Operational Update

29 Jul 2015 07:01

RNS Number : 3958U
LGO Energy PLC
29 July 2015
 

For Immediate Release, 7am

 

29 July 2015

 

LGO ENERGY PLC

("LGO" or the "Company")

 

Operational Update

 

LGO is pleased to announce that its latest development well, GY-676, at its Goudron Field development in Trinidad, reached total depth at 3,545 feet measured depth ("MD") on 19 July 2015. Electric log interpretation from both the Goudron Sandstone and C-sand intervals confirms the presence of recoverable hydrocarbons, with the net hydrocarbon pay in the main C-sand target estimated as 222 feet. The well has been successfully cased for future production.

Well GY-676 is the fifth of the seven 2015 wells and the second well from drilling Pad 5 in the north-east of the field. Net oil pay in the Goudron Sandstone was encountered between 535 and 1,255 feet with an estimated 250 feet of total net pay. The oil bearing C-sand interval was encountered between 1,870 and 3,455 feet MD. Shows of light oil at surface were reported at a depth of 2,077 feet, typical for these wells which are drilled close to pressure balance. Net hydrocarbon bearing pay in the C-sand interval is estimated as 222 feet. These observed net pay zones are fully in line with pre-drill expectations for this well.

The next well in the planned sequence, GY-677, the sixth in the 2015 program, and the fourteenth in the field redevelopment program has now been spudded and drilled and cased to the first casing point at 355 feet MD.

 

Second Quarter Production

Group oil production averaged 951 bopd during the second quarter 2015. This includes managed natural depletion from the new wells drilled last year on Pads 1, 2 and 3 at Goudron. This figure does not reflect production from Goudron Pad 4 since wells GY-672, GY-673 and GY-674, were drilled during the second quarter and only brought on line at the end of the period. Operations continue to optimise production from those new Pad 4 wells and a further update on that will be issued in due course. Once all seven 2015 wells have been completed the Company will be able to update production guidance.

 

Future Goudron Drilling Plans

Well Services Rig 70 has been moved to the next cellar on Pad 5 and it has spudded the sixth well of the 2015 program, GY-677, which is planned to be drilled to a total depth of 3,286 feet MD (3,000 feet TVDss) at a location 540 feet south-west of the surface location. Well GY-677 is once again targeting a C-sand reservoir interval.

The final well in the 2015 C-sand program, well GY-678, will be drilled from Pad 3 and will target an area which is similar to the very successful well GY-670 which was flowed at rates above 1,000 barrels of oil per day in late 2014. Further drilling on Pad 5 is planned for at a later date. Well GY-678 will be designated a "data well" with additional tests including the cutting of a 30-foot core in the C-sand. This additional data is key to the planned enhanced oil recovery ("EOR") project for which we are planning a pilot project which we anticipate commencing in 2016.

 

A program of shallow Goudron Sandstone wells, which can be drilled using a smaller drilling rig, is now being worked-up with plans to commence that work later in the year. A rig has been identified and it is being brought up to necessary specifications for this work. Sites are being selected for the drilling of simple low cost vertical wells to depths up to 1,700 feet in order to exploit the Goudron Sandstone. The thirteen wells drilled in our 2014 and 2015 campaigns have so far exhibited an average of 288 feet of net oil pay in the Goudron Sandstone. Site preparation can be scaled back considerably with the use of the small footprint rig, and locations can therefore be sited close to Goudron Sandstone targets across the field.

 

As previously announced, the recent independent reserves assessment by LR Senergy identified between 170 and 343 million barrels of Proved and Probable oil in place in the Goudron Sandstone. This new drilling work is intended to start to convert a portion of that to producing reserves and broaden the production base. To accommodate the expanded drilling program, we have made the necessary applications for the current 30 well environmental approvals to be increased to 60 wells.

 

Fergus Jenkins, LGO's Chief Operating Officer, commented:

"Our C-sand drilling program at Goudron continues to progress very well and we are now on our sixth new well in 2015. Drilling times and costs have been markedly reduced from 2014 and we have been collecting valuable data to plan the future development of the field, including the EOR project which has exciting potential. Goudron continues to operate in a very efficient fashion with low historical operating costs of less than $10 per barrel which is beneficial in the low oil price environment in which we continue to have to operate."

 

Steve Horton, LGO's Chairman, commented:

 

 "The Company has a sound investment case for the long-term development of its portfolio in Spain and Trinidad. The Goudron asset in Trinidad, with its low operating cost, is especially robust to low oil prices and we are confident of the Company's underlying value."

 

Qualified Person's Statement:

The information contained in this announcement has been reviewed and approved by Neil Ritson, Chief Executive Officer and Director for LGO Energy plc, who has over 35 years of relevant experience in the oil industry. Mr. Ritson is a member of the Society of Petroleum Engineers (SPE), an Active Member of the American Association of Petroleum Geologists (AAPG) and is a Fellow of the Geological Society of London.

 

 

Enquiries:

LGO Energy plc

+44 (0) 203 794 9230

Neil Ritson

Fergus Jenkins

Beaumont Cornish Limited

+44(0) 20 7628 3396

Nomad

Rosalind Hill Abrahams

Roland Cornish

FirstEnergy Capital LLP

+44(0) 20 7448 0200

Joint Broker

Jonathan Wright

David van Erp

 

Bell Pottinger

+44 (0) 20 3772 2500

Financial PR

Henry Lerwill

 

Glossary:

 

C-sand

sandstone reservoirs below the pre-Mayaro unconformity and above the pre-Lower Cruse unconformity encompassing sandstones of equivalent age to both the Gros Morne and the Lower Cruse formations

EOR

enhanced oil recovery

oil in place or STOIIP

stock tank oil initially in place, those quantities of oil that are estimated to be in known reservoirs prior to production commencing

pay and net pay

a reservoir or portion of a reservoir formation that contains economically producible hydrocarbons. The overall interval in which pay sections occur is the gross pay; the portion of the gross pay that meets specific criteria such as minimum porosity, permeability and hydrocarbon saturation are termed net pay

proved reserves

those quantities of petroleum, which, by analysis of geoscience and

engineering data, can be estimated with reasonable certainty to be commercially recoverable (1P), from a given date forward, from known reservoirs and under defined economic conditions, operating methods, and government regulations

probable reserves

those additional reserves which analysis of geoscience and engineering data indicate are less likely to be recovered than Proved Reserves but more certain to be recovered than Possible Reserves. It is equally likely that actual remaining quantities recovered will be greater than or less than the sum of the estimated Proved plus Probable Reserves (2P)

MD

measured depth; the depth of a well measured along the length of the borehole

TD

total depth

TVDss

true vertical depth below the sea level datum

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCPKCDQPBKKCOB
Date   Source Headline
1st Jul 201610:54 amRNSHolding(s) in Company
14th Jun 20167:00 amRNSFinancing and Goudron Field Update
9th Jun 20164:26 pmRNSIssue of shares for services and TVR
9th Jun 20161:38 pmRNSAnnual Report and Accounts and Notice of AGM
25th May 20169:53 amRNSHolding(s) in Company
18th May 20166:07 pmRNSHolding(s) in Company
13th May 20165:23 pmRNSHolding(s) in Company
13th May 20165:18 pmRNSHolding(s) in Company
12th May 20165:41 pmRNSHolding(s) in Company
12th May 201612:52 pmRNSHolding(s) in Company
12th May 20167:00 amRNSWell GY-50 and first quarter 2016 production
10th May 20166:04 pmRNSHolding(s) in Company
10th May 201612:42 pmRNSHolding(s) in Company
4th May 20165:17 pmRNS£3.25million Fundraising, Loan Restructuring & TVR
27th Apr 20167:00 amRNSRecompletion of Well GY-671, Goudron
20th Apr 20167:00 amRNSGoudron Operational Update
18th Apr 20163:28 pmRNSResult of Meeting, Issue of Equity, TVR
6th Apr 20169:36 amRNSUpdate Goudron Workover Program
1st Apr 20164:13 pmRNSTotal Voting Rights
31st Mar 20167:00 amRNSNotice of General Meeting
24th Mar 20167:00 amRNSGoudron Overriding Royalty Rates Reduced
16th Mar 20167:00 amRNS£1.95 million Share Issues
14th Mar 20167:00 amRNSUpdate Goudron production investment
9th Mar 20167:00 amRNSTermination of Offer Period and Goudron update
4th Mar 20167:00 amRNSBanking Update
25th Feb 20162:49 pmRNSREPLACEMENT Form 8.3 - LGO Energy PLC
25th Feb 201610:01 amRNSForm 8.3 - LGO Energy PLC
24th Feb 20167:00 amRNSCorporate and Operations Update
4th Feb 20162:05 pmRNSForm 8 (OPD) LGO Energy Plc (Replacement)
1st Feb 201612:23 pmRNSTotal Voting Rights
29th Jan 20164:25 pmRNSForm 8.3 - LGO Energy PLC
22nd Jan 20167:00 amRNSIssue of Shares, TVR and Rule 2.10
19th Jan 20166:00 pmRNSConference Presentation
31st Dec 20157:00 amRNSTotal Voting Rights
24th Dec 201512:23 pmRNSUpdate on Trinity-Inniss
17th Dec 20154:38 pmRNSForm 8.3 - LGO Energy PLC
14th Dec 201511:57 amRNSForm 8.3 - [LGO Energy PLC]
14th Dec 20157:00 amRNSIssue of Equity, TVR and Rule 2.10 Announcement
11th Dec 20153:03 pmRNSForm 8 (OPD) LGO Energy plc
8th Dec 20152:46 pmRNSShares Issued and Rule 2.10 Announcement
7th Dec 20158:00 amRNSStrategic review and commencement of Offer Period
7th Dec 20157:00 amRNSTabaquite Block, Trinidad
4th Dec 201510:09 amRNSSettlements with Various Creditors
26th Nov 201512:20 pmRNSBanking update and board change
3rd Nov 20157:00 amRNSCorporate and Operational Update
19th Oct 20157:00 amRNSUpdate Goudron Field well GY-678, Trinidad
12th Oct 20157:00 amRNSAcquisition of 25% stake in Bolt
5th Oct 20157:00 amRNS£1 million raised for further Goudron investment
24th Sep 20157:00 amRNSGoudron Sandstone oil production
22nd Sep 20152:42 pmRNSPresentation at First Energy Conference

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.