Netherlands - Development Update

15 Feb 2007 15:00

Embargoed for release: 1500 on 15 February 2007

Northern Petroleum Plc ("The Company" or "Northern") Netherlands - Development Update

Northern Petroleum Plc, the oil and gas production, development and exploration company with core interests under its management in The Netherlands, Italy and the United Kingdom, announces updated development plans for six oil and gas fields in The Netherlands. First production is delayed and now targeted to come on-stream in stages between 2007 year end and March 2008. Forecasted production levels have been increased through the concentration of efforts on three fields. On-site operations are starting in early March 2007.

Highlights:

* The initial gross production level target has been increased to 2300 barrels of oil per day ("bopd") and 10 Mw of electrical generating capacity by the end of March 2008; * The three fields are projected to yield a total oil and gas income at a rate ahead of previous projections at that stage; * Brakel well has been scheduled to be re-perforated during early March 2007 and testing should be completed before the end of the month; * The Ottoland oil field lateral well has been scheduled to commence in early April 2007; and * Much of the pre-engineering design work on the fields has been completed to make the final planning and construction period as short as possible.

Northern Petroleum Nederland B.V. ("NPN") has now significantly redesigned and improved the development plans for its six onshore oil and gas fields in The Netherlands. NPN has taken advantage of the benefits of flexibility offered by a six field development project. Efforts will now maximise the potential of the projects where regulatory approvals are in place or are expected imminently, namely Brakel, Ottoland and Papekop.

The gross production level target has been increased to 2300 bopd and 10 Mw of electrical generating capacity by end of March 2008 from the originally targeted 1000 bopd and 40Mw of electricity generation capacity at the end of 2007. Higher profit margins should result.

The licences have been affected by the delays at the central level of administration caused by the recent rapid increases in licensing and field activities. Such delays have been more evident than those from shortages of equipment and services.

Two of the Andel licence fields are being tackled first: Brakel and Ottoland. The Brakel well has been scheduled to be re-perforated in early March 2007 and testing should be completed before the end of the month. The objective is to increase gas deliverability and triple on-site electricity generating capacity from 2Mw to 6Mw.

The contracted rotary drilling rig is currently scheduled to be on the Ottoland site in early April to drill the long lateral intersection of the Bunter sandstone oil reservoir. It is designed to provide a much enhanced rate of oil production. The timing of the rig arrival may vary, earlier or later, according to when the rig is released from its current operations.

Upon release from Ottoland the rig will be utilised on third party operations, following which NPN plans to exercise its option for a second well, Papekop-1z, subject to successful prior fulfilment of final permitting requirements.

As much pre-engineering design work has been completed as is efficiently practicable to make the final planning and construction period as short as possible. Advanced tendering and contracting of the longest lead time items is in progress, one factor successfully accommodated in the project re-structuring.

Under the revised development plan it is projected that the three fields will yield a total oil, gas and electricity income at a rate ahead of the previous projections for March 2008.

The transfer of the part of the Drenthe production licence to NPN is taking longer than previously expected as the old licence has to be amended in line with the post-2003 changes to the Mining Legislation. This has affected the timing for the development of the substantial Geesbrug gas field and Grolloo, but in the meantime much of the engineering design work has continued to minimise the potential for delays. The financial terms will be more favourable than under the old Drenthe licence. The development of these fields and the Andel VI discovery will follow as soon as possible.

Derek Musgrove, Managing Director of Northern, stated:

"I am pleased that our team has demonstrated a flexible response to non-operational delays. In part, this demonstrates the strength of a six field position and original production level plans which were not too ambitious in the first phase. The response to reinforce projects gaining progress on the administration and planning fronts with additional effort and resources has been the correct action.

"The fundamental value of the assets has not been impaired and oil, gas and electricity prices are still significantly ahead of our original forecasts."

In accordance with the AIM Rules - Guidance for Mining and Oil & Gas Companies, the information contained in this announcement has been reviewed and signed off by the Exploration Manager of Northern, Mr Graham Heard BSc (Hons), who has over 30 years experience as a petroleum geologist.

---ENDS---

For further information please contact:

Northern Petroleum Plc Tel: +44 (0) 20 7743 6080

Derek Musgrove, Managing Director

Graham Heard, Exploration Manager

Investec Tel: +44 (0) 20 7597 5000

Michael Ansell

Panmure Gordon & Co Tel: +44 (0) 20 7459 3600

Katherine Roe

Bishopsgate Communications Limited Tel: +44 (0) 20 7562 3350

Nick Rome / Maxine Barnes

Notes to Editors:

Northern Petroleum Plc is an oil and gas production, development and exploration company with core interests under its management in The Netherlands, Italy and the United Kingdom and other interests in Guyane and Spain. The Company has proven and probable reserves of 60.5 million barrels of oil equivalent and is currently working towards putting its six Netherlands development assets into production with the support of Standard Bank. Further information on Northern is available at www.northpet.com.

NORTHERN PETROLEUM PLC
Date   Source Headline
30th Jun 20082:30 pmPRNResult of AGM
30th Jun 20087:00 amPRNAGM Statement
16th Jun 20087:45 amPRNBoard Appointments at ATI Oil Plc
5th Jun 20088:53 amPRNNotification of Shareholding
5th Jun 20088:50 amPRNNotification of Shareholding
2nd Jun 20087:00 amPRNExtension of Loan Facility to ATI Oil Plc
20th May 200810:55 amPRNNotification of Shareholding
15th May 20088:57 amPRNNotification of Shareholding
14th May 20085:47 pmPRNDirector/PDMR Shareholding
14th May 20087:00 amPRNPlanning permission to drill extension of oil field
12th May 20087:01 amPRNUnaudited Preliminary Results
9th May 20084:13 pmPRNNotice of Results
30th Apr 20087:00 amPRNTotal Voting Rights
2nd Apr 20087:00 amPRNOperations Update
31st Mar 200811:07 amPRNNotification of Shareholding
10th Mar 20086:16 pmPRNCorrection : Adriatic Resource Upgrade
10th Mar 20087:00 amPRNAdriatic Resource Upgrade
1st Feb 20083:40 pmPRNNotification of Shareholding
29th Jan 20088:09 amPRNAward of Fifth Italian Licence
15th Jan 200810:19 amPRNHolding(s) in Company
14th Jan 200812:20 pmPRNHolding(s) in Company
9th Jan 20087:00 amPRNHolding(s) in Company
28th Dec 200712:29 pmPRNAppointment of Broker
20th Dec 200710:49 amPRNIssue of Warrants
4th Dec 20072:38 pmPRNRovesti Update
30th Nov 20079:25 amPRNTotal Voting Rights
21st Nov 200712:53 pmPRNHolding(s) in Company
14th Nov 20074:15 pmPRNHolding(s) in Company
7th Nov 20073:15 pmPRNDirector/PDMR Shareholding
6th Nov 20073:27 pmPRNAdditional Listing
1st Nov 200711:05 amPRNDirector/PDMR Shareholding
31st Oct 20077:00 amPRNTotal Voting Rights
30th Oct 200712:07 pmPRNAdditional Listing
29th Oct 20076:00 amPRNChange of Registered Office
26th Oct 20077:00 amPRNATI Loan Extension
18th Oct 20078:57 amPRNDirector/PDMR Shareholding
10th Oct 20073:57 pmPRNHolding(s) in Company
4th Oct 20077:00 amPRNGiove P2 Reserves
2nd Oct 20077:00 amPRNDyas Agreement Completed
27th Sep 20077:00 amPRNHalf-yearly Report
25th Sep 200712:02 pmPRNNotice of Results
11th Sep 20075:51 pmPRNHolding(s) in Company
11th Sep 20077:00 amPRNAward of Italian Licences
5th Sep 20078:29 amPRNHolding(s) in Company
29th Aug 20078:50 amPRNHolding(s) in Company
28th Aug 20078:30 amPRNHolding(s) in Company
20th Aug 200712:00 pmPRNPreliminary Production Testing of Avington-3z Well
17th Aug 20074:55 pmPRNAIM Rule 26 Website
31st Jul 200711:25 amPRNAdditional Listing and Total Voting Rights
30th Jul 20077:00 amPRNTransfer of Licences

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.