H1 2022 Operational Update

5 Aug 2022 07:00

RNS Number : 0141V
Chaarat Gold Holdings Ltd
05 August 2022
 

05 August 2022

Chaarat Gold Holdings Limited

("Chaarat" or "the Company")

H1 2022 Operational Update

Chaarat (AIM:CGH), the AIM-quoted gold mining Company with an operating mine in Armenia and assets at various stages of development in the Kyrgyz Republic, announces its production and operational results for the half year ended 30 June 2022 ("H1" or the "Period") for its Kapan Mine ("Kapan") in Armenia and a general corporate update.

 

Kapan

 

As previously disclosed, Kapan experienced a fatal workplace injury on May 14th. This was the first recordable injury in over 14 months. Recordable injury frequency review ("RIFR") (per one million hours worked) is now 0.74 compared to 1.4 in H1 2021.

 

• Ore mined of 321.1 thousand tonnes ("kt") vs 303.7 kt in H1 2021 represents a year-on-year increase of 6.5%. Mine grade was 12.2% lower at 2.94 g/t AuEq in H1 2022 compared to 3.35 g/t AuEq in H1 2021. Focus for H2 2022 remains on reducing dilution and developing areas of the mine with wider veins.

 

• Mill throughput was stable at 373.3 kt year on year (-0.5%, H1 2021 374.8 kt), and mill AuEq recovery for own ore was also stable at 79.5% in H1 2022 compared with 79.4% in H1 2021.

 

Kapan production of 30,562 gold equivalent ounces1 ("oz") vs 33,248 oz in H1 2021 (-8.1%) consisting of 22,877 oz from own ore and 6,685 oz from third-party ore. Full-year guidance of 56-62koz of total own-ore and third-party ore production remains unchanged for 2022.

 

There were 62.7 thousand tonnes ("kt") of ore on stockpile at the end of the period.

 

All-in-sustaining cost ("AISC"2) of USD1,420 /oz vs USD1,063 /oz in H1 2021 (+33.6%). The increase is due to the strengthening of the Armenian Dram in Q2 2022 (AMD/USD + 10.3% vs H1 2021 average), increases in energy prices and cost of other raw materials in line with inflation seen across the mining sector globally.

 

Preliminary unaudited standalone EBITDA3 contribution of USD8.1 million vs USD13.5 million in H1 2021 (-40%). While EBITDA in Q1 was higher than in the same period last year, the decrease in EBITDA for H1 2022 was mainly driven by provisional pricing adjustments due to lower commodity prices and the adverse AMD/USD exchange rate in Q2 2022 increasing costs. If commodity prices remain soft, the Company expects an offsetting positive impact on the costs in H2 2022.

 

• Third-party ore treatment of 63.5kt for H1 2022 vs 70kt for H1 2021 (-9.3%) was in line with budget and contributed USD1.7 million to the above-mentioned EBITDA for H1 2022. This compares with a contribution of USD1.8 million for H1 2021 (-6%).

 

• The exploration work on the East flank is ongoing. First assay results of this multi-year project are expected by Q4 2022.

 

Outlook for Kapan

 

• Chaarat remains on track to deliver on its 50-53koz own ore and 6-9koz third-party ore guidance for the year.

 

Third-party ore supply is expected to remain in line with H1 for the remainder of 2022.

 

East Flank drilling campaign is ongoing as part of a 2-year programme to develop an initial JORC resource and reserve statement which is currently expected by the end of 2023.

 

The Company is continuing to take steps to mitigate the adverse exchange rate impact and increases in energy prices and cost of other raw materials.

 

Tulkubash & Kyzyltash

 

Chaarat performed a Tulkubash Reserve and Resource update including a 13% increase from 571koz to 647koz in Ore Reserves through a tonnage and grade increase based on the 2021 drilling programme results and a $1,600/oz pit shell optimisation.

 

Discussions with potential debt providers are ongoing. The Company expects these to be assisted by the recent resolution of the dispute between the Kyrgyz Government and Centerra Gold. Centerra Gold announced the closing of the agreement with the Kyrgyz government on 29 July 2022.

 

As previously indicated, construction activity will resume once financing has been secured.

 

• Metallurgical test work on the Kyzyltash core drilled in 2021 continues as planned. Full results are expected in Q3 2022. To date the results, support the findings of the previous Kyzyltash studies.

 

Corporate Finance

 

The Company continues discussions with various parties, including existing bondholders, regarding proposals in relation to the convertible bond due at the end of October 2022 and will provide an update on the status of these discussions in due course.

 

Chaarat reduced the principal outstanding for the Kapan acquisition loan by a further USD2.2 million to USD14.3 million outstanding resulting in unaudited Net Debt at group level of USD44.4 million4. A further USD2.3 million has been paid in July 2022, further reducing the Net Debt to USD42.1 million.

 

1 Gold equivalent ounces for 2021 recalculated on 2022 budget prices with Au at $1,775/oz and gold ratios of 75 for silver, 6,597 for copper and 20,381 for zinc. In last years' Q1 2021 operations update, 2021 oz were based on gold ratios of 68 for silver, 7,287 for copper and 21,862 for zinc leading to a lower AuEq number reported in that previous year.

2 AISC on a gold oz produced basis exclude smelter TC/RC charges, which in H1 2022 add c. USD 160/oz of cost. The H1 2022 AISC includes sustaining capex of c. USD3.1 million incurred during the period (which excludes non-sustaining capex i.e., development capex).

³ In reporting financial information, the Group presents EBITDA as an alternative performance measure, "APM", which is not defined or specified under the requirements of IFRS. The Group believes that this measure provides stakeholders with additional useful information on the performance of the business and, within that, Kapan. EBITDA is calculated by adjusting profit/(loss) for depreciation and amortisation, net finance costs, unrealised foreign exchange gain/(loss), fair value gain on warrant and change in provisions.

4 In reporting financial information, the Group presents Net debt as an alternative performance measure, "APM", which is not defined or specified under the requirements of IFRS. The Group Net debt comprises convertible loan notes, other loans, contract liabilities, lease liabilities and warrant financial liabilities, net of cash and cash equivalents.

 

 

Mike Fraser, Chief Executive Officer, commented:

"The tragic fatal event at Kapan on the 14th May was felt deeply across the Company. A detailed internal and external investigation was conducted, and remedial actions are underway.

 Kapan made good progress operationally in the quarter despite mining in narrower vein areas which had an impact on grade. Financial performance was impacted by lower commodity prices and a higher Armenian Dram compared to the US Dollar.

We are pleased to note in the final resolution of the dispute between Centerra and the Kyrgyz government. This was a material condition to progressing funding of our Tulkubash project in the second half of 2022.

Chaarat continues to evaluate opportunities for inorganic growth in line with our growth agenda. Gold equities have been impacted by reduced liquidity in the sector, but this in turn provides a unique opportunity to grow the value of the Company."

 

 

Enquiries

 

Chaarat Gold Holdings Limited

+44 (0)20 7499 2612

Mike Fraser, Chief Executive Officer

IR@chaarat.com

 

 

Canaccord Genuity Limited (NOMAD and Joint Broker)

+44 (0)20 7523 8000

Henry Fitzgerald-O'Connor

 

James Asensio

 

finnCap Limited (Joint Broker)

+44 (0)20 7220 0500

Christopher Raggett

 

 

 

Panmure Gordon (UK) Limited (Joint Broker)

+44 (0)20 7886 2500

John Prior

Hugh Rich

 

 

About Chaarat

 

Chaarat is a gold mining company which owns the Kapan operating mine in Armenia as well as Tulkubash and Kyzyltash Gold Projects in the Kyrgyz Republic. The Company has a clear strategy to build a leading emerging markets gold company through organic growth and selective M&A.

 

Chaarat aims to create value for its shareholders, employees and communities from its high-quality gold and mineral deposits by building relationships based on trust and operating to the best environmental, social and employment standards. Further information is available at www.chaarat.com/.

 

H1 2022 PRODUCTION & OPERATIONAL SUMMARY

 

H1 2022

H1 2021

Tonnes ore mined

321,136

301,658

AuEq Grade (g/t)

2.94

3.30

Tonnes ore milled

373,323

374,794

Tonnes ore milled (Third-Party Ore)

63,511

70,005

AuEq Recovery Kapan (%)

79.5

79.4

Gold equivalent production (oz)

30,562

33,285

Gold equivalent production (own ore)

23,877

26,266

Gold equivalent production (third party ore)

6,684

6,982

Gold production (oz)

17,944

18,154

Silver production (oz)

269,687

331,381

Copper production (t)

941

1,161

Zinc production (t)

2,804

3,170

AuEq Sales

25,118

22,909

Realised gold price (USD/oz)

1,858

1,783

AISC (USD/oz)

1,420

1,063

 

 

ENDS

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDDGGDIUUGDGDS
Date   Source Headline
25th Feb 20214:36 pmRNSPrice Monitoring Extension
17th Feb 20213:36 pmRNSHolding(s) in Company
16th Feb 20217:00 amRNSChaarat – Investor Presentation with Q&A Session
10th Feb 20219:09 amRNSHolding(s) in Company
10th Feb 20217:00 amRNSCompletion of US$52 million Financing Package
5th Feb 202112:25 pmRNSCompletion of US$ 22 million Debt Reduction
5th Feb 20217:00 amRNSFundraise and Planned Debt Reduction
21st Jan 20217:00 amRNSFY 2020 Production, Operational & Financial Update
7th Jan 20217:00 amRNSAppointment of Joint Broker
30th Dec 20201:06 pmRNSRefinancing of Balance of Investor Loan
17th Nov 20204:41 pmRNSSecond Price Monitoring Extn
17th Nov 20204:35 pmRNSPrice Monitoring Extension
13th Nov 20207:00 amRNSCessation of hostilities in Nagorno-Karabakh
5th Nov 20203:10 pmRNSHolding(s) in Company
2nd Nov 20207:00 amRNSIssue of balance of security fee shares to Labro
28th Oct 20207:00 amRNSQ3 2020 Production and Operational Update
26th Oct 20207:00 amRNSHolding(s) in Company
23rd Oct 20207:00 amRNSCompletion of Debt Refinancing & PDMR shareholding
8th Oct 20207:00 amRNSKyrgyz Republic update
6th Oct 20201:30 pmRNSDebt Refinancing of Investor Loan
30th Sep 20207:00 amRNSArmenia update
21st Sep 20203:00 pmRNSHolding(s) in Company
18th Sep 20207:00 amRNSHolding(s) in Company
16th Sep 202012:15 pmRNSGrant of Waiver
11th Sep 20204:40 pmRNSSecond Price Monitoring Extn
11th Sep 20204:35 pmRNSPrice Monitoring Extension
11th Sep 20207:00 amRNSRetail Investor Presentation
11th Sep 20207:00 amRNSInterim results for six months ended 30 June 2020
8th Sep 20207:00 amRNSAnalyst & Investor Call on H1 2020 Interim Results
4th Sep 20207:00 amRNSAppointment of Nominated Adviser and Joint Broker
11th Aug 20202:37 pmRNSHolding(s) in Company
6th Aug 20209:59 amRNSHolding(s) in Company
4th Aug 20207:00 amRNSH1 2020 Production and Operational Update
26th Jun 20204:41 pmRNSSecond Price Monitoring Extn
26th Jun 20204:36 pmRNSPrice Monitoring Extension
10th Jun 20207:00 amRNSGrant of waiver
9th Jun 20208:06 amRNSKyzyltash update
21st May 20207:00 amRNSQ1 2020 Operational and Production Update
20th May 20203:11 pmRNSResult of AGM
1st May 20204:08 pmRNSHolding(s) in Company
30th Apr 20204:01 pmRNSHolding(s) in Company
27th Apr 20206:01 pmRNSProceeds and closure of Placing - Replacement
27th Apr 20205:36 pmRNSHolding(s) in Company
27th Apr 20207:00 amRNSConfirmed proceeds and closure of Placing
23rd Apr 20205:27 pmRNSNotice of AGM and 2019 Annual Report
15th Apr 20206:01 pmRNSWebcast - Corporate Update & Proposed Equity Raise
15th Apr 20207:30 amRNSProposed Equity Capital Raise and Funding Update
9th Apr 20203:30 pmRNSFinal results for year ended 31 December 2019
9th Apr 20202:20 pmRNSExtension of investor loan
30th Mar 202012:07 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.