Operations Update

26 Jul 2016 07:00

RNS Number : 2155F
Green Dragon Gas Ltd
26 July 2016
 

26 July 2016

GREEN DRAGON GAS LTD.

("Green Dragon" or the "Company")

Operations Update

Green Dragon Gas Ltd. (LSE: GDG), one of the largest independent companies involved in the production and sale of Coalbed Methane ("CBM") gas in China, is pleased to announce an operations update for the six-months ended 30 June 2016.

In H1 2016 Green Dragon has continued to focus on the implementation of its infrastructure programme aimed at increasing gas processing and sales capacity from its existing drilled wells. The programme is concentrating on the connection of existing drilled wells to sales infrastructure together with the installation of significant additional compression across the production circuits. By increasing and rebalancing the compression installed across the production circuits, the Company is seeking to lower wellhead pressure resulting in significantly increased gas recoveries from existing wells.

Operational highlights

· GSS H1 2016 sales volume up 62% and 43% versus H1 and H2 2015 respectively

· Reached a H1 2016 sales peak of 6.0mmcf/day (170,000m3/day) at GSS, an increase of 18% compared to 31 December 2015

· Continued focus on infrastructure and compression across the GSS production circuits

· First screw compressor installed at GSS in April 2016, allowing wellhead pressure to be taken to vacuum,resulting in an increase in gas sales of 45% from the well

· Run-time efficiency of compressors at GSS of 87% in H1 2016 with average uptime of 93% recorded through June 2016

· The Company reiterates its exit rate production capacity target of 16 bcf for year end 2016

Randeep S. Grewal, Chairman and Founder of Green Dragon, commented:

"I am pleased with the continued progress we have made in the first half of 2016 in relation to infrastructure and creating the foundation for continued increases in sales volumes from the existing well stock. We have demonstrated the potential of our wells by consistently delivering increased sales volumes and with our focus on compression and production infrastructure we expect this to continue through the end of 2016 and into 2017. Our final challenge on our large GSS project is increasing gas sales by reducing casing pressure at the well bore on the currently drilled well stock where production capacity is significantly higher than the current gas sales. I am satisfied with the first well head screw compressor installed on well GSS188, which has resulted in the 45%increase in its gas sales. As the proof of concept has been successful, we can now focus on repeating the same technological improvement on the rest of the well stock.

"This year marks the Company's 10th anniversary of admission to trading on the London Stock Exchange and the turning point for our operations. The road here has been long and, at times, challenging. However, with continued perseverance I am confident of delivering significant value to our shareholders."

 

Upstream

Production and Infrastructure

· Continued focus on infrastructure and increasing gas production for sale

· 708 wells producing gas for sale across all blocks (2015: 666)

· H1 2016 well counts across all blocks summarised as follows:

 

GSS

GCZ

GSN

GPX

GQY-A

GQY-B

GFC

GGZ

Total Wells

1,588

114

201

12

7

52

30

33

Wells producing gas for sale

621

87

0

0

0

0

0

0

 

· Gross production capacity across all licence areas increased to 6.01 bcf (H2 2015: 5.44 bcf)

Exploration

· Significant progress made on GGZ block ahead of planned Chinese Reserve Report this year

· 2 wells tested successfully across 3 production horizons

· 5 wells came online with 2 producing gas

Downstream

· Green Dragon equity gas H1 2016 sales mix split was 94% PNG and 6% CNG (2015: 95% PNG; 5% CNG)

· Sales at GSS increased to 1.07 bcf (H2 2015: 0.75 bcf) an increase of 42% versus H2 2015

· Sales and production for the last 3 periods are summarised as follows:

 

H1 2015

H2 2015

H1 2016

Sales GSS (Bcf)

0.66

0.75

1.07

PNG

0.55

0.52

0.67

CNG

0.33

0.38

0.28

Power

0.08

0.09

0.12

Sales GCZ (Bcf)

0.94

0.88

0.83

 

10.00% Green Dragon Gas Ltd. Bond ISIN: NO 001 072437.0

As stated in the 2015 financial statements published on 27April, 2016, the results do not include the Group's share of CNOOC GSN transactions or operated GSS 1,388 well's revenue, associated costs and results margins. The sales revenues and volumes associated with the CNOOC operated areas of GSS and GSN, for period ending year end 2015, will be reported in due course as they are currently being audited by independent auditors.

 

Upon conclusion of the audit, the Interest Coverage Ratio and Leverage Ratio for the Company's outstanding Bond, currently not compliant, shall be adjusted in accordance with the results.

 

Green Dragon continues to pursue the completion of the CNOOC audit so that they will be able to give a final and conclusive statement of their results for the year to 31 December 2015.

 

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) No 596/2014.

 

For further information on the Company and its activities, please refer to the website at www.greendragongas.com or contact:

Instinctif Partners

David Simonson / George Yeomans

Tel: +44 20 7457 2020

 

Citigroup

Tom Reid / Luke Spells

Tel: +44 20 7986 4000

 

Peel Hunt

Richard Crichton / Ross Allister

Tel: +44 20 7418 8900

 

About Green Dragon Gas

Green Dragon Gas is a leading independent gas producer with operations in China and is listed on the main market of the London StockExchange (LSE: GDG). The Company has 549Bcf of 2P reserves and 2379Bcf of 3P reserves across eight production blocks covering over7,566km² of licence area in the Shanxi, Jiangxi, Anhui and Guizhou provinces. It holds six Production Sharing Agreements with strong, highly capitalised Chinese partners including CUCBM (CNOOC), CNPC and PetroChina, and has infrastructure in place to support multiple routes to monetise gas production.

 

END

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDDMGZNKVLGVZG
Date   Source Headline
30th Apr 20187:00 amRNSNotice of Full Year Financial Results
16th Apr 20187:25 amRNSAnnual Audited Reserve Report
27th Feb 20187:00 amRNSGGZ Block Exploration Progression
30th Jan 20187:00 amRNS2017 Operational Update and 2018 Outlook
3rd Jan 20188:04 amRNSChange of Name
20th Dec 20171:19 pmRNSResult of AGM
6th Dec 20177:00 amRNSNotice of AGM
17th Nov 20173:10 pmRNSDebt Maturity Extensions Update
16th Nov 20177:01 amRNSDebt Maturity Extensions Update
30th Oct 20179:28 amRNSDebt Maturity Extensions
4th Oct 20177:00 amRNSExecution of Further Supplementary Agreements
28th Sep 20177:00 amRNSInterim Results for the Six Months Ended June 2017
25th Sep 20177:00 amRNSNotice of Interim Results
20th Sep 20177:35 amRNSGreen Dragon's Asset Development Update
15th Sep 20177:00 amRNSGreka Chengzhuang Block Approval
30th Aug 201711:56 amRNSHolding(s) in Company
31st Jul 20177:00 amRNSGreka Shizhuang South Block Update
26th Jun 20177:00 amRNSGIC Convertible Bond Update
5th Jun 20177:00 amRNSNordic Bond Update
27th Apr 20177:00 amRNSAudited results - year ended 31 December 2016
26th Apr 20177:00 amRNSNotice of Results
18th Apr 20177:08 amRNSDevelopment Plan Approved For GCZ Block
27th Feb 20177:00 amRNS11th Year of Audited Reserves Growth
2nd Feb 20177:00 amRNSOperations Update and 2017 Outlook
19th Dec 20167:00 amRNSUpdated Corporate Presentation
15th Dec 20167:00 amRNSGIC US$50 million Convertible Bond Extension
8th Dec 20167:00 amRNSNew Chinese Energy Development Plan
29th Sep 20167:00 amRNSInterim Results for the Six Months Ended June 2016
26th Sep 20167:00 amRNSGuizhou Block Update
9th Sep 201612:00 pmRNSReport on Payments to Governments for 2015
2nd Sep 20165:52 pmRNSNordic Bond Update
26th Jul 20163:23 pmRNSResult of AGM
26th Jul 20167:00 amRNSOperations Update
25th Jul 20167:44 amRNSDate of Operations Update
4th Jul 20164:56 pmRNSNotice of AGM
24th Jun 201612:00 pmRNSResponse to EU Referendum Result
9th May 201610:44 amRNSInvestor Roadshow
29th Apr 20167:00 amRNSAnnual Report on Website
27th Apr 20167:00 amRNSAudited results - year ended 31 December 2015
21st Apr 201610:32 amRNSCapital Markets Day Update
14th Apr 20161:51 pmRNSNotice of Results
21st Mar 20167:00 amRNSGSS-008 Well Celebrates 8th Year of Production
15th Mar 20167:00 amRNSChina increases CBM cash subsidy 50%
23rd Feb 20163:43 pmRNSSpeech at Natural Resources Forum Presentation
23rd Feb 20167:00 amRNS10th Year of Audited Reserves Growth
17th Feb 20167:00 amRNSPresentation at Natural Resources Forum
17th Feb 20167:00 amRNSAudited Reserves Update
3rd Feb 20167:00 amRNSOperations Update and 2016 Outlook
25th Jan 20167:00 amRNSDate of Operations Update
4th Jan 20167:00 amRNSProduction Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.