The latest Investing Matters Podcast episode featuring financial educator and author Jared Dillian has been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksFerro-alloy Re. Regulatory News (FAR)

Share Price Information for Ferro-alloy Re. (FAR)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 6.25
Bid: 6.00
Ask: 6.50
Change: 0.00 (0.00%)
Spread: 0.50 (8.333%)
Open: 6.25
High: 6.25
Low: 6.25
Prev. Close: 6.25
FAR Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Balasausqandiq Feasibility Study Update

29 Nov 2021 07:00

RNS Number : 7775T
Ferro-Alloy Resources Limited
29 November 2021
 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 which is part of UK law by virtue of the European Union (Withdrawal) Act 2018

 

29 November 2021

Ferro-Alloy Resources Limited ('FAR' or the 'Company' or the 'Group')

 

Balasausqandiq Feasibility Study Update

 

Ferro-Alloy Resources Limited (LSE:FAR), the vanadium producer and developer of the large Balasausqandiq vanadium deposit in Southern Kazakhstan, is pleased to announce an update on the progress of the expanded feasibility study (the 'Feasibility Study' or 'Study') for the large Balasausqandiq vanadium deposit ('Balasausqandiq') . 

 

Overview

 

FAR is currently well advanced in the workstreams necessary to produce a Bankable Feasibility Study ('BFS'). Following the investments by Vision Blue Resources during 2021, the decision has been taken to expand the scope of the Study to include not only the finalisation of the BFS for the first phase of development, known as Phase 1, but also to include Phase 2. Phase 1 envisages the treatment of 1 million tonnes of ore per year to produce 5,600 tonnes of vanadium pentoxide, and Phase 2 envisages an expansion to 4 million tonnes per year with production rising to 22,400 tonnes of vanadium pentoxide.

 

The Company has commissioned SRK Consulting (Kazakhstan) Limited to produce the overall Feasibility Study, with the metallurgy and process plant being covered by Tetra Tech Inc. The results of the BFS are expected during the last quarter of 2022.

 

A considerable body of work has been undertaken in previous studies, including the assessment of the reserves of just one (of five) ore-bodies on a JORC 2012 basis at 23 million tonnes, and the operation of a test plant at which the proposed process was developed and tested at pilot and commercial scales. Balasausqandiq is unusual in being a sedimentary deposit comprised of black shales which are capable of a far lower-cost treatment route, in terms of both capital and operating costs, than the more plentiful vanadium ores comprising titano-magnetite which require pre-concentration and roasting at high temperatures.

 

The former test-plant is currently operating on a commercial basis to produce vanadium, molybdenum and nickel concentrates from bought-in secondary raw-materials.

 

 

Drilling

 

At Balasausqandiq, there are five currently known ore-bodies. The first, OB1, has been explored sufficiently for a reserve of 23 million tonnes of ore to be announced under the JORC 2012 standard, providing enough ore to feed Phase 1 of the development of Balasausqandiq. Ore bodies two to five have been explored and a reserve announced under the former Kazakhstan system of reserve classification. In line with the decision to upgrade the scope of the feasibility study, the decision has been taken to carry out further drilling of OB1 to further understand the underground geometry and to use this information to tailor a drilling programme to be carried out on ore-bodies two to five with the intention of being able to define a reserve under JORC 2012 sufficient for Phase 2.

 

Contracts have been signed with two drilling companies. The first will complete a programme of diamond core-drilling and the second, a programme of the faster Reverse Circulation ('RC') drilling where the core is recovered as the drill chippings rather than as whole core.

 

The core-drilling rigs have now arrived on site and first drilling started on 23 November 2021. An initial programme of 6,000 metres will be carried out after which the requirements for the remainder of the programme, likely to be between 2,000 and 4,000 metres, can be re-assessed.

 

The RC contract provides for an expected start-date of 1 February 2022. The initial programme is for 9,000 metres. After assessment, a decision will be taken on how much further drilling of up to around 5,000 metres is required. It is currently expected that the RC drilling will be completed towards the end of the first quarter 2022.

 

Metallurgy

 

The FAR process utilises pressure acid leaching ('PAL') for the extraction of vanadium and associated uranium, molybdenum, aluminium, potassium and rare earth elements. The process was developed by the Company at its Shieli operation in Kazakhstan and has been tested at both pilot and semi-commercial scales. As part of the Feasibility Study, a comprehensive metallurgical test work program has been implemented at SGS - Canada (Lakefield) to validate the process and confirm critical process parameters tested in the pilot plant such as leach extraction, extraction kinetics, effect of recycle streams, solid/liquid separation requirements, reagent consumptions and final vanadium pentoxide product quality. To further de-risk the project a separate leach and comminution variability programme is also being implemented at SGS.

 

Initial batch testing has been completed and the results were in line with historical data from the Company. The next stage, "locked-cycle" testing where the leaching process is carried out multiple times to simulate actual ongoing operations, has commenced and will provide more definitive results, expected in early 2022.

 

By-products

 

As part of the process of leaching the vanadium, uranium, molybdenum, aluminium, potassium and rare-earth elements are also recovered into solution. Recovery from the leach solution is carried out by a three-stage sorption process in which uranium and molybdenum are recovered in the first, vanadium in the second and rare-earth elements can possibly be recovered in the third. The aluminium and potassium can be precipitated from the solutions as potassium alum. The recovery of these by-products will be confirmed within the test-programme discussed above.

 

Potentially a key by-product, carbon, is contained in the tailings and comprises a form of carbon similar in physical and chemical form to carbon black which is usually made by burning oil or gas. The Company has previously successfully tested two potential uses for this product; the first as a filler for making rubber and the second for smelting to make ferro-silicon. Two test-programmes have now been started to examine these options in more depth. A contract has been signed with professors from the Kazakhstan National University, Al Farabi, to examine the use as a filler in making rubber, with further testing by Belarusian State Technological University in Minsk, and a contract with the National Centre for Complex Processing of Mineral Raw Materials of the Republic of Kazakhstan has been commissioned to test the production of briquettes and use for smelting. Results of both contracts are expected during H1 of 2022.

 

 

Nick Bridgen, CEO, commented: "Balasausqandiq benefits from a combination of low capital and operating costs, access to infrastructure, an advantageous location and huge scale.

 

"World demand for vanadium is growing as more vanadium flow-batteries to store renewable energy are being built and vanadium in its traditional use as an alloy of steel is needed to cut down on CO2 used in steel production.

 

"Through its ability to supply large quantities of vanadium at low cost, Balasausqandiq is destined to play an essential part in the reversal of global warming."

 

 

 

 

 

For further information, visit www.ferro-alloy.com or contact:

 

Ferro-Alloy Resources Limited

Nick Bridgen (CEO)

info@ferro-alloy.com

 

Shore Capital

(Corporate Broker)

VSA Capital

Jerry Keen/Toby Gibbs

 

Andrew Monk/Simon Barton

+44 207 408 4090

 

+44 (0)203 005 5000

St Brides Partners Limited

(Financial PR & IR Adviser)

Catherine Leftley

+44 207 236 1177

 

About Ferro Alloy Resources Limited:

The Company's operations are all located at the Balasausqandiq deposit in Kyzylordinskoye Oblast in the South of Kazakhstan. Currently the Company has two main business activities:

a) the high grade Balasausqandiq vanadium project (the "Project"); and

b) an existing vanadium concentrate processing operation (the "Existing Operation") 

Balasausqandiq is a very large deposit, with vanadium as the principal product together with several by-products. Owing to the nature of the ore, the capital and operating costs of development are very much lower than for other vanadium projects. 

A reserve on the JORC 2012 basis has been estimated only for the first ore-body (of five) which amounts to 23 million tonnes, not including the small amounts of near-surface oxidised material which is in the Inferred resource category. In the system of reserve estimation used in Kazakhstan the reserves are estimated to be over 70m tonnes in ore-bodies 1 to 5 but this does not include the full depth of ore-bodies 2 to 5. 

There is an existing concentrate processing operation at the site of the Balasausqandiq deposit. The production facilities were originally created from a 15,000 tonnes per year pilot plant which was then adapted to treat concentrates and expanded. Further expansion is being undertaken which is expected to result in annualised production capacity of around 1,500 tonnes of contained vanadium pentoxide plus significant by-product molybdenum. 

The strategy of the Company is to develop both the Project and the Existing Operation in parallel. Although they are located on the same site and use some of the same infrastructure, they are separate operations.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCBUBDBCDDDGBL
Date   Source Headline
29th Apr 20247:00 amRNSFinal Results
26th Apr 20247:00 amRNSQ1 2024 Production Results
15th Feb 20241:00 pmRNSSale of 3rd Tranche of Exempt Offer Bond Programme
1st Feb 20247:00 amRNSFeasibility Study Update & Bond Programme
12th Jan 20247:00 amRNSQ4 2023 Production Results
22nd Dec 20237:00 amRNSTrading Update
30th Nov 20237:00 amRNSTotal Voting Rights
22nd Nov 20237:00 amRNSHolding(s) in Company
21st Nov 202312:17 pmRNSDirector/PDMR Shareholding
14th Nov 20237:00 amRNSIssue of Equity
1st Nov 20235:08 pmRNSResult of AGM
17th Oct 20237:00 amRNSExempt Offer Bond Programme - Second Tranche Sale
10th Oct 202312:53 pmRNSExisting Operation Q3 Production Results
6th Oct 20237:00 amRNSNotice of AGM
19th Sep 20237:00 amRNSExempt Offer Bond Programme - Second Tranche
12th Sep 20237:00 amRNSInvestor Presentation
12th Sep 20237:00 amRNSGrant of Share Options
11th Sep 20237:00 amRNSHalf-year Report
21st Aug 20237:00 amRNSTrading Update
27th Jul 20239:00 amRNSLaunch of Bond Programme /Listing of First Tranche
19th Jul 20237:00 amRNSInvestor Presentation via Investor Meet Company
17th Jul 20237:00 amRNSExisting Operation H1 Production Results
3rd May 20237:00 amRNSInvestor Presentation via Investor Meet Company
2nd May 20232:25 pmRNSDirectors Share Purchase
2nd May 20232:20 pmRNSFull Updated Ore-Body 1 Mineral Resource Estimate
28th Apr 20237:00 amRNS2022 Final Results and Updated Ore-Body 1 MRE
30th Jan 20237:00 amRNSTrading & Operational Update and Grant Funding
20th Dec 20222:05 pmRNSSecond Price Monitoring Extn
20th Dec 20222:00 pmRNSPrice Monitoring Extension
20th Dec 20227:00 amRNSBalasausqandiq Feasibility Study Update
7th Dec 20227:00 amRNSFeasibility Study: Drilling Programme Completes
28th Nov 20224:41 pmRNSSecond Price Monitoring Extn
28th Nov 20224:36 pmRNSPrice Monitoring Extension
28th Nov 20222:05 pmRNSSecond Price Monitoring Extn
28th Nov 20222:00 pmRNSPrice Monitoring Extension
10th Nov 20223:43 pmRNSResult of AGM
13th Oct 20227:00 amRNSNotice of AGM
27th Sep 20226:00 pmRNSHolding(s) in Company
22nd Sep 20227:00 amRNSGrant of Options
15th Sep 20225:15 pmRNSResult of PrimaryBid Offer
15th Sep 202212:20 pmRNSResult of Placing and Subscriptions
15th Sep 20227:02 amRNSPrimaryBid Offer
15th Sep 20227:01 amRNSProposed Placing
15th Sep 20227:00 amRNSInterim Results
1st Jul 20227:38 amRNSBalasausqandiq Feasibility Study Update
1st Jul 20227:00 amRNSBalasausqandiq Feasibility Study Update
29th Jun 20227:00 amRNSGrant of Options
29th Apr 20227:00 amRNSFinal Results
5th Apr 20224:41 pmRNSSecond Price Monitoring Extn
5th Apr 20224:36 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.