Updated Resource Statement

4 Dec 2014 07:00

RNS Number : 7963Y
Beowulf Mining PLC
04 December 2014
 



4 December 2014

 

Beowulf Mining Plc

("Beowulf" or the "Company")

Kallak indicated resource increased by 34% to 118.5Mt, with inferred resource of over 33.8Mt and exploration target of 90-100Mt

 

Beowulf (AIM: BEM; Aktietorget: BEO), the mineral exploration and development company focused on the Kallak iron ore project in northern Sweden and its Swedish exploration portfolio is pleased to report an updated resource statement for Kallak North, maiden resource statement for Kallak South and an additional exploration target for Kallak.

 

Highlights are as follows:

 

· Total indicated resource has increased by 34% to 118.5Mt at 27.5% Fe from 88.3Mt at 27.7% Fe in the 2013 resource statement.

· Total inferred resource of 33.8Mt at 26.2% Fe, and an exploration target of 90-100Mt at 22-30% Fe representing potential ore below the pit shells modelled for this resource statement, and in the gap between drilling defined Kallak South mineralized zones.

· Kallak North indicated resource has increased by 20% to 105.9Mt at 27.9% Fe from 88.3Mt at 27.7% Fe in the 2013 resource statement.

· Kallak North has an inferred resource of 17Mt at 28.1% Fe and the orebody remains open at depth and to the north.

· Maiden indicated resource for Kallak South of 12.5Mt at 24.3% Fe and inferred resource of 16.8Mt at 24.3% Fe.

· High grade intersections for Kallak South, announced on 6 October, sit below the base of the pit shell used for the maiden resource and could be accessible using an underground mining method.

· Resource estimate based on a significantly lower price of $90/t 62% Fe as compared to $150/t 62% Fe in the 2013 resource statement.

· The potential for eventual open pit extraction has been tested with open pit optimization, using Whittle software.

· Testwork conducted earlier in 2014 on samples from Kallak yielded a high grade concentrate of over 69% Fe, with a recovery of 95% for magnetite, and showing very low levels of phosphorous and sulphur.

· Kallak, as defined by drilling, is approximately 3,700m in length and 350m in width.

 

Category

Tonnage

[Mt]

Fe

[%]

P

[%]

S

[%]

Kallak North

Indicated

105.9

27.9

0.035

0.001

Inferred

17.0

28.1

0.037

0.001

Kallak South

Indicated

12.5

24.3

0.041

0.003

Inferred

16.8

24.3

0.044

0.005

Global

Indicated

118.5

27.5

0.036

0.001

Inferred

33.8

26.2

0.040

0.003

 

Notes:

1. The effective date of the Mineral Resource Estimate is 28 November 2014.

2. Resources have been classified as Indicated or Inferred, following the guidelines of the JORC Code, 2012 edition.

3. Cut-off grade of 15% Fe has been used.

4. Mineral Resources which are not Mineral Reserves have no demonstrated economic viability.

 

Kurt Budge, Chief Executive Officer of Beowulf, commented:

"The 2014 drilling campaign has delivered a substantial 34% increase in indicated resources for Kallak. This was achieved despite using a considerably lower iron ore price of $90/t 62% Fe as compared to $150/t 62% Fe in the 2013 resource statement. A more optimistic price outlook would clearly benefit the project, but Kallak's scale and quality, as evidenced by the Company's exploration and metallurgical testwork results, cannot be ignored.

"In addition, we have the added bonus of delivering both a maiden resource for Kallak South and a sizable 90-100Mt exploration target. There are more tonnes to be had at Kallak, but the focus is now on finding the right partner to work with us on developing the project. We have already completed a substantial body of work across many key disciplines, which positions the Company well for targeting potentially interested parties."

.

 

Enquiries:

Beowulf Mining Plc

Kurt Budge, Chief Executive Officer

Tel: +44 (0)7984 402 794

Cantor Fitzgerald Europe

Stewart Dickson / Jeremy Stephenson / Carrie Lun

Tel: +44 (0)20 7894 7000

Blytheweigh

Tim Blythe / Halimah Hussain / Eleanor Parry

Tel: +44 (0)20 7138 3204

http.//www.beowulfmining.net

 

Competent Person Review

The mineral resources for the Kallak North and Kallak South iron ore deposit have been prepared and categorised for reporting purposes by Mr. Thomas Lindholm, of GeoVista AB, Fellow of the MAusIMM, following the guidelines of the JORC Code, 2012 edition. Mr. Lindholm is qualified to be a Competent Person as defined by the JORC Code on the basis of training and experience in the exploration, mining and estimation of mineral resources of ferrous deposits and by his membership in a recognized professional association. Mr. Lindholm consents to the inclusion in this announcement of resource statement information in the form and context in which it appears.

 

Consulting Team

Geological interpretation and solid modelling have been carried out by Mr. Mathias Forss MSc Geology and Mineralogy of AB Scandinavian Geopool Ltd., Finland, in cooperation with Dr. Robin Bernau Ph.D., FGS, MAusIMM (CP) of Micon International Ltd, U.K. Mr. Forss has fulfilled the role of Kallak project geologist since 2013. Mine planning has been carried out by Mr. Peter Shankaya B.Min.Sc., Engineering Institute of Zambia of Micon International Ltd, U.K.

 

Cautionary Statement

Statements and assumptions made in this document with respect to the Company's current plans, estimates, strategies and beliefs, and other statements that are not historical facts, are forward-looking statements about the future performance of Beowulf. Forward-looking statements include, but are not limited to, those using words such as "may", "might", "seeks", "expects", "anticipates", "estimates", "believes", "projects", "plans", strategy", "forecast" and similar expressions. These statements reflect management's expectations and assumptions in light of currently available information. They are subject to a number of risks and uncertainties, including, but not limited to, (i) changes in the economic, regulatory and political environments in the countries where Beowulf operates; (ii) changes relating to the geological information available in respect of the various projects undertaken; (iii) Beowulf's continued ability to secure enough financing to carry on its operations as a going concern; (iv) the success of its potential joint ventures and alliances, if any; (v) metal prices, particularly as regards iron ore. In the light of the many risks and uncertainties surrounding any mineral project at an early stage of its development, the actual results could differ materially from those presented and forecast in this document. Beowulf assumes no unconditional obligation to immediately update any such statements and/or forecasts.

 

About Kallak

The Kallak North iron ore deposit is located about 40km west of the Jokkmokk municipality centre in the Norrbotten County in Northern Sweden.

Local infrastructure is excellent with all-weather gravel roads passing through the project area and all parts easily reached by well used forestry tracks. A major hydroelectric power station with associated electric power-lines is located only a few kilometres to the south east. The nearest railway (the 'Inland Railway Line') passes approximately 40km to the east. This railway line is connected at Gällivare with the 'Ore Railway Line', which is used by LKAB for delivery of their iron ore material to the Atlantic harbour at Narvik (Norway) or to the Botnian Sea harbour at Luleå (Sweden).

The total Kallak project area is approximately 243km2. The mineral resource estimate for Kallak North and South is based on drilling conducted between 2010-2014, a total 27,895m drilled, including 131 drillholes.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLLFFFVFLLVIIS
Date   Source Headline
31st Jan 20239:00 amRNSPrice Monitoring Extension
27th Jan 202311:28 amRNSProHearings presentation
26th Jan 20237:00 amRNSCEO Interview
25th Jan 20237:00 amRNSFunding to progress the development of Kallak
24th Jan 20231:03 pmRNSCEO Interview
24th Jan 20237:00 amRNSPositive Economics from Kallak North Scoping Study
17th Jan 202311:00 amRNSResult of General Meeting
13th Jan 20232:00 pmRNSPrice Monitoring Extension
12th Jan 20237:00 amRNSFurther investment in Vardar Minerals
9th Jan 20238:10 amRNSGrafintec Update - Anode Materials Plant PFS
30th Dec 20227:00 amRNSNotice of General Meeting
22nd Dec 20227:00 amRNSRääpysjärvi Assay Results
20th Dec 20227:00 amRNSFunding to progress the development of Kallak
16th Dec 20227:00 amRNSNew Highly Prospective Vardar Licences
14th Dec 20227:00 amRNSRed Lead - Exploration Target Identified
21st Nov 20227:00 amRNSDrilling into Majdan Peak Targets in Kosovo
18th Nov 20227:00 amRNSUnaudited Results Ended 30 September 2022
17th Nov 20227:00 amRNSCEO Interview
16th Nov 20227:00 amRNSJokkmokk Iron - Kallak Iron Ore Project Update
7th Nov 20227:00 amRNSBoard Changes
12th Oct 20227:00 amRNSSedermeradagen Presentation
7th Oct 20227:00 amRNSRääpysjärvi Results and Graphite Anode Value Chain
5th Oct 202212:50 pmRNSCEO Presentation
26th Sep 20227:00 amRNSGrafintec Signs new MoU For Anode Materials Hub
12th Sep 20227:00 amRNSThe vision for Jokkmokk Iron - CEO interviewed
8th Sep 20227:00 amRNSMajdan Peak: compelling exploration targets
25th Aug 202212:20 pmRNSGrafintec Update
22nd Aug 20227:00 amRNSDrilling Discovers Polymetallic Epithermal System
19th Aug 20227:00 amRNSUnaudited Financial Results
22nd Jul 20229:06 amRNSSecond Price Monitoring Extn
22nd Jul 20229:00 amRNSPrice Monitoring Extension
8th Jul 20227:00 amRNSLong Term Incentive Plan and Grant of Options
4th Jul 20227:00 amRNSFinancing of SEK 22 million
22nd Jun 202212:55 pmRNSAGM Results and Annual Report Publication
13th Jun 20227:00 amRNSCEO appointed for Jokkmokk Iron
10th Jun 202210:45 amRNSGállok / Kallak Update
31st May 20227:00 amRNSResults for the Period Ended 31 March 2022
26th May 20227:01 amRNSCEO Interview
26th May 20227:00 amRNSResults for the year ended 31 December 2021
13th May 20227:00 amRNSKallak Update – CEO Visit to Sweden
27th Apr 20227:00 amRNSKallak Update
21st Apr 202212:00 pmRNSDirector Dealing
30th Mar 20227:00 amRNSStart of Drilling in Kosovo
29th Mar 20227:00 amRNSKallak North Exploitation Concession
23rd Mar 20224:40 pmRNSSecond Price Monitoring Extn
23rd Mar 20224:35 pmRNSPrice Monitoring Extension
23rd Mar 20222:06 pmRNSSecond Price Monitoring Extn
23rd Mar 20222:00 pmRNSPrice Monitoring Extension
23rd Mar 202211:05 amRNSSecond Price Monitoring Extn
23rd Mar 202211:00 amRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.