Pin to quick picksBushveld Minerals Regulatory News (BMN)

Share Price Information for Bushveld Minerals (BMN)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.65
Bid: 0.60
Ask: 0.70
Change: 0.025 (4.00%)
Spread: 0.10 (16.667%)
Open: 0.625
High: 0.68
Low: 0.65
Prev. Close: 0.625
BMN Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q3 2022 and 9M 2022 Operational Update

25 Oct 2022 07:00

RNS Number : 9499D
Bushveld Minerals Limited
25 October 2022
 

Market Abuse Regulation ("MAR") Disclosure

 

This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 ("MAR"), and is disclosed in accordance with the Company's obligations under Article 17 of MAR. 

 

25 October 2022

Bushveld Minerals Limited

("Bushveld Minerals" "Bushveld" or the "Company")

Q3 2022 and 9M 2022 Operational Update

Bushveld Minerals Limited (AIM: BMN), the integrated primary vanadium producer and energy storage solutions provider ("Bushveld"), today provides an operational update for the three months and nine months ending 30 September 2022.

 

Group highlights

· Production of 2,657 mtV for 9M 2022 (9M 2021: 2,629 mtV).

· Production of 1,016 mtV for Q3 2022 (Q2 2022: 668 mtV) supported by Kiln 3 improved performance.

· Weighted average production cash cost (C1)[1] of US$28.9/kgV for 9M 2022 (9M 2021: US$25.80/kgV).

· Weighted average production cash cost (C1) of US$29.3/kgV for Q3 2022 (Q2 2022: US$31.0/kgV.)

 

2022 Group guidance

· Production guidance of 3,900 mtV - 4,100 mtV maintained.

· (C1) Production cash cost guidance at each asset is maintained.

· On track to achieve an annualised steady state production run rate of 5,000 mtVp.a. - 5,400 mtVp.a. by the end of 2022..

 

Fortune Mojapelo, CEO of Bushveld Minerals Limited, commented: 

"I am pleased to report a solid production update for the quarter to end-September, reflecting continued stability at Vametco and further ramp-up at Vanchem's Kiln 3. Despite ongoing power supply issues, the ramp-up at Kiln 3 has seen monthly production more than double from July's production. I am pleased to report that as a result of Kiln 3, total production at Vanchem has increased by 83% compared to the previous quarter. 

This year, South Africa has experienced unprecedented levels of loadshedding whereby the state utility temporarily turns off the electricity to an area due to a supply shortage. Q3 2022 was notably a severe period of loadshedding since the onset of the energy crises in 2007, with 75 events totalling to 218 hours of load shedding and, in turn, lost or significantly curtailed production hours. Calendar 2022 is proving to be the worst year in the last 5 and September was so far the worst month.

The near-term prognosis from Eskom does not indicate significant improvement and at Vanchem, where we are primarily affected, we will continue to use diesel generators during loadshedding periods. Engagements with the local municipality to explore ways to mitigate the impacts are ongoing. In addition, we are exploring renewable self-generation options to supplement power requirements, similar to the mini-grid project we are constructing at Vametco.

The elevated inflationary environment globally continues to put pressure on costs, which we expect to be partially mitigated by the increase in production throughput rates, our continued efforts on cost reduction and the benefit of a weaker ZAR.

Despite these challenges, we remain on track to achieve our annualised steady state production target by the end of 2022, as well as our cost guidance for each asset."

Conference call

Bushveld Minerals Chief Executive Officer, Fortune Mojapelo, and Finance Director, Tanya Chikanza will host a conference call at 12:30 pm UK time (13:30 pm SAST) today to discuss the quarterly update with analysts and investors. Participants may join the call by dialling:

Tel: United Kingdom: +44 (0) 330 551 0200, Toll Free: 0808 109 0700; South Africa: +27 11 589 8302, Toll Free: 0 800 980 512

Password: Quote Bushveld when prompted by the operator.

A replay of the conference call will be available on the Company's website post the call.

 

BUSHVELD VANADIUM

 

Group1

 

Unit

 

Q3 2022

 

9M 2022

9M 2022 vs

9M 2021

Q3 2022 vs

Q3 2021

Q3 2022 vs

Q2 2022

Production

mtV2

1,016

2,657

1.0%

-3.7%

52.1%

Sales3

mtV2

1,034

2,678

10.0%

25.2%

31.4%

Weighted average production cash cost (C1)

US$/kgV

29.3

28.9

12.1%

20.8%

5.7%

1. Based on provisional, unaudited figures.

2. mtV = metric tonnes of vanadium.

3. Reported as final sales to customers.

 

VAMETCO

Operational highlights for Vametco (on a 100% basis)1

Description

Unit

 

Q3 2022

 

9M 2022

9M 2022 vs

9M 2021

Q3 2022 vs

Q3 2021

Q3 2022 vs

Q2 2022

Ore mined

Tonnes

 430 316

1 174 672

34.8%

18.1%

35.1%

Total mined (ore + waste)

Tonnes

1 328 291

 3 000 452

27.0%

48.0%

68.1%

Ore grade (in Whole Rock)

% V2O5

0.96

0.86

22.9%

17.1%

14.3%

Concentrate produced

Tonnes

106 096

 290 746

3.1%

-6.7%

24.7%

Concentrate grade

% V

 1.03

 1.04

-1.9%

-3.7%

-1.9%

Recovery from Kiln to MVO

%

70.3

72.9

1.2%

-6.3%

-8.7%

Production (Nitro Vanadium)

mtV2

666

 1 892

7.9%

-12.9%

39.7%

Production cash cost (C1)3

ZAR/KgV

 457.4

 395.2

11.4%

40.1%

20.7%

Production cash cost (C1)3

US$/KgV

26.9

24.8

1.6%

20.6%

10.2%

Foreign exchange rate

ZAR: USD

 17.0

 15.9

9.4%

16.4%

9.4%

1. Based on provisional, unaudited figures. Bushveld's net attributable interest of the above figures is approximately 74%. Production cash cost is based on vanadium produced.

2. mtV = metric tonnes of vanadium.

3. Excludes depreciation, royalties and selling, general & administrative and social expenses. Production cash cost is based on vanadium produced. Production cash cost (C1) measure does not have any standardized meaning prescribed by IFRS and differs from measures determined in accordance with IFRS. This measure is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. This measure is not necessarily indicative of net earnings or cash flow from operating activities as determined under IFRS. 

 

Production

· 9M 2022 production of 1,892 mtV (9M 2021: 1,753 mtV). The increase is supported by continued operational performance and stability.

- Q3 2022 production of 666 mtV (Q2 2022: 477 mtV). The annual planned maintenance shutdown was conducted in Q2 2022.

Costs

· 9M 2022 production cash cost (C1) of US$24.8/kgV (9M 2021: US$24.4/kgV). Inflationary pressures resulted in higher raw materials costs and energy costs which were partially offset by a weaker ZAR:USD exchange rate.

- Q3 2022 production cash cost (C1) of US$26.9/kgV (Q2 2022: US$24.4/kgV). The increase is attributable to the greater use of raw materials during the quarter.

· Costs are expected to normalise through the rest of the year, with 2022 production cash costs expected to be within guidance as we keep implementing our cost containment initiatives but remain dependant on inflationary pressures not increasing even further.

 

2022 Guidance

· On track to meet full-year production guidance of 2,550 mtV - 2,650 mtV.

· On target to meet production cash cost (C1) guidance of US$22.7/kgV - US$23.5/kgV (ZAR346.9/kgV and ZAR358.7/kgV).

 

VANCHEM

Operational highlights for Vanchem1

Description

Unit

Q3 2022

9M 2022

9M 2022 vs

9M 2021

Q3 2022 vs

Q3 2021

Q3 2022 vs

Q2 2022

Ore Milled

Tonnes

 69 237

 168 907

19.6%

30.0%

28.5%

Ore Grade (in Whole Rock)

% V2O5

 1.41

 1.33

-5.0%

-3.0%

14.8%

Milled ore to kiln

Tonnes

 51 108

 124 101

26.3%

39.5%

29.0%

Milled Ore Grade

% V

 0.93

 0.94

0.0%

0.1%

-1.5%

Vametco concentrate to kiln

Tonnes

 2 846

 9 689

-41.2%

-48.3%

106.0%

Concentrate Grade

% V

 0.93

 0.94

-11.0%

-12.0%

-2.8%

Recovery: Kiln to Final Product

%

 71.4

 68.6

-16.0%

-6.0%

-1.9%

Chemicals

mtV2

 26

 137

-23.2%

-71.6%

-65.4%

Flake

mtV2

 69

 76

-70.5%

16.8%

100.0%

FeV

mtV2

 255

 552

80.7%

82.1%

120.8%

Nitro Vanadium 

mtV2

 -

 -

-100.0%

0.0%

0.0%

Total production

mtV2

 350

 765

-12.7%

20.4%

83.3%

Production cash cost (C1)3

ZAR/kgV

 574.9

 623.5

48.9%

44.2%

-23.8%

Production cash cost (C1)3

US$/kgV

 33.8

 39.1

36.2%

23.8%

-30.4%

Foreign exchange

ZAR: USD

 17.0

 15.9

9.4%

16.4%

9.4%

 

1. Based on provisional, unaudited figures.

2. mtV = metric tonnes of vanadium

3. Excludes depreciation, royalties and selling, general & administrative and social expenses. Production cash cost is based on vanadium produced. Production cash cost (C1) measure does not have any standardized meaning prescribed by IFRS and differs from measures determined in accordance with IFRS. This measure is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. This measure is not necessarily indicative of net earnings or cash flow from operating activities as determined under IFRS.

 

Production

· 9M 2022 production of 765 mtV (9M 2021: 876 mtV). Decrease in production due to lower than anticipated recoveries associated with the Kiln 1 wind-down, electricity load shedding, and a slower than expected ramp-up post commissioning of Kiln 3, as previously mentioned.

· Q3 2022 production of 350 mtV (Q2 2022: 191 mtV). Higher production volumes, supported by improved performance of Kiln 3, with production of 61 mtV in July, 151 mtV in August and 138 mtV in September.

- Kiln 3 performance would have been even better if it had not been for electricity load shedding, with September experiencing the highest frequency and severity of load shedding.

Costs

· 9M 2022 production cash cost (C1) of US$39.1/kgV (9M 2021: US$28.7/kgV). Increase in cost due to lower production volumes, higher raw material costs and costs associated with the ramp-up of Kiln 3.

· Q3 2022 production cash cost (C1) of US33.8/kgV (Q2 2022: US$48.5/kgV). Cost reduction, supported by higher production volumes during the quarter.

· Costs are expected to normalise through the rest of the year, with 2022 production cash costs expected to be within guidance as we keep implementing our cost containment initiatives but remain dependant on inflationary pressures not increasing even further.

 

2022 Guidance

· Production guidance of 1,350 mtV - 1,450 mtV is maintained, supported by Kiln 3 ramping-up as planned, although, severe load shedding poses a risk to Vanchem's ability to meet guidance.

· Production cash cost guidance of US$34.9/kgV - US$35.5/kgV (ZAR534/kgV and ZAR542/kgV) maintained.

 

HEALTH AND SAFETY

· Q3 2022 Total Injury Frequency Rate ("TIFR") of 12.01 (Q3 2021: 8.74) due to increased number of lost time injuries ("LTIs") of 5 vs zero in Q3 2021.

- The Group will focus its efforts on increasing inspections, plant tasks observations and engagement with employees.

 

ESKOM ELECTRICITY LOAD SHEDDING

The South African energy crisis deepened during Q3 2022. As Eskom, South Africa's national utility, was forced to implement several load shedding measures during Q3 2022, the power utility imposed up to stage 6 which resulted in 6000 MW of demand being curtailed across South Africa. During this period, Vametco's operational performance was not affected by these periods of load curtailment and there is no impact on the plant's production performance.

Unlike Vametco, Vanchem purchases its power through its local electricity distributor, the Emalahleni municipality. The municipality imposes periods of total power loss (and not curtailment) during load shedding, resulting in almost total shutdown of the plant, thereby impacting Vanchem's operational performance. The plant has generators to power the kiln but not the rest of the plant. The use of generators comes at a significant cost implication due to the current cost of diesel. Vanchem has been actively engaging with the local municipality to implement a load curtailment solution. A bilateral technical team from Vanchem and the municipality is preparing for necessary technical hardware to migrate to the curtailment regime that would signal a marked production improvement for Vanchem. Further to this and in collaboration with the Bushveld Energy team, we are developing battery storage and renewable energy import options to supplement the power requirements of Vanchem.

 

VANADIUM PRICE AND OUTLOOK

· 9M 2022 ferrovanadium London Metal Bulletin ("LMB") price of US$41.1/kgV, CRU Ryan's Note of US$56.5/kgV and Asian Metals of US$34.8/kgV (9M 2021: US$38.2/kgV, US$37.7/kgV and US$36.5/kgV) with USA prices trading at a premium to the rest of the world.

· Q3 2022 LMB Ferrovanadium prices: US$33.8/kgV, (Q2 2022: US$43.8/kgV). CRU Ryan's notes US$50.9/kgV (Q2 2022: US$67.5/kgV) and Asian Metals US$30.4/kgV (Q2 2022: US$33.7/kgV).

· Sales volumes and markets have been flexed to maximise revenue by optimising sales of Nitro Vanadium into the higher priced North American steel market and increasing premium vanadium chemical sales into aerospace and petroleum / catalyst applications.

· Demand for Bushveld Mineral's suite of vanadium products remains strong, and the flexibility afforded by the diverse product mix and wide geographic presence is a significant strength when the current reduction in steel capacity utilisation is considered, allowing emphasis on higher value products and markets. The expectation remains that sales volume will equal production volume.

 

 

ENDS

 

Enquiries: info@bushveldminerals.com

Bushveld Minerals Limited

+27 (0) 11 268 6555

Fortune Mojapelo, Chief Executive Officer

Chika Edeh, Head of Investor Relations

SP Angel Corporate Finance LLP

Nominated Adviser & Broker

+44 (0) 20 3470 0470

Richard Morrison / Charlie Bouverat

 

Grant Baker / Richard Parlons

 

 

RBC Capital Markets

Joint Broker

+44 (0) 20 7653 4000

Jonathan Hardy / Caitlin Leopold

 

 

Tavistock

Financial PR

Gareth Tredway / Tara Vivian-Neal/ Adam Baynes

+44 (0) 207 920 3150

 

 

ABOUT BUSHVELD MINERALS LIMITED

Bushveld Minerals is a low-cost, vertically integrated primary vanadium producer. It is one of only three operating primary vanadium producers, owning 2 of the world's 4 operating primary vanadium processing facilities. In 2021, the Company produced 3,592 mtV, representing approximately 3% of the global vanadium market. With a diversified vanadium product portfolio serving the needs of the steel, energy and chemical sectors, the Company participates in the entire vanadium value chain through its two main pillars: Bushveld Vanadium, which mines and processes vanadium ore; and Bushveld Energy, an energy storage solutions provider. Bushveld Vanadium is targeting to materially grow its vanadium production and achieve an annualised steady state production run rate of between 5,000 mtVp.a. and 5,400 mtVp.a by the end of 2022. Growth plans to expand to 8,000 mtVp.a. will be pursued, subject to funding and market conditions.

 

Bushveld Energy is focused on developing and promoting the role of vanadium in the growing global energy storage market through the advancement of vanadium-based energy storage systems, specifically Vanadium Redox Flow Batteries ("VRFBs")

 

Detailed information on the Company and progress to date can be accessed on the website www.bushveldminerals.com

About Vametco

Vametco is located near Brits on the Western Limb of the Bushveld Complex. The integrated operation comprises a vanadium ore mine and a processing plant that produces mostly Nitro Vanadium. The mine lies adjacent to the Brits Vanadium Project, which will in future serve as an alternative source of near surface run of mine ("ROM") ore feed to the Vametco plant.

The Vametco mining operation uses open pit bench mining methods to mine a well-defined orebody. The deposit is continuous with limited faulting and dips in a northerly direction at approximately 19 degrees.

ROM ore is fed into a primary, secondary and tertiary crushing circuit, followed by milling and magnetic separation to produce magnetite concentrates. The magnetite concentrate is fed into the extraction process which consists of a rotary kiln for roasting followed by leaching and precipitation. Thereafter the precipitated vanadium as ammonium metavanadate is converted to modified vanadium oxide ("MVO") in a rotary calciner. MVO is fed into the mix plant and finally into the shaft furnaces to produce Nitro Vanadium.

About Vanchem

Vanchem is situated at Ferrobank Industrial Park in Emalahleni Local Municipality, Mpumalanga Province in the Republic of South Africa. Vanchem is a primary vanadium producing facility with a beneficiation plant capable of producing various vanadium oxides, ferrovanadium and vanadium chemicals. Vanchem uses the salt roast beneficiation process, similar to the one used at Vametco. The plant comprises: a core salt-roast processing plant, including 3 roasting kilns, an electric smelting ferrovanadium converter, an alumino-thermic smelting facility, also located at Highveld, a vanadium chemical plant; and a rail siding linking the plant with Bushveld deposits and additional potential supply sources through the national rail network.


[1] Weighted average production cash cost (C1): is the blended weighted average production cash cost (C1) of Vametco and Vanchem, divided by group production.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
QRTPPGBAUUPPPGC
Date   Source Headline
23rd Apr 20247:01 amRNSQ1 2024 Operational & Corporate Update
23rd Apr 20247:00 amRNSMineral Resources and Reserves Annual Update
14th Mar 20249:32 amRNSFurther Update on Outstanding Funds
14th Mar 20247:00 amRNSTR-1 Notification of Major Holdings
7th Mar 20243:00 pmRNSTR-1 Notification of Major Holdings
29th Feb 20245:30 pmRNSFurther Update on Outstanding Funds
16th Feb 20247:08 amRNSFurther update on Outstanding Funds
5th Feb 20247:08 amRNSFull year 2023 Operational Update
2nd Feb 20242:30 pmRNSForm 8.3 of the Takeover Code
1st Feb 20247:00 amRNSCompletion of Convertible Loan Note Refinancing
29th Jan 20244:25 pmRNSResignation of Finance Director
19th Jan 20244:32 pmRNSFurther Update on Outstanding Funds
15th Jan 20245:25 pmRNSTR-1 Notification of Major Holdings
15th Jan 20245:23 pmRNSTR-1 Notification of Major Holdings
15th Jan 202411:12 amRNSFurther update on Outstanding Funds
10th Jan 202412:55 pmRNSUpdate on Outstanding Funds
3rd Jan 20242:30 pmRNSUpdate following Equity Issue
27th Dec 20232:30 pmRNSResult of General Meeting
21st Dec 20237:00 amRNSReminder to vote at the General Meeting
19th Dec 202311:24 amRNSConfirmed Acquisition of Interests in Vametco
19th Dec 20237:32 amRNSConfirmed Acquisition of Interests in Vametco
15th Dec 20237:52 amRNSDefinitive sales and marketing agreement with SPR
15th Dec 20237:51 amRNSDefinitive agreement for 64% Mokopane Sale
14th Dec 202311:07 amRNSOption Agreement with Portillion
13th Dec 20237:00 amRNSCorporate Update
12th Dec 20237:00 amRNSResults of PrimaryBid Offer
6th Dec 202312:00 pmRNSInvestor Presentation
5th Dec 20231:00 pmRNSPrimaryBid Offer
5th Dec 202312:51 pmRNSResult of Bookbuild
29th Nov 20233:35 pmRNSProposed Fundraising
27th Nov 20237:00 amRNSAgreement on Convertible Loan Note Refinancing
20th Nov 202310:20 amRNSBushveld Energy Update
20th Nov 20237:15 amRNSAgreement for acquisition of interest in Vanchem
16th Nov 20235:32 pmRNSResignation of Finance Director
6th Nov 20237:00 amRNSQ3 2023 and 9M 2023 Operational Update
30th Oct 20237:00 amRNSConditional acquisition of interests in Vametco
18th Oct 20237:00 amRNSHolding(s) in Company
10th Oct 20237:00 amRNSResponse to Market Speculation
26th Sep 20237:00 amRNSInterim Results for Six Months ended 30 June 2023
20th Sep 20234:45 pmRNSHolding(s) in Company
11th Sep 20237:00 amRNSInvestment by Southern Point Resources
1st Sep 20233:58 pmRNSTR-1: Standard Notification of Major Holdings
21st Aug 20236:00 pmRNSTR-1: Standard Notification of Major Holdings
9th Aug 20231:00 pmRNSMustang Energy Update: Conversion Notice
3rd Aug 20234:39 pmRNSHolding(s) in Company
2nd Aug 20232:29 pmRNSResult of AGM
2nd Aug 20237:00 amRNSQ2 and H1 2023 Operational Update
28th Jul 20237:00 amRNSEnerox Update
14th Jul 20233:58 pmRNSConvertible Loan Note Update
6th Jul 20239:00 amRNSREPLACEMENT: Posting of Accounts and Notice of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.