Circle Oil Plc 

("Circle" or the "Company")

 

Operating Update Egypt

 

Circle Oil Plc (AIM: COP), the international oil and gas exploration, development and production company, is pleased to announce the following update regarding the Al Amir SE Field ("AASE") and the Geyad Field in Egypt.

 

AASE-18 Well

AASE-18 was spud on 7 July 2013 and is located in the north-western part of the AASE. The well encountered the Kareem sands over 200 feet high to prognosis with 34 feet of net pay in the Shagar and 32 feet of net pay in the Rahmi, both zones of good reservoir quality. Following successful logging, the well has been tested and completed as a Rahmi producer. Rahmi perforations between 9,757-9,797.5 feet MD were completed on 30 August 2013 and the well was put onto multi rate testing and pressure build up on 31 August. The flow test on a 48/64" choke produced at a rate of 1,952 bopd and 1.821 MMscf/d of gas (331boepd). Following a pressure build up, the well was connected for production with an initial flow rate on a 18/64" choke of 1,056 bopd of 42 degree API crude oil and 0.907 MMscf/d of gas (165 boepd).

AASE-15 Well

AASE-15 was spud on 23 August 2013, located in the north-western part of the field, downdip of and 800 metres north-west of Rahmi producer AASE18. This well is planned as a vertical hole to appraise the Shagar and Rahmi sands and, depending on reservoir quality and hydrocarbon saturation, may be completed as a Rahmi injector or a Shagar producer.

 

Production

The current gross daily production rate from the AASE and the Geyad Field is now standing at 11,234 bopd and 12.54 MMscf/d (2,282 boepd). Cumulative production from the NW Gemsa Concession has now exceeded 12.6 million barrels of 42 degree API crude oil.

Water Injection

Water injection in the AASE and Geyad Field is currently about 32,330 bwpd and the cumulative injection to date is about 13.5 MMbw.

 

The NW Gemsa Concession, containing the Al Amir and Geyad Development Leases, covering an area of over 260 square kilometres, lies about 300 kilometres south-east of Cairo in a partially unexplored area of the Gulf of Suez Basin.

 

The concession agreement included the right of conversion to a production licence of 20 years, plus extensions, in the event of commercial discoveries. The NW Gemsa Concession partners include: Vegas Oil and Gas (50% interest and operator); Circle Oil Plc (40% interest); and Sea Dragon Energy (10% interest).

 

 

Prof Chris Green, CEO, said

"Circle is very pleased with the results of the AASE-18 well, which will provide significant additional oil and gas production from the Al Amir SE field. This has resulted in a further increase in the total gross daily production to over 13,500 boepd."

Glossary

boepd

bopd

barrels of oil equivalent per day

barrels of oil per day

bwpd

barrels of water per day

MD

MMbw

MMscf/d

Measured Depth

Millions of barrels of water.

Millions of standard cubic feet of gas per day

 

In accordance with the guidelines of the AIM Market of the London Stock Exchange, Professor Chris Green, Chief Executive Officer of Circle Oil Plc, an explorationist and geophysicist with over thirty years oil & gas industry experience, and Dr Stuart Harker, VP Geology, also with over 30 years experience, are the qualified persons as defined in the London Stock Exchange's Guidance Note for Mining and Oil and Gas companies, who have reviewed and approved the technical information contained in this announcement. Professor Green and Dr Harker have relied on primary information supplied by the operator in carrying out their review.

For further information contact:

Circle Oil Plc (+44 20 7638 9571)

Professor Chris Green, CEO

 

Investec (+44 20 7597 5970)Chris SimGeorge Price

James Rudd

 

Liberum Capital Limited (+44 20 3100 2222)Simon Atkinson

 

Citigate Dewe Rogerson (+44 20 7638 9571)Martin JacksonJack Rich

Murray Consultants (+353 1 498 0320)Joe MurrayJoe Heron

 

Notes to Editors

 

Circle Oil Plc (AIM: COP) is an international oil & gas exploration, development and production Company holding a portfolio of assets in Morocco, Tunisia, Oman, and Egypt with a combination of low-risk, near-term production, and significant upside exploration potential. The Company listed on AIM in October 2004.

 

Internationally, the Company has continued to expand its portfolio over the past years and now has assets in the Rharb Basin, Morocco; the Ras Marmour Permit in southern Tunisia; the Mahdia Permit offshore Tunisia, and the Zeit Bay area of Egypt. Circle also has the largest licensed acreage of any company in Oman. In addition to its prospective Block 52 offshore, Circle has an ongoing exploration programme in Block 49 onshore.

Circle's strategy is to locate and secure additional licences in prospective hydrocarbon provinces and, through targeted investment programmes, monetise the value in those assets for the benefit of shareholders. This could be achieved through farm-outs to selected partners who would then invest in and continue the development of the asset into production, or Circle may opt to use its own expertise to appraise reserves and bring assets into production, generating sustained cash flow for further investment.

Further information on Circle is available on its website at www.circleoil.net

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBRGDCCUGBGXC
Date   Source Headline
3rd Aug 20107:00 amRNSPlacing
21st Jul 20107:00 amRNSDrilling Update Egypt
7th Jul 20102:48 pmRNSEgypt Operating Update
7th Jul 201012:08 pmRNSAppointment of Chief Executive Officer
28th Jun 20105:02 pmRNSPosting of Annual Report
21st Jun 20107:00 amRNSPreliminary Results
15th Jun 201011:37 amRNSHolding(s) in Company
4th Jun 20104:35 pmRNSBoard Changes
26th May 20107:00 amRNSEgypt Operating Update
21st Apr 201011:00 amRNSOperating Update Egypt
1st Apr 20105:18 pmRNSDavid Hough
25th Mar 201012:27 pmRNSOperational Update
22nd Mar 20102:30 pmRNSOperational Update
11th Mar 20107:00 amRNSAppointment of Nominated Adviser and Broker
9th Mar 20107:00 amRNSOperational Update - Egypt
4th Feb 20107:00 amRNSOperational Update - Egypt
1st Feb 20107:00 amRNSNew Moroccan Permits Signed
21st Jan 20104:37 pmRNSExercise of Options
20th Jan 20108:50 amRNSDrilling and Production Update
15th Jan 20107:00 amRNSOperational Update
11th Jan 20103:15 pmRNSExercise of Options and Total Voting Rights
23rd Dec 20099:19 amRNSGrant of Share Options
16th Dec 200912:41 pmRNSExercise of Warrants and Total Voting Rights
10th Dec 200911:44 amRNSOperating Update
24th Nov 20097:00 amRNSExercise of Options and TVR
17th Nov 20097:00 amRNSExercise of Options and Total Voting Rights
27th Oct 20091:30 pmRNSDrilling Update
22nd Oct 20097:00 amRNSAl-Amir SE-4 Well
21st Oct 20094:21 pmRNSAl-Amir SE-4 Well
8th Oct 200912:04 pmRNSExercise of Options and Total Voting Rights
1st Oct 20091:14 pmRNSExercise of Options and Total Voting Rights
23rd Sep 20097:00 amRNS2009 Interim Results
21st Sep 200910:48 amRNSExercise of Options
10th Sep 20093:02 pmRNSAGM Resolutions Passed
2nd Sep 20097:00 amRNSEgypt Update
1st Sep 20092:05 pmRNSExercise of Options
25th Aug 20097:00 amRNSDrilling Update
21st Aug 20092:01 pmRNS?16.5 Million Secondary Placing
1st Jul 20097:00 amRNSBoard Change
26th Jun 20094:35 pmRNSPosting of 2008 Report & Accounts
23rd Jun 20097:00 amRNSAvailability of 2008 Report and Accounts
22nd Jun 20097:05 amRNSPreliminary Results
19th Jun 20092:49 pmRNSDrilling Update
3rd Jun 20097:00 amRNSDrilling Update
19th May 20097:00 amRNSDrilling Update
1st May 200912:29 pmRNSChange of Registered Office
24th Apr 20097:00 amRNSBoard Appointment
23rd Apr 20097:00 amRNSMorocco Drilling Update
15th Apr 20097:00 amRNSMorocco Update
2nd Mar 20097:00 amRNSOperating Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.