventional metallurgical processing based on gravity concentration and whole ore cyanidation technology has proven optimal for gold recovery. CJSC Mekhanobr Engineering, responsible for the design of the tailings storage facility, and LLC Agrospetskompleks, responsible for the design of the water treatment facility, have both provided the expertise to develop comprehensive plans that will ensure that the project remains in compliance with the environmental requirements and guidelines.

The Belaya Gora Project is located 66 kilometers south of the Mnogovershinnoye mine (MNV) and is accessed by an all weather road. In July 2009, the State Committee on Reserves of the Russian Federation (GKZ) registered 820,000 oz of C1+C2 reserves onto the state balance. In order to enhance project economics the Company commenced selective mining of ore with processing via the MNV facilities in November 2010. This first stage of production is expected to continue through to commissioning of the stand alone process plant.

Belaya Gora's management team is in the process of finalising the detailed construction schedule and work plans in order to commence site specific activities. Land clearing and preparation for construction have already commenced and site construction will immediately follow the receipt of the construction permit. The Company's capital construction team has already initiated the selection of a general contractor as well as preparation of tendering documents for the supply of capital equipment.

For further information please contact:

Highland Gold

Dmitry Yakushkin, Head of Communications + 7 495 424 95 21

Duncan Baxter, Chairman + 44 (0) 1534 814 202

Matrix

Robin Henshall, Partner +44 (0) 20 3206 7172

(Nominated Adviser and Broker)

Nick Stone +44 (0) 20 3206 7343

Fin Public Relations

Alex Glover + 44 (0) 20 7608 2280

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEMFDMFFSEEW
Date   Source Headline
7th Feb 201312:34 pmRNSBlocklisting Interim Review
30th Jan 20137:00 amRNSTrading Statement
21st Dec 20124:40 pmRNSSecond Price Monitoring Extn
21st Dec 20124:35 pmRNSPrice Monitoring Extension
17th Dec 20127:00 amRNSHolding(s) in Company
10th Dec 20127:00 amRNSAcquisition
29th Nov 20127:00 amRNSDrilling Report
29th Nov 20127:00 amRNSProject update
22nd Nov 20127:00 amRNSAPPOINTMENT OF JOINT BROKER
14th Nov 20127:00 amRNSTrading Statement
6th Nov 20127:00 amRNSDrilling Report
1st Oct 20127:00 amRNSDrilling Report
19th Sep 20127:00 amRNSHalf Yearly Report
15th Aug 201212:00 pmRNSHolding(s) in Company
10th Aug 20127:00 amRNSTrading Statement
9th Aug 20121:10 pmRNSBlocklisting Interim Review
24th Jul 20127:00 amRNSProject update Unkurtash
16th Jul 201212:00 pmRNSDirector/PDMR Shareholding
12th Jul 20127:00 amRNSAcquisition
12th Jul 20127:00 amRNSDirectorate Change
14th Jun 20123:35 pmRNSResult of AGM
11th Jun 201210:55 amRNSHolding(s) in Company
1st Jun 201210:21 amRNSAcquisition
22nd May 20127:00 amRNSIncrease in JORC Compliant Resources
8th May 201211:27 amRNSHolding(s) in Company
2nd May 201212:17 pmRNSBoard change
30th Apr 201211:47 amRNSHolding(s) in Company
26th Apr 201211:24 amRNSSale of Shares by Barrick Corporation
24th Apr 20127:00 amRNSFinal Results
20th Apr 20127:00 amRNSNotice of release of 2011 results
28th Mar 20121:36 pmRNSBlocklisting Interim Review
13th Feb 20127:00 amRNSBarrick Divestiture
31st Jan 20127:00 amRNSDirectorate Change
30th Jan 20127:00 amRNSTrading Statement
23rd Jan 20127:01 amRNSHGML Results Announcement
29th Dec 20117:00 amRNSAcquisition
22nd Dec 20117:00 amRNSDirectorate Change
29th Nov 20117:00 amRNSConstruction permit received
23rd Nov 20117:00 amRNSAcquisition
14th Nov 20117:00 amRNSProduction Update
7th Nov 20117:00 amRNSChange of Nomad
20th Sep 20117:00 amRNSHalf Yearly Report
16th Aug 20117:00 amRNSTrading Statement
2nd Aug 20117:00 amRNSMNV JORC update
27th Jul 20117:00 amRNSProject Progress Update
18th Jul 20117:00 amRNSExploration results
22nd Jun 20117:00 amRNSPROJECTS UPDATE
16th Jun 201112:01 pmRNSResult of AGM
1st Jun 20117:00 amRNSReserve Update
27th Apr 20117:00 amRNSFinal Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.