Less Ads, More Data, More Tools Register for FREE

Pin to quick picksBHR.L Regulatory News (BHR)

  • There is currently no data for BHR

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Minas Moatize Expansion Project Update

4 Jul 2012 07:00

RNS Number : 8724G
Beacon Hill Resources plc
04 July 2012
 



 4 July 2012

 

Beacon Hill Resources Plc / ASX: BHU / AIM: BHR/ Sector: Mining

 

Beacon Hill Resources Plc ('Beacon Hill' or 'the Company')

Minas Moatize Expansion Project Update

 

HIGHLIGHTS

 

·; Optimisation work continues on the Minas Moatize Expansion Project aimed at a phased expansion of the existing operation to in excess of 2Mtpa of saleable coal.

·; Optimisation builds on the Definitive Feasibility Study ('DFS') published in February 2012, which projected a pre-tax NPV of US$662 million for the Project

·; The Expansion Project, is being undertaken in two further phases:

o Phase I - 0.6Mtpa ROM - currently operating

o Phase II - 1.2Mtpa ROM - expansion of existing 'Phase I CHPP' in 2013

o Phase III - 4.0Mtpa ROM - commissioning of new 'Phase III CHPP' in mid 2014

 

·; Discussions regarding financing of Phase III of the Expansion Project are progressing well focusing on raising debt finance, including options of key infrastructure financing on a Build, Own and Operate ('BOO') basis.

·; A drilling programme recommended in the DFS has now been completed - this will provide further test data for:

o Washability, liberation and flotation testing to optimise the design of the life of mine wash plant ('Phase III CHPP');

o Upgrading the Minas Moatize JORC Coal Resource and Reserve;

o Geotechnical investigations to optimise the pit design and the foundation design for the Phase III CHPP.

 

Justin Lewis Chairman of Beacon Hill commented, "Beacon Hill is focused on the expansion of the Minas Moatize Mine, as set out in the DFS published earlier this year. Having completed a further drilling programme, we have now commenced further test work, to facilitate and progress the optimisation of the design of the Phase III wash plant and the overall pit design. A successful outcome of the tests will result in a further improvement of the overall economics of the project through higher coking coal yields.

 

The next step for the Minas Moatize mine is the expansion of the current wash plant doubling its processing capacity to 1.2Mtpa ROM coal.

 

Minas Moatize Expansion PROJECT

The expansion of the Minas Moatize Coal Mine ('Minas Moatize Expansion' or the 'Project') is based upon increasing production to 4Mtpa ROM, producing on average 2.2Mtpa of saleable coking and thermal coal during its mine life. In February 2012, Beacon Hill published the DFS for the Minas Moatize Expansion, completed by consultants TWP Australia Pty Ltd, which demonstrated strong economics for the project. Financial modelling, using a 13% discount rate, demonstrates a pre-tax NPV13 of US$662 million and a post-tax NPV13 of US$428 million.

 

The Minas Moatize Expansion is being undertaken in two further phases over the next 30 months as detailed below:

 

Phase

Timing

Description

Transport

ROM (Mtpa)

Estimated Capex

Phase I

Current

Current operations

(Phase I CHPP)

 

Road

0.6

$N/A

Phase II

H1 2013

Expansion of Current Washplant

(Phase II CHPP)

 

Road or Rail*

1.2

$5m

Phase III

H2 2014

New Life of Mine Washplant (Phase III CHPP)

Rail / Road

4.0

$150m (owner operator)

$18m (BOO and contract mining)

*Rail will be used when available. Existing trucking operation will be sufficient to transport Phase II production

 

The commencement of Phase III is subject to certain key milestones, including:

 

·; Rail allocation - the Group is involved in ongoing discussions with the operator of the Sena railway, CFM, and anticipates being able to enter into a formal agreement for an allocation before the end of the year when the current upgrade works (to achieve an estimated 6.5 Mtpa capacity) are completed;

 

·; Finalisation of the design of the Phase III CHPP - this is an ongoing process following the finalisation of the initial design as part of the DFS. The current testwork referred to below, together with operational experience gained from the existing washplant will be incorporated into this process. The Group anticipates being in a position towards the end of the current year to finalise contracts for the construction of the plant.

 

·; Financing - the Group is in ongoing discussions with a numbers of banks and project financiers to fund the capital requirement associated with Phase III. Two principle avenues currently being pursued, are via a debt facility and a Build, Own and Operate contract. It is not the Board's current intention to use the equity markets to fund Phase III of the Expansion.

 

DRILLING PROGRAMME

The DFS identified a number of areas where additional investigation could lead to further optimisation of the Project and further test work, when combined with experience of the coal handling behaviour within the existing wash plant, would lead to optimisation of the design and construction of the Phase III CHPP.

 

The Group has recently completed a drilling programme, which comprised 19 holes (10 HQ Resource Holes, 3 Large Diameter ('LD') Holes and 6 Geotechnical Holes). The core samples from this drilling programme have been forwarded to laboratories in South Africa and the United States for further testing and evaluation.

 

Washability, liberation and flotation testing for the Phase III CHPP design is underway based on the drill programme undertaken (a total of 448m of large LD drilling). The drill programme has also provided further test data for:

- Resource Definition - total of 759m of HQ drilling was undertaken for the purposes of improving resource definition and confidence;

- Geotechnical Investigation - total of 305m of HQ drilling was undertaken for geotechnical purposes in order to optimise the pit design, waste rock dump design and for the foundation design of the CHPP.

 

Washability and Liberation Testing Optimisation

Since Mozambican sourced coal is a relatively new product, optimum bulk processing methods are still being refined. Minas Moatize has the key advantage that it is currently operating a small scale wash plant (Phase I CHPP) which enables it to test various processing methods. Two drivers to improve processing results are:

- Liberation of high quality (coking) coal from ROM coal; and

- Treatment of the coal fines.

 

Higher quality (coking) coal is liberated by the crushing of the ROM coal at the beginning of the process, but since smaller size coal (fines) is harder to process, it is preferable to keep crushing to a minimum. The aim is to determine the optimum balance between minimising the crushing of the coal whilst maximising the liberation of the higher quality coal.

 

Mozambican coal is characterised by being a brittle coal, which when combined with the crushing process creates high volumes of 'fines'. A significant proportion of high grade coking coal is contained within these coal fines and the DFS confirmed that an improved understanding and treatment of the fines content in the coal has potential to increase the coking coal yield. Experience with the existing Phase I CHPP has also highlighted this as an opportunity for yield improvement.

 

The optimisation of the final design of the Phase III CHPP is focused upon identifying the optimum liberation size and design of the fines circuit. The liberation, flotation and filtration tests on the LD cores will investigate these properties, with the aim of upgrading the overall quality of the coking coal and coking coal yield that will been achieved from the Phase III CHPP. A successful outcome of the tests will result in a further improvement of the overall economics of the project through higher coking coal yields.

 

Resource Definition 

As part of the DFS the Company reported a maiden JORC compliant Coal Reserve for Minas Moatize, which totalled a Mineable Reserve of 42.66Mt with the potential upside of a further 7.9Mt. The potential upside in the Reserve related to areas in the coal seams that had insufficient data to meet the JORC Measured (drill holes < 350m apart) or Indicated (drill holes > 350m but

 

Analysis of the drilling programme will enable reclassification of areas of the Upper Chipanga, Middle Chipanga and Bananeiras coal seams to upgrade the overall JORC Coal Resource and Reserve of Minas Moatize, which will be announced in due course.

 

Geotechnical Investigation

Six geotechnical investigation holes have been drilled to determine ground conditions, which will be used to enable detailed foundation design at key load points of the Phase III CHPP.

 

The results from the geotechnical holes will also assist in optimising the pit design. The preliminary pit design reported in the DFS, whilst supported by geotechnical pit design criteria, did not have the benefit of test information from core logs The results from the geotechnical holes will support the optimisation of detailed pit design work and the additional data will assist in deriving pit wall slope design, stand up times and bench and batter configurations.

 

 

**ENDS**

For further information, please contact:

Beacon Hill Resources Plc

Justin Lewis, Chairman

Peter Wilson, Chief Operating Officer

+61 3 9627 9910

info@bhrplc.com

Canaccord Genuity Limited (Nominated Advisor & Broker)

John Prior / Sebastian Jones

+44 20 7523 8350

Halcyon Corporate (Australian Corporate Advisor)

Ryan Whitelegg / Jonathan Tooth

+61 3 9627 9941

St Brides Media & Finance (UK Media Enquiries)

Susie Geliher (susie@sbmf.co.uk) / Elisabeth Cowell (elisabeth@sbmf.co.uk)

+44 20 7236 1177

 

 

Glossary

BOO

Build, Own & Operate

CFM

Mozambique Ports & Railways

CHPP / Washplant

Coal Handling and Preparation Plant ('CHHP') or Washplant is used to wash / process coal into a higher value product that is saleable into global export markets

Coking Coal

Also known as Metallurgical Coal is a high quality coal used in the steel production industry

DFS

Definitive Feasibility Study

Fines

Coal that is less than 2mm

Flotation

A method to separate coal in the coal processing process

FOB

Free on Board: The seller is responsible for transporting the coal to the port and loading the coal onto the vessel

JORC

Joint Ore Reserves Committee: The JORC Code is the Australasian Code for Reporting of Identified Mineral Resources and Ore Reserves

Liberation

The amount of physical breakage or crushing required to separate materials of different material densities (i.e. to separate the clean coal from the rock)

Phase I CHPP

Current wash plant that has a capacity to process 0.6Mtpa of ROM Coal

Phase II CHPP

Upgraded and optimised Phase 1 CHPP that will have the capacity to process approximately 1.2Mpta of ROM coal

Phase III CHPP

New life of mine wash plant that will have capacity to produce up to 3 products simultaneously and process approximately 4Mtpa ROM Coal

ROM

Run of mine coal as received from the mine

Thermal Coal

Steaming coal intended for use in the steam and power generation industry

 

 

Notes

 

Beacon Hill Resources

Beacon Hill Resources Plc is focused on building a portfolio of near-term production projects in commodities relating to the steel production industry. Beacon Hill is dual listed on London's AIM Market (Code: BHR) and the Australian Securities Exchange (Code: BHU).

 

Beacon Hill has 3 projects:

1. Minas Moatize Project, Mozambique

2. Changara Coal Project, Mozambique

3. Arthur River Magnesite Project, Australia

 

Minas Moatize Project

Beacon Hill, through its subsidiary Minas Moatize Limitada, owns and operates the Minas Moatize Coal Mine, which is one of three operating coal mines producing and selling coal in the Tete Province of Mozambique.

 

In February 2012, Beacon Hill published the DFS for the Minas Moatize Expansion, which demonstrated strong economics for the project. Financial modelling, based on a 4Mtpa ROM operation producing on average 2.2Mtpa of saleable coking and thermal coal using a 13% discount rate, demonstrates a pre-tax NPV13 of US$662 million and a post-tax NPV13 of US$428 million.

 

The Minas Moatize Expansion is being undertaken in three phases:

 

Phase

Timing

Description

Transport

ROM (Mtpa)

Phase I

Current

Current operations(Phase I CHPP)

Road

0.6

Phase II

H1 2013

Expansion of Current Washplant(Phase II CHPP)

Road or Rail*

1.2

Phase III

H2 2014

New Life of Mine Washplant (Phase III CHPP)

Rail / Road

4

*Rail will be used when available. Existing trucking operation will be sufficient to transport Phase II production

 

Changara Coal Project

Beacon Hill acquired majority ownership in a joint venture to explore and develop the Changara Coal Project in the Tete Province of Mozambique in December 2011. The Changara Coal Project covers a licence area of 184km2, which is 70 times the size of Minas Moatize. The project is located in the heart of the highly prospective coking coal basin of the Songo Area of the Tete Province. 

The joint venture is a further step in Beacon Hill's wider expansion strategy in the globally significant coking coal region of Tete and will provide the Group with an opportunity to invest in a longer term development project that has the potential to considerably enhance its resource base. 

Arthur River Magnesite Project

Beacon Hill has recently completed the Preliminary Scoping Study for the Arthur River Magnesite Project in Tasmania, Australia. The Study has indicated that the Project has robust financial potential and provides a strong platform to move forward towards a full Feasibility Study and securing a joint venture ('JV') and / or off-take partner to fund the development of the Project.

 

Financial modelling, using a discount rate of 10% (real), demonstrates a pre-tax NPV of A$42 million based on a mine life of 17 years and a 292,000dtpa ROM operation producing on average 100,000tpa of calcined magnesia.

 

More details on Beacon Hill can be found at www.bhrplc.com.

 

Competent Persons Statement

The Competent Person for reporting of coal resources, Peet Meyer of PC Meyer Consulting Pty Limited, who is a member of the Geological Society of South Africa (GSSA) and the Fossil Fuel Foundation. Peet Meyer has more than 21 years' experience in the southern African coal industry of which he has spent more than 5 years in the Mozambique Coalfields. He has the appropriate relevant qualifications and experience to be considered as a Competent Person as defined in the Standards on Mineral Resources and Reserves - Definitions and Guidelines (2004).

 

The Competent Person for reporting of coal reserves, Mr. Simon Griffiths, who is a Member of The Australian Institute of Mining and Metallurgy (AusIMM) and Society for Mining, Metallurgy, and Exploration, Inc. (SME) has sufficient experience which is relevant to the style and mineralisation and type of deposit under consideration and the activity to which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'.

 

The Coal Resources and Reserves are reported in compliance with the guidance as defined in Appendix 5A of the ASX Listing Rules being the Australasian Code for Reporting Exploration Results, Mineral Resources and Ore Reserves (the JORC Code), 2004 Edition.

 

Mr Meyer and Mr Griffiths have consented to being named as the authors of the Resource and Reserve Statements respectively in this announcement.

 

Forward Looking Statement

Certain statements made during or in connection with the communication, including, without limitation, those concerning the economic outlook for the coal mining industry, expectations regarding coal prices, production, cash costs and other operating results, growth prospects and the outlook of Beacon Hill operations, its liquidity and the capital resources and expenditure, contain or comprise certain forward-looking statements regarding Company's development and exploration operations, economic performance and financial condition.

 

Although the Company believes that the expectations reflected in such forward-looking statements are reasonable, no assurance can be given that such expectations will prove to have been correct. Accordingly, results could differ materially from those set out in the forward-looking statements as a result of, among other factors, changes in economic and market conditions, success of business and operating initiatives, changes is the regulatory environment and other government actions, fluctuations in coal prices and exchange rates and business and operational risk management. For a discussion of such factors, refer to the Company's most recent annual report and half year report. The Company undertakes no obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUGURGMUPPUAC
Date   Source Headline
12th Jan 20154:15 pmRNSAppointment of Administrators
17th Dec 20143:10 pmRNSResult of GM and Suspension of Trading
17th Dec 201410:00 amRNSSuspension - Beacon Hill Resources Plc
17th Dec 201410:00 amRNSSuspension of Trading on AIM
16th Dec 20141:30 pmRNSHolding(s) in Company
15th Dec 20145:00 pmRNSHoldings in Company
11th Dec 20147:00 amRNSSubscription to Raise GBP56,055
10th Dec 20147:00 amRNSShareholder Conference Call Recording
4th Dec 201411:40 amRNSIssue and Allotment of Ordinary Shares
2nd Dec 201411:25 amRNSHoldings in Company
1st Dec 20144:40 pmRNSSecond Price Monitoring Extn
1st Dec 20144:35 pmRNSPrice Monitoring Extension
1st Dec 20147:50 amRNSFinancing and Restructuring Update
1st Dec 20147:45 amRNSChange of Nominated Adviser and Broker
28th Nov 201410:45 amRNSHolding(s) in Company
24th Nov 20144:40 pmRNSSecond Price Monitoring Extn
24th Nov 20144:35 pmRNSPrice Monitoring Extension
24th Nov 20141:40 pmRNSIssue and Allotment of Ordinary Shares
21st Nov 201411:45 amRNSResponse to Share Price Increase
20th Nov 20143:00 pmRNSHolding(s) in Company
18th Nov 20149:15 amRNSHolding(s) in Company
14th Nov 20144:40 pmRNSHolding(s) in Company
4th Nov 201412:00 pmRNSNew Debt Facility and Restructuring Update
3rd Nov 20144:56 pmRNSHolding(s) in Company
3rd Nov 20144:56 pmRNSHolding(s) in Company
3rd Nov 20144:54 pmRNSHolding(s) in Company
3rd Nov 20144:52 pmRNSHolding(s) in Company
27th Oct 20147:00 amRNSHoldings in Company
23rd Oct 201410:00 amRNSUpdate on Vitol Senior Debt Facility
21st Oct 20147:00 amRNSHolding(s) in Company
20th Oct 201410:05 amRNSHolding(s) in Company
20th Oct 201410:04 amRNSHolding(s) in Company
17th Oct 201410:00 amRNSHolding(s) in Company
14th Oct 20147:00 amRNSHolding(s) in Company
13th Oct 201411:00 amRNSHolding(s) in Company
9th Oct 201411:20 amRNSAgreement to Sub-Lease Rolling Stock
8th Oct 20149:30 amRNSHolding(s) in Company
1st Oct 20143:00 pmRNSResult of General Meeting
1st Oct 20141:00 pmRNSHolding(s) in Company
26th Sep 20146:18 pmRNSHolding(s) in Company
26th Sep 20146:18 pmRNSHolding(s) in Company
23rd Sep 20149:32 amRNSInterim Results
15th Sep 20144:00 pmRNSResults of General Meeting
15th Sep 20147:00 amRNSConditional Placement of Ordinary Shares
4th Sep 20147:00 amRNSHoldings in Company
28th Aug 20147:00 amRNSNotice of General Meeting and Posting of Circular
19th Aug 20147:00 amRNSFunding Update
8th Aug 20143:03 pmRNSHolding(s) in Company
31st Jul 201411:00 amRNSHoldings in Company
21st Jul 20143:30 pmRNSResults of GM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.