Wressle Development Update

3 Aug 2020 07:00

Europa Oil & Gas (Holdings) Plc - Wressle Development Update

Europa Oil & Gas (Holdings) Plc - Wressle Development Update

PR Newswire

London, July 31

Europa Oil & Gas (Holdings) plc / Index: AIM / Epic: EOG / Sector: Oil & Gas

Europa Oil & Gas (Holdings) plc (‘Europa’ or ‘the Company’)

 Wressle Development Update

Europa Oil & Gas (Holdings) plc, the UK, Ireland and Morocco focused oil and gas exploration, development and production company, notes today’s update from Egdon Resources (‘Egdon’) confirming the commencement of site works at the Wressle Oil Field development (‘Wressle’ or the ‘Project’) in North Lincolnshire. This is in line with the previously stated target to achieve first oil at Wressle in H2 2020. Wressle lies on licences PEDL180 & 182 in which Europa holds a 30% working interest alongside Egdon (30%), and Union Jack Oil (40%).

As advised by the operator, Egdon, the civils contractor has mobilised to site and has commenced works to reconfigure the Wressle production area. Works being undertaken include the installation of a new High Density Polyethelene impermeable membrane; French drain system; an approved surface water interceptor; the construction of a purpose-built bund area for storage tanks; a tanker loading plinth; and an internal roadway system.

The reconfiguration of the Wressle production area forms a central part of the Wressle development plan, the key stages of which and work carried out to date are listed below:

Discharging the planning conditions, finalising detailed designs, tendering and procurement of materials, equipment and services and finalising all Health and Safety Executive (“HSE”) documentation and procedures: Key planning conditions have been discharged, detailed design tendering is underway and all HSE documentation and procedures are progressing in line with expectations Installation of groundwater monitoring boreholes and establishing baseline groundwater quality through monitoring and analysis: Four groundwater boreholes have been installed and two rounds of sampling and analysis undertaken to date Reconfiguration of the site: Site works have commenced Installation and commissioning of surface facilities Sub-surface operations Commencement of production

Simon Oddie, Interim CEO and Executive Chairman of Europa, said: “Today’s news that siteworks have commenced and that the Wressle field remains on course to commence production in H2 2020 is highly encouraging. With oil at over US$40 per barrel and Wressle requiring oil prices of US$17.62 per barrel to breakeven, we are keen to get what promises to be a highly profitable UK onshore field into production. At an initial gross rate of 500bopd, our 30% share in the field will equate to 150 bopd net to Europa which will scale up our existing production to well over 200bopd and in the process transform our revenue profile. This will provide us with a strong platform with which to advance our portfolio of multistage licences including our industry leading exploration position in the proven gas play of the Slyne Basin offshore Ireland and our large Inzegane permit offshore Morocco where initial work has identified 30 targets which could hold up to 10 billion barrels of oil."

Further Information on Wressle

Wressle was discovered by the Wressle-1 well in 2014. During testing, a total of 710 barrels of oil equivalent per day were recovered from three separate reservoirs, the Ashover Grit, the Wingfield Flags and the Penistone Flags. Under the development plan, Wressle is expected to commence production at an initial gross rate of 500bopd, which would more than double Europa’s existing UK onshore production to over 200bopd. With an estimated breakeven oil price of US$17.62 per barrel, production at Wressle is expected to be very profitable at current oil prices of over US$40 per barrel. In September 2016, a Competent Person’s Report provided independent estimates of reserves and contingent and prospective oil and gas resources for the Wressle discovery of 2.15 million stock tank barrels classified as discovered (2P+2C).

* * ENDS * *

For further information please visit www.europaoil.com or contact:

Simon OddieEuropa+ 44 (0) 20 7224 3770
Phil GreenhalghEuropa+ 44 (0) 20 7224 3770
Christopher RaggettfinnCap Ltd+ 44 (0) 20 7220 0500
Simon HicksfinnCap Ltd+ 44 (0) 20 7220 0500
Frank BuhagiarSt Brides Partners Ltd+ 44 (0) 20 7236 1177
Megan DennisonSt Brides Partners Ltd+ 44 (0) 20 7236 1177

Notes

Europa Oil & Gas (Holdings) plc has a diversified portfolio of multi-stage hydrocarbon assets which includes production, development and exploration interests, in countries that are politically stable, have transparent licensing processes, and offer attractive terms. In terms of production, in 2019 Europa produced 91 boepd. Production is set to increase to over 200 boepd in H2 2020 once the Wressle field in the UK, which is currently under development, comes on stream at a gross rate of 500 bopd.

The Company holds four exploration licences offshore Ireland which have the potential to host gross mean un-risked prospective resources of 3.9 billion barrels oil equivalent and 2.7* trillion cubic feet (‘tcf’) gas (*subject to regulatory approval for the transfer of FEL 3/19). The Company’s flagship projects offshore Ireland are Inishkea and Edge, two near field gas prospects in the Slyne Basin which the Company classifies as lower risk infrastructure-led exploration due to their close proximity to the producing Corrib gas field and associated gas processing infrastructure. In September 2019, Europa was awarded a 75% interest in the Inezgane permit offshore Morocco. Initial results of technical work have identified 30 prospects and leads that have the potential to hold close to 10 billion barrels of unrisked resources.

Date   Source Headline
27th Jan 20257:00 amRNSHolding(s) in Company
23rd Jan 20257:00 amRNSChange in Registered Office
18th Dec 20247:00 amRNSWhisby - Net Profits Agreement Terminated
12th Dec 20247:00 amRNSBoard Changes
29th Nov 20241:53 pmRNSResult of AGM
28th Nov 20247:00 amRNS-RNotice of Investor Presentation and Q&A
12th Nov 20247:00 amRNSWressle Planning Update
4th Nov 20247:00 amRNSNotice of AGM and Posting of Annual Report
30th Oct 20242:41 pmRNSDirector/PDMR Dealing
28th Oct 20247:00 amRNSFinal results for the year to 31 July 2024
18th Oct 20247:00 amRNSWressle Planning Update
17th Oct 20247:00 amRNSResponse to media speculation
16th Sep 20247:00 amRNSWressle - Receipt of Planning Approval
13th Sep 202410:05 amRNSP2358 Licence (Serenity) update
22nd Jul 20241:17 pmRNSDirector/PDMR Dealing
22nd Jul 20247:00 amRNSEG-08 Revised Prospective Resources
16th Jul 20247:00 amRNSHolding(s) in Company
24th Jun 20247:00 amRNSChange of Nominated Adviser
7th May 20247:00 amRNSRetail Investor Reception
3rd May 20247:00 amRNS33rd Licensing Round Update
22nd Apr 20247:00 amRNSUpdated Irish Licence Emissions Report
17th Apr 20249:41 amRNSDirector/PDMR Dealing
17th Apr 20247:00 amRNSInterim Results
8th Apr 20247:00 amRNSBoard Change
5th Mar 202410:31 amRNSDirector/PDMR Dealing
15th Feb 20241:37 pmRNSHolding(s) in Company
14th Feb 20247:00 amRNSExtension of PEDL 343 Licence (Cloughton)
29th Jan 20247:00 amRNSFEL 4/19 Licence Extension Approval
19th Jan 20247:00 amRNSAward & Concurrent Cancellation of Options
18th Jan 20246:08 pmRNSHolding(s) in Company
15th Jan 20247:00 amRNSWressle Production Update – PEDL180/182
5th Jan 20243:33 pmRNSDirector/PDMR Dealing
2nd Jan 20247:00 amRNSPEDL 180 and PEDL 182 Competent Person’s Report
21st Dec 202311:09 amRNSDirector/PDMR Dealing
21st Dec 20237:01 amRNSBoard Changes
21st Dec 20237:00 amRNSAcquisition of Interest in EG-08 Licence
19th Dec 20237:00 amRNSWressle Production Update – PEDL180/182
29th Nov 202311:05 amRNSWressle Operator Community Update
27th Nov 20237:00 amRNSAttempted Requisition of General Meeting
23rd Nov 20236:05 pmRNSResult of AGM
23rd Nov 20237:00 amRNSWithdrawal of AGM Resolutions
8th Nov 20237:00 amRNSWressle Production Resumes – PEDL180/182
6th Nov 20237:00 amRNSNotice of Investor Presentation
30th Oct 20237:00 amRNSNotice of AGM & Posting of Annual Report
23rd Oct 202310:59 amRNSDirector/PDMR Dealing
23rd Oct 20237:00 amRNSFinal Results
18th Oct 20237:00 amRNSWressle Update
4th Oct 20237:00 amRNSSerenity Update
2nd Oct 20237:00 amRNSFEL 4/19 Update
11th Sep 20237:00 amRNSCloughton Gas in Place Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.