AGM Statement

29 Jun 2011 07:00

RNS Number : 3001J
Beacon Hill Resources plc
29 June 2011
 



Beacon Hill Resources Plc / Ticker: BHR / Index: AIM / Sector: Mining

29 June 2011

Beacon Hill Resources plc ('Beacon Hill' or 'the Group')

AGM Statement

 

Beacon Hill Resources PLC (AIM: BHR), the AIM listed coal producer, is pleased to provide an update on its projects, which will be read at today's Annual General Meeting.

 

Highlights

 

·; First production of export grade coal to commence at Minas Moatize coal mine in Tete, Mozambique

 

·; Mining from initial open pit and commissioning of the temporary wash plant underway

 

·; Initial trial trucking of coal to the port of Beira by road to start in July ahead of first export shipment

 

Justin Lewis, Chairman of Beacon Hill Resources, commented "We are delighted to announce the commencement of operations at Minas Moatize with production of its first washed export grade coal. This is another significant milestone for the development of the Minas Moatize coal mine, which, has been achieved in less than a year since we acquired the mine.

 

"A further key development is the forthcoming commencement of trial trucking of coal to Beira which we will ramp up over the coming months. This will enable us to start stockpiling coal at the port pending a first export shipment."

 

AGM Statement

 

"I am very pleased today to announce the following trading update to shareholders, in particular in relation to the Minas Moatize coking coal project in the Tete province of north western Mozambique.

 

Minas Moatize

 

Since we acquired Minas Moatize in May 2010, the Group has pursued a twin track strategy, firstly, to continue production from the existing underground mining operation producing coal for the local markets as well as small volumes for export markets. Secondly, the Group is rapidly developing a larger open pit mine that will have the ability to produce 2.35Mtpa of saleable coal, which will include 0.9Mtpa of coking coal.

 

Current Production

 

As announced at the time of the results, we have been progressively winding down production from the underground mining operations at Minas Moatize in preparation of the large open pit mine, which is planned to commence mining in Q1 2012. I am pleased to be able to announce that today the Group has commenced mining from the initial open pit, together with the commissioning of the mine's temporary coal handling and preparation plant ('the Washplant'). This is an historic step for the Minas Moatize mine, enabling it to produce Mozambique's first export grade washed coal.

 

The total estimated resource of the initial open pit area is approximately 180,000 tonnes which will be progressively mined over the next 12 months. The pit has already been pre-stripped and mining is being undertaken with excavators and trucks using a local mining contractor and will have the ability to produce approximately 15,000 tonnes of coal per month.

 

The Washplant has been purpose built for Minas Moatize in South Africa and has capacity of 120 tonnes per hour. The Washplant is a modular unit that includes a double roller crusher, dense medium separation plant and a fines treatment plant. The plant is able to treat run of mine ('ROM') coal with a feed size of

 

Minas Moatize currently has 39,000 tonnes of unwashed coking and thermal coal stockpiled at the mine and now has the ability to mine further thermal coal over the next 12 months. Therefore, in advance of production from the main open pit mine, the Group is now able to produce a washed coking coal (from our underground operation), a washed export thermal coal, and a domestic thermal coal. This will put the Group in an advantageous position of being able to use the current production to both test its logistics network as well as secure long term customers.

 

Development of Expanded Open Pit Mine

 

The development of the expanded open pit mine has been the Group's main focus over the last 12 months. The Group is making good progress in regard to developing the main open pit and should be ready to commence pre-stripping from it in Q1 2012, building up to a ROM of 4Mtpa producing 2.35Mtpa of saleable coal.

 

As we announced in early March, TWP Australia Pty Ltd ('TWP') has been appointed to finalise the Definitive Feasibility Study including the design of both the mining operation and also the permanent Coal Handling and Preparation Plant. TWP's work continues to progress well and on schedule. In addition, we continue to undertake further work in respect of coal qualities and will shortly commence pilot coking oven tests in Australia on large diameter cores drilled earlier in the year.

 

Transport Infrastructure

 

Logistical infrastructure and the ability to get product to market is a key challenge in Mozambique. Beacon Hill believes that is has a significant advantage in that it is currently the sole producer, giving it a competitive advantage in relation to the logistics.

 

The Group's long term logistics solution will be to utilise the Sena railway line, which runs from Moatize to the port of Beira, and will be operated on a multi-user basis. At its peak, the Minas Moatize mine is proposed to be produce approximately 1.8Mtpa of coal for export on the seaborne market. As has been widely reported, the refurbishment of the Sena railway line has been further delayed until at least September of this year. As a result the Group has been unable to complete a first export shipment of coal by rail to date, however, the operators of the Sena railway line remain confident of being able to transport initial volumes of Minas Moatize coal in the second half of this year.

 

In order to ensure that Minas Moatize is not wholly dependent on a railway line going forward we have been developing an alternative transport option using trucks. Minas Moatize has several proposals from regional trucking companies with a view to transporting up to 0.5Mtpa by truck and road to the port of Beira. This is a transport solution where we are not dependent on the provision of third party infrastructure. I am therefore pleased to announce that the Group will commence trial trucking of coal from the Minas Moatize mine to the port of Beira at the beginning of July, enabling the Group to begin stockpiling coal at its facility at Beira in advance of making a first export shipment.

 

Licence 1165L

 

On 4 April 2011 the Group announced that it had entered into a Memorandum of Understanding to potentially acquire a 100% interest in coal licence area 1165L in the Moatize Coal Basin in Northern Mozambique. The exclusivity agreement with Global Minerals & Metals Pte Limited relating to the acquisition of Licence 1165L has since been extended to 2 August 2011.

 

The Group continues to work with the vendors of Licence 1165L to finalise the legal documentation and due diligence to complete this acquisition, and an announcement will be made in due course to update shareholders of developments in this regard.

 

Tasmania Magnesite

 

As recently announced the Group has recently completed Phase 1 of a drilling programme at the Arthur River Project in Tasmania. The results, which will provide the Group with a clearer understanding of the deposit in terms of size, metallurgy and hydrology will be inputted into the Scoping Study. The Scoping Study, which focuses on confirming the economics of the project in addition to developing an initial conceptual mine plan, is currently being finalised and the Group anticipates that it will be completed before the end of 2011. The Scoping Study will also provide the basis for moving forward to a full Feasibility Study including the submission of a development proposal and environmental management plan to secure mining approval, the completion of the approved drilling programme and the securing of a joint venture and or off-take partners for the project."

 

 

**ENDS**

 

For further information on the Company, visit www.bhrplc.com or contact:

 

Justin Lewis

Chairman, Beacon Hill Resources Plc

+61 (0) 3 9627 9905

+61 439 162369

John Prior

Collins Stewart Europe Limited

+44 (0) 20 7523 8350

Adam Miller

Collins Stewart Europe Limited

+44 (0) 20 7523 8350

Jeremy Wrathall

Renaissance Capital Ltd

+44 (0) 20 7367 8273

Susie Geliher

St Brides Media & Finance Ltd

+44 (0) 20 7236 1177

 

Notes

Beacon Hill Resources Plc (AIM: BHR) is an AIM listed resource company focussed on the acquisition and development of assets in commodities relating to the steel production industry. The Group currently has two primary assets - the Minas Moatize Coal Mine in Tete, Mozambique and Tasmania Magnesite NL in Tasmania.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
AGMSEMFIAFFSELM
Date   Source Headline
18th Jun 20137:10 amRNSCorporate Presentation
28th May 20134:30 pmRNSDirectorate Change
24th May 20135:30 pmRNSResult of AGM
24th May 20137:00 amRNSAGM Statement
1st May 201310:00 amRNSNotice of AGM and Posting of Reports & Accounts
30th Apr 20137:00 amRNSQuarterly Report
4th Apr 20135:30 pmRNSHolding(s) in Company
4th Apr 201311:01 amRNSHolding(s) in Company
3rd Apr 20131:15 pmRNSRESULTS OF GENERAL MEETING
3rd Apr 201310:00 amRNSOperations Update
27th Mar 20137:00 amRNSAudited Financial Results
22nd Mar 20137:00 amRNSChange in Shareholder Ownership:Major New Investor
19th Mar 20135:17 pmRNSHolding(s) in Company
18th Mar 20133:39 pmRNSNotice of General Meeting and Posting of Circular
18th Mar 20137:00 amRNSManagement Appointment
12th Mar 20134:40 pmRNSResults of Placing
11th Mar 201311:30 amRNSProposed Cash Placing to raise up to US$25 million
28th Feb 20134:35 pmRNSPrice Monitoring Extension
28th Feb 20139:14 amRNSHolding(s) in Company
28th Feb 20137:00 amRNSUnaudited Preliminary Results
27th Feb 201311:33 amRNSHolding(s) in Company
20th Feb 201310:52 amRNSHolding(s) in Company
18th Feb 201310:40 amRNSPresentation on Strategic Update
11th Feb 20137:00 amRNSReceipt of 0.5Mt Sena Rail Line Allocation
8th Feb 20134:35 pmRNSIssue of Equity to Former Chairman
7th Feb 20139:16 amRNSHolding(s) in Company
4th Feb 20138:02 amRNSHolding(s) in Company
1st Feb 20137:00 amRNSRolling Stock Operating Lease Signed, Sena Line
29th Jan 20137:00 amRNSQuarterly Activities Report
28th Jan 20137:00 amRNSResource Upgrade for Minas Moatize Coking Coal
9th Jan 201312:15 pmRNSResults of General Meeting
21st Dec 20124:40 pmRNSSecond Price Monitoring Extn
21st Dec 20124:35 pmRNSPrice Monitoring Extension
19th Dec 20124:40 pmRNSSecond Price Monitoring Extn
19th Dec 20124:35 pmRNSPrice Monitoring Extension
19th Dec 201211:29 amRNSNotice of General Meeting
4th Dec 20122:30 pmRNSPresentation on Strategic Update
3rd Dec 20127:06 amRNSStrategic Update
14th Nov 20128:48 amRNSHolding(s) in Company
9th Nov 201210:30 amRNSGrant of Options to Managing Director
7th Nov 20127:00 amRNSIssue of Convertible Loan Notes
2nd Nov 20129:20 amRNSAppointment of Managing Director
18th Oct 20128:18 amRNSQuarterly Report for the Period Ended 30 September
11th Oct 20127:00 amRNSAppointment of Managing Director and Board Changes
5th Oct 20128:04 amRNSLogistics Update
30th Aug 20124:35 pmRNSPrice Monitoring Extension
28th Aug 20124:35 pmRNSPrice Monitoring Extension
28th Aug 20127:00 amRNSHalf Year Report for the period ended 30 June 2012
31st Jul 20127:01 amRNSQuarterly Activities Report
31st Jul 20127:00 amRNSCommencement of Phase II Expansion

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.