Uis Tin Mine Operational Update

18 Feb 2020 07:00

RNS Number : 2749D
AfriTin Mining Ltd
18 February 2020
 

18 February 2020

AfriTin Mining Limited

("AfriTin" or the "Company")

Uis Tin Mine Operational Update

AfriTin Mining Limited (AIM: ATM), a tin mining company with a portfolio of assets in Namibia and South Africa, is pleased to provide an operational update relating to its Phase 1 Pilot Plant project ("Processing Plant") at its flagship asset, the Uis Tin Mine ("Uis") in Namibia.

Highlights

Maiden sale of tin concentrate concluded;

Second shipment of tin concentrate has been dispatched from the Uis mine;

Processing plant throughput increased by an average of 63% month-on-month from November 2019 to January 2020;

Debottlenecking of and enhancements to the Processing Plant underway to increase throughput and achieve nameplate production of 60 tonnes of tin concentrate per month; and,

Appointment of Mr. Nico Smit as Vice President of Operations and Projects.

The first shipment of tin concentrate (6 tonnes grading more than 60% Sn metal contained) has now been delivered to Thailand Smelting and Refining Company ("Thaisarco") according to the terms of the offtake agreement, as announced in August 2019. The concentrate was produced by the Company's Phase 1 pilot mining and processing facility at Uis during October and November 2019.

A second shipment of 20 tonnes of tin concentrate has been dispatched from the mine. The concentrate is trucked to the port of Walvis Bay in Namibia, then shipped to Thailand. The offtake agreement provides for an 80% prepayment for each shipment upon bill of lading in Walvis Bay.

Following initial production of tin concentrate, processing plant throughput has increased by an average of 63% month-on-month from 4,300 tonnes of ore in November 2019, to 5,800 tonnes in December 2019, and to 11,400 tonnes in January 2020. The Company expects to continue to ramp-up plant production over the next six months to nameplate of 45,000 tonnes of ore to the plant and the production of 60 tonnes of tin concentrate per month.

The ramp-up is supported by a number of operational commissioning initiatives including:

·; Transition from the current six-day plant roster to a continuous 24/7 operation, pending the required government approvals;

·; Debottlenecking of and enhancements to the Processing Plant, in particular the fines tailings dewatering circuits which require additional capacity due to a higher than expected fines ratio in the Run Of Mine feed;

·; Expanding the on-site laboratory to facilitate metal accounting and increased plant recovery; and,

·; Implementation of computerised maintenance management system to support targeted plant availability.

 

The debottlenecking of the Processing Plant focusses on the dewatering of the grits tailings (less than 630 microns), dewatering of the slimes tailings (less than 45 microns) and expanding the feed capacity to the spiral plant. Modifications that are currently in progress are expected to more than double the throughput capacity of these circuits.

The Company is also pleased to announce the appointment of Mr. Nico Smit as Vice President of Operations and Projects. He is a qualified processing engineer and brings a wealth of operational experience to the team which includes process plant commissioning and optimisation, and various executive management roles in the mining sector. He joins the Company from his current position as Regional Director Advisory at Hatch.

Anthony Viljoen, CEO of AfriTin Mining Limited commented:

 

"The first shipment of tin concentrate and first revenues from the Uis Tin Mine in three decades marks a significant milestone for the Company and the Erongo region of Namibia.

"We will continue to deliver this operation as we ramp up production to nameplate of 60 tonnes of tin concentrate per month. Combined with a JORC-compliant mineral resource estimate of 95,539 tonnes of contained Sn, we are well placed to advance the project to the goal of establishing an enlarged mining and processing facility."

 

Glossary of abbreviations

JORC

The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves

Sn

Elemental symbol for Tin

 

 

 

For further information, please visit www.afritinmining.com or contact:

AfriTin Limited

Anthony Viljoen, CEO

+27 (11) 268 6555

Nominated Adviser and Joint Broker

WH Ireland Limited

Katy Mitchell

Adrian Hadden

James Sinclair-Ford

+44 (0) 207 220 1666 

Corporate Advisor and Joint Broker

Hannam & Partners

Andrew Chubb

Jay Ashfield

Nilesh Patel

+44 (0) 20 7907 8500

Joint Broker

NOVUM Securities Limited

Jon Belliss

+44 (0)20 7399 9400

Financial PR (United Kingdom)

Tavistock

+44 (0) 207 920 3150

Jos Simson

Barney Hayward

 

The information contained within this announcement is deemed by the Company to constitute inside information under the Market Abuse Regulation (EU) No. 596/2014

About AfriTin Mining Limited

Notes to Editors

AfriTin Mining is the first pure tin company listed in London and its vision is to create a portfolio of globally significant, conflict-free, tin-producing assets. The Company's flagship asset is the Uis Tin Mine in Namibia, formerly the world's largest hard-rock tin mine.

AfriTin is managed by an experienced board of directors and management team with a current two-fold strategy: fast track Uis Tin Mine in Namibia to commercial production in 2020 as Phase 1, ramping up to 5,000 tonnes of concentrate in a Phase 2 expansion. The Company strives to capitalise on the solid supply/demand fundamentals of tin by developing a critical mass of tin resource inventory, achieving production in the near term and further scaling production by consolidating tin assets in Africa.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDEAFAXFDDEEAA
Date   Source Headline
27th May 20267:00 amRNSUis Financing & Lithium Ridge Drilling Complete
8th May 20269:45 amRNSNotification of Major Holdings
5th May 20267:00 amRNSSecond Batch of Lithium Ridge Drill Results
29th Apr 20268:31 amRNSNotification of Major Holdings
29th Apr 20267:00 amRNSAmendment of Convertible Loan Notes
24th Apr 20262:09 pmRNSNotification of Major Holdings
23rd Apr 20267:08 amRNS-RUpdate: Investor Presentation via IMC
20th Apr 20267:00 amRNSStrategic Equity Placement To Accelerate Growth
13th Apr 20267:00 amRNSPositive Tungsten Test Results At Brandberg West
26th Mar 20267:00 amRNSBusiness Update For Period Ended 28 February 2026
3rd Mar 20264:03 pmRNSEmployee Incentive Scheme Update
24th Feb 20267:00 amRNSThaisarco Strengthens Relationship with Andrada
10th Feb 20262:40 pmRNSEIB Partnership for Uis Mine Feasibility Study
9th Feb 20267:00 amRNSHigh-grade initial drill results at Lithium Ridge
4th Feb 20267:00 amRNSACAM Transaction Update
26th Jan 20267:00 amRNSLithium Ridge Exploration Update
21st Jan 20267:00 amRNSPartnership with ACAM to develop Brandberg West
19th Jan 202611:00 amRNSOrange Trust Loan Conversion to Equity
17th Dec 20257:00 amRNSQ3 Operational Update For Period End 30 Nov 2025
1st Dec 202510:35 amRNSNotification of Major Holdings
27th Nov 20257:00 amRNSInterim Results for Six Months Ended 31 Aug 2025
7th Nov 20257:00 amRNS-RPublication of 2025 Sustainability Report
24th Oct 20255:26 pmRNSNotification of Major Holdings
24th Oct 20255:25 pmRNSNotification of Major Holdings
30th Sep 20252:00 pmRNSResults of the Annual General Meeting
29th Sep 20257:00 amRNSBoard Changes
15th Sep 20257:00 amRNSQ2 Operational Update For Period Ended 31 Aug 2025
3rd Sep 20257:00 amRNSExploration Drilling Commences at Lithium Ridge
29th Aug 20257:00 amRNSAudited Financial Results For Year End 28 Feb 2025
21st Aug 20257:00 amRNSAndrada accelerates growth of its tin production
15th Aug 20257:00 amRNSIssuance of Shares & Total Voting Rights
27th Jun 20257:00 amRNSResults of strategic Subscription & Placing
26th Jun 20257:00 amRNSProposed Strategic Subscription and Placing
19th Jun 20252:00 pmRNSNotification of Major Holdings
17th Jun 20257:00 amRNSAndrada Secures High-Grade Tin Feedstock
6th Jun 20257:00 amRNSOperational Update For Period Ended 31 May 2025
22nd May 202511:28 amRNSChange of Registered Address
10th Apr 20257:00 amRNSUis Exploration Drilling Results
31st Mar 20257:00 amRNSFY Operational Update For Period Ended 28 Feb 2025
11th Mar 202512:59 pmRNSNotification of Major Holdings
7th Mar 202512:41 pmRNSNotification of Major Holdings
4th Mar 20254:51 pmRNSDirector/PDMR Shareholding
28th Feb 20257:00 amRNSSQM earn-in agreement receives NaCC Approval
21st Feb 20252:17 pmRNSEmployee Incentive Scheme Update & Issue of Shares
14th Feb 202512:20 pmRNSNotification of Major Holdings
12th Feb 20257:00 amRNSOrange Trust Funding
6th Feb 20257:00 amRNSMineral Resource Update at Uis
20th Dec 20247:00 amRNSQ3 Operational Update for Period Ended 30 Nov 24
28th Nov 20247:00 amRNSUnaudited Interim Results 6 Months Ended 31/08/24
20th Nov 20247:00 amRNSPublication of 2024 Sustainability Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.