Operations Update

6 May 2009 07:00

RNS Number : 7309R
Emerald Energy PLC
06 May 2009
 



Emerald Energy Plc

6 May 2009

Operations Update - Syria, Block 26

Emerald Energy Plc ("Emerald" or the "Company") is pleased to provide the following update on operations in Block 26, Syria. 

Khurbet East No.9 Development Well

The Khurbet East No.9 well, located approximately one kilometre south of the Khurbet East No.1 well and planned as the first of three development wells to support the expansion of the Khurbet East early production facility, has been drilled vertically to a total depth of 1,986 metres. The well encountered the top of the Cretaceous Massive reservoir at 1,937 metres and preliminary analysis of the wire-line logs indicates a 26 metre gross (23 metre net) oil-bearing interval within this reservoir with an average porosity over the net oil-bearing section of approximately 22%. A definitive oil-water contact was not identified in the well as the primary reservoir section lies directly above a relatively impermeable and low porosity section.

During the final 12 hours of a 24 hour open-hole flow test of the gross reservoir interval, the well flowed, under natural flow, at an average stabilised oil rate of approximately 3,040 barrels per day through a 48/64 inch choke and with a water cut of between 3% and 4%. Preliminary analysis of the flow test indicates very good reservoir permeability, consistent with the production wells in the central portion of the Khurbet East Field.

The Khurbet East No.9 well will be completed as a production well and tied-in to the early production facility. After completion of operations on Khurbet East No.9, the rig will commence drilling of the Khurbet East No.10 wellthe second of the three development wells planned to support the expansion of the early production facility.

Expansion of Khurbet East Early Production Facility

The expansion of the capacity of the early production facility to 18,000 barrels per day is proceeding on schedule with commissioning of the new equipment expected to commence in June and production start-up expected early in the third quarter of 2009

Exploration 3D Seismic Survey

Acquisition of the 850 square kilometre 3D seismic survey in the area around the Khurbet East and Yousefieh fields continues on schedule, with approximately 90% of the area completed. The Company expects the programme will be completed this month, with delivery of final processed data expected late in the third quarter of 2009 and interpretation of these data commencing immediately thereafter.

Emerald's Chief Executive Officer, Angus MacAskill, said:

"We are very pleased with progress towards delivery of the early production facility expansion, with the results of Khurbet East No.9, the first of three development wells planned to fill the additional capacity, demonstrating the southern extension of the excellent reservoir quality seen in the central portion of the field. We are also pleased with the progress in acquiring this large exploration 3D seismic survey and look forward to the results of the interpretation of these data later in the year."

Enquiries: Lisa Hibberd 020 7925 2440

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLQELFBKEBEBBD
Date   Source Headline
30th Sep 200812:17 pmRNSUpdate on activities
16th Sep 20082:57 pmRNSDrilling Update
15th Sep 20084:38 pmRNSBlock awarded in Peru
10th Sep 20087:00 amRNSKhurbet East Field Update, Bl
2nd Sep 20087:00 amRNSColombia - Vigia No.6 Well Re
1st Sep 20087:00 amRNSBlocklisting Interim Review
29th Aug 20087:00 amRNSTotal Voting Rights
26th Aug 20081:12 pmRNSResult of EGM
7th Aug 20083:23 pmRNSExtraordinary General Meeting
22nd Jul 20087:00 amRNSKhurbet East Update
14th Jul 20087:16 amRNSColombia - Operations Update
14th Jul 20087:16 amRNSInterim Results
10th Jul 20083:25 pmRNSHolding(s) in Company
10th Jul 20082:57 pmRNSTotal Voting Rights
8th Jul 20087:00 amRNSOperations Update
1st Jul 20087:49 amRNSKhurbet East Field Update, Bl
26th Jun 20088:19 amRNSAppointment of Joint Broker
17th Jun 20087:00 amRNSWell update
19th May 20087:00 amRNSOperations Update
15th May 20082:41 pmRNSResult of AGM
15th May 20087:00 amRNSInterim Management Statement
13th May 20086:00 amRNSKhurbet East Field Update, Bl
7th Apr 20087:57 amRNSContract Award in Colombia
25th Mar 20087:10 amRNSDrilling Report
17th Mar 20088:36 amRNSFinal Results
11th Mar 20082:47 pmRNSHolding(s) in Company
6th Mar 20082:56 pmRNSHolding(s) in Company
6th Mar 20087:00 amRNSActivities update
3rd Mar 20084:03 pmRNSHolding in Company
3rd Mar 20081:09 pmRNSBlocklisting Interim Review
26th Feb 20084:34 pmRNSHolding in Company
20th Feb 20084:38 pmRNSHolding(s) in Company
14th Feb 20087:01 amRNSOperations Review
13th Feb 20082:22 pmRNSHolding(s) in Company
13th Feb 20087:00 amRNSUpdate - Block 26, Syria
5th Feb 20087:00 amRNSSyria Update
7th Jan 20087:00 amRNSDrilling Report
20th Nov 20077:01 amRNSSyria Update
5th Nov 20077:01 amRNSUpdate on Block 26, Syria
24th Sep 20077:01 amRNSOperations update
3rd Sep 20077:00 amRNSBlock listing 6 month return
13th Aug 20077:01 amRNSInterim Results
27th Jul 20077:00 amRNSSyria Update
16th Jul 20077:14 amRNSExtension of PSC in Syria
16th Jul 20077:00 amRNSOperations review/update
13th Jul 200711:10 amRNSIssue of Convertible Bonds
28th Jun 20072:11 pmRNSHolding(s) in Company
15th Jun 20077:01 amRNSDrilling Report
4th Jun 20077:04 amRNSDrilling Report
29th May 20077:01 amRNSTotal Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.