Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAsa Resources Regulatory News (ASA)

  • There is currently no data for ASA

Operations and exploration update

18 Oct 2011 07:00

RNS Number : 3355Q
Mwana Africa PLC
18 October 2011
 

18 October 2011

Mwana Africa PLC

("Mwana", the "Group" or the "Company")

Operations and Exploration Update

Mwana Africa PLC is pleased to provide an update on operations and exploration activity for the quarter ending 30 September 2011.

Highlights

·; Quarterly gold production at Freda Rebecca of 13,686oz (equivalent to an annualised rate of 54,720 oz per annum), exceeded the Phase II target annualised production rate of 50,000 oz.

·; Phase II monthly target production achieved three months ahead of schedule.

·; Phase II tonnage build up underpinned by successful ramp up of underground production volumes.

Mwana Chief Executive Officer, Kalaa Mpinga, commented: "I am delighted with the progress at Freda Rebecca in particular, where the Phase II production target was reached well ahead of schedule. This success is a result of the commitment and dedication of our management team. Our next objective at Freda Rebecca is to focus on operating efficiency and reliability whilst seeking to optimise plant performance."

 

Freda Rebecca Gold Mine

A total of 13,686 ounces ('ozs') of fine gold were produced during the quarter ending September 2011. Average monthly production for the quarter was 4,562oz (which was in excess of the Phase II target of 4,167 oz per month). Targeted production rates were therefore achieved three months ahead of schedule.

Qtr ending 30 September 2011

Qtr ending 30

June 2011

Variance

Tonnes Mined (t)

254,096

179,238

41.8%

Tonnes Milled (t)

275,099

151,219

81.9%

Head Grade (g/t)

2.29

2.22

3.2%

Recovery (%)

77%

83%

(7.2)%

Gold ounces produced (oz)

13,686

8,224

66.4%

Average Gold Price Received ($/oz)

1,708

1,517

12.6%

Cash operating costs ($/oz)

886

1,004

(11.8)%

SIB Capex

932,894

363,831

156.4%

Phase 2 Capex

1,547,980

1,490,771

3.8%

Exploration Capex

51,635

0

-

 Note: figures shown are unaudited and may vary upon final audit. Gold ounces reported are exclusive of ounces attributable to gold in lock-up in the leach circuit.

During the quarter, underground expansion of load and haul capacity progressed well and has achieved the level of performance necessary to sustain Phase II production volumes. Development work and production drilling has enabled the operation to access an additional production block. This has had a positive impact on tonnage generation and in sustaining planned mill feed grade.

Head grade for the quarter was on budget. Recoveries were adversely affected by poor grinds during commissioning phase and leach tank outages which affected residence times.

As previously announced, Mill II and associated CIL/CIP circuits were completed on time and on budget and the ramp up to the Phase II target rate of production has now been achieved. The combined milling circuits have performed well and integration and optimisation of the combined feed classification systems is ongoing to improve process recoveries.

Freda Rebecca continues to engage the government of Zimbabwe on the issue of indigenization and management remains optimistic that this will be resolved.

Further information about Freda Rebecca Gold Mine can be found at: www.mwanaafrica.com/oe/zim_freda.asp

Zani-Kodo JV

Drilling continued with two rigs active during the reporting period. Twenty holes were completed in the quarter for a total of 4,957m drilled.

Drilling was carried out in the following areas (Figure 1):

§ Zani Central. Drilling was completed over the 650m strike length of this target. Inclined holes were drilled to test the shallow portion of the mineralised zone.

§ Kodo downdip extension. A further 'step out' drilling of 5 holes was completed to target the downdip extension of the high grade Kodo Main zone. In addition a single infill hole along the northern limit of the Kodo main zone was completed in order to fully close off mineralisation in that direction.

Results for 16 holes at Zani Central were received during the quarter and are summarised in Table 1 below:

Hole ID

Intersection (m)

Grade

(g/t Au)

From

To

Width

ZNCDD021

52

53

1

1.67

79

86

7

0.79

156

187

31

1.29

Including

161

165

4

2.11

and

183

184

1

9.20

ZNCDD025

176

193

17

1.46

Including 

187

193

6

2.81

ZNCDD037

194

203

9

3.26

ZNCDD001

87

103

16

1.22

Including 

91

96

5

2.4

ZNCDD003

No significant intersections

ZNCDD004

No significant intersections

ZNCDD008

78

91

13

0.95

94

103

9

1.04

ZNCDD009

142

154

12

1.07

ZNCDD010

212

226

14

1.24

Including 

222

225

3

2.99

ZNCDD002

179

180

1

4.20

ZNCDD014

134

158

24

0.81

Including

142

152

10

1.30

170

189

19

0.95

Including

176

180

4

2.16

ZNCDD029

178

195

17

1.66

Including

178

184

6

1.98

and

188

195

7

2.11

205

215

10

2.01

Including

211

215

4

4.03

ZNCDD013

76

83

7

1.85

Including

81

82

1

9.30

100

101

1

2.23

123

133

10

0.99

Including

123

129

6

1.49

138

144

6

0.76

147

153.00

6

0.50

ZNCDD050

125

140

15

1.13

Including

135

140

5

1.64

191

192

1

3.72

ZNCDD053

90

104

14

1.01

107

113

6

0.81

ZNCDD061

60

62

2

1.52

69

71

2

2.61

80

81

1

8.80

 

Table 1. Assay results received from July-September 2011, Zani Central area.

The results status of Zani Central at the end of September 2011 is shown in Figure 2.

§ The results indicate the continuity of a broad (12-37m) zone of low grade mineralization with narrow high grade portions locally. The mineralised zone is associated with a sheared Banded Iron Formation;

§ The zone dips to the east at around 50° and is continuous along strike with 650m identified to date;

§ The lack of intersections in the northernmost holes (ZNCDD002 and ZNCDD003) indicates that mineralisation has been closed off in that direction. This is interpreted to be the result of a NE trending fault;

§ The zone remains completely open at depth and to the south;

§ A resource calculation will be carried out once all remaining results have been received.

Kodo downdip extension

§ No assay results have been received as yet;

§ Visible sulphide zones with pyrrhotite and arsenopyrite are present in all holes and at the targeted depth for the extension of the high grade Kodo Main orezone;

§ The best visible intersection is a 19m wide sulphide rich zone in hole KDODD063;

§ An updated resource calculation for the Kodo Main zone will be carried out once results have been received;

Forward Plan

Drilling will continue on the Kodo downdip extension and will be initiated at the Gombiri target immediately south of Zani Central.

 

For figures 1 and 2, please click on the link below:

http://www.rns-pdf.londonstockexchange.com/rns/3355Q_-2011-10-17.pdf

 

 

Further information about Zani Kodo can be found at: http://www.mwanaafrica.com/oe/drc_zani.asp

Bindura Nickel Corporation

BNC's assets remained on care and maintenance for the quarter ending 30 September 2011, successfully maintaining the integrity of the assets whilst restart funding is sought.

In September BNC shareholders approved a convertible loan facility of $10m to be provided by Mwana. The loan element of the facility has been approved by the Reserve Bank of Zimbabwe. Mwana will be able to exercise the convertible element of the facility only upon a further specific approval by the Reserve Bank of Zimbabwe and the Ministry of Youth Development, Indigenisation and Empowerment. The facility allows Mwana to provide funds for the ongoing working capital requirements at BNC.

The Trojan Mine remains ready to resume production, with all the processes up to the tertiary crushers having been hot commissioned in the previous financial year. Limited development and drilling continues to be undertaken at Trojan. The mine hoisted 1,982 tonnes of waste and 3,541 tonnes of ore during the quarter as part of its care and maintenance programme. Total underground development during the care and maintenance programme stood at approximately 1,045m at the end of September 2011. The current development is targeting key priority areas included in the restart plan.

 

Further information about Bindura Nickel Corporation can be found at: http://www.mwanaafrica.com/oe/zim_bnc.asp

 

 

Katanga Concessions (SEMHKAT)

During the quarter exploration work concentrated on the Lunsano and Kitemena-Kitungulu areas. These areas are located in license areas PR754, PR757 and PR758 (Fig 3).

Kitemena-Kitungulu

Regional geological mapping is on-going. Regional mapping has revealed mainly rock units of the Lower Kundelungu comprising Grand conglomerat and shale units exhibiting silicification and iron-metasomatism (Fig 4).

Lunsano

The Lunsano area hosts a copper anomaly 2km by 2km in areal extent and of the size +100pm Cu. The Lunsano area overlies Roan units which have strong potential for copper mineralization.

Detailed geological mapping is on-going with the aid of trenching and pitting and the geology has been updated (Fig 5). Mapping has revealed rock units of argillaceous talcaceous shale, grand conglomerat, laminated and silicified dolomites, vuggy or stromatolitic dolomite, sandstone and ferruginous dolomitic shale. Chalcopyrite mineralization has been identified in outcrops of gossanous dolomitic shale which also underlie the Lunsano copper anomaly. The area is considered to have excellent potential for significant copper mineralization.

Kibandawepala Hill is situated in PR754 (Fig 5). This area contains a doleritic intrusion. Malachite mineralization associated with quartz veining, talc zones and specular haematite have been observed in pits. A 202.2m trench has been dug showing brecciated and highly sheared zones (talc schist) in the metadolerite. The trench has been sampled and results are awaited. The area is considered to have potential for Cu-Fe-Ni mineralization.

A total of 85 pits and 345m of trenching has been completed in Lunsano. Currently trenching is investigating the potential of the exposed units of the Mines Group (SD, RSC and RSF) to the south west of Lunsano.

 

Month

Pits

Trenches

No of pits

volume(m3)

No of trenches

Metrage(m)

July

0

0

0

0

August

14

24.25

1

202.4

September

71

181.77

1

143.2

Total

85

206.02

2

345.6

Table 2. Lunsano pitting and trenching.

 

Regional soil sampling was carried out on a grid 1km by 400m which was then reduced to infill grids of 500m by 200m and then 200m by 50m. Sampling to date at Lusano and Kitemena-Kitungulu is summarized in Table 3. A total of 401 termite samples from the Lunsano copper anomaly have been taken.

 

Area

month

Soil

Termite

Trench

Pit

Rock chip

Total

Lunsano

July

819

0

0

0

0

819

August

632

129

199

0

3

963

September

0

272

0

90

0

362

Kitemena-Kitungulu

August

224

0

0

0

0

224

Total

1675

401

199

90

3

2368

 

Table 3. Summary of Sampling.

 

A total of 2,278 soil and termite samples have been sent to laboratory to date. A total of 199 samples from the 202.2m trench at Kibandawepala Hill have also been submitted. Samples taken from pits and trenches at Lunsano will be analysed by Niton.

A total of 977 soil sample results have been received to date and updated on plan (Fig 6).

At Lunsano the results indicate a strong copper anomaly to the south and east, thus making the dolomitic shale-conglomerate contact a potential target.

The Kibandawepala hill shows a strong copper anomaly of the size +400ppm (Fig 6) and with a peak value of 2090ppm. The results on the hill show elevated nickel and zinc values with peaks of 1350ppm Ni and 430ppm Zn. The spatial analysis of Ni and Zn content in relationship with copper content will be assessed.

Forward Plan at SEMHKAT:

·; Continuation of detailed geological mapping at Lunsano;

·; Continuation of regional geological mapping to the north of Kitungulu-Kitemena;

·; Trench-pit sampling and trench-pit sample preparation in Lunsano to continue;

·; Continuation of field data and sample results capturing and updating of plans and sections;

·; Continuation of creation of new database;

·; Review of potential Semhkat permits for soil sampling.

 

For figures 3-6, please click on the link below:

 

 

Further information about the Katanga Concessions can be found at http://www.mwanaafrica.com/oe/drc_katanga.asp 

 

Klipspringer Diamond Mine

Underground recovery of the shaft bottom was completed during the period under review. The mine has been completely dewatered and cleaning the final remnants of mud and debris are almost complete.

Before the mine can start with production from the underground workings, the following work needs to be completed:

·; Re-establish permanent electrical reticulation damaged during the flood;

·; Seal off fissure opening where the main water course crosses the Leopard fissure;

·; Install and commission main pumps at shaft bottom.

The first rains of the summer season have fallen, thereby minimizing the risk to mine property and infrastructure from veldt fires. In total 20mm have fallen and the storm water control measures implemented after the flooding incidents at the end of 2010 proved effective.

The diamond market softened somewhat during the quarter whilst the rand weakened towards the end of the reporting period. Management continues to review market conditions regularly and evaluate various options to bring the mine back into operation.

 

Further information about Klipspringer Diamond Mine can be found at: http://www.mwanaafrica.com/oe/sa_klipspringer.asp

Charl du Plessis, Executive Vice President Exploration of Mwana Africa, who holds a PhD and is a Member of the AusIMM, and, James Arthur, Executive Vice President Operations of Mwana Africa, Fellow of the Southern African Institute of Mining and Metallurgy, are 'Qualified Persons' as defined in the AIM Rules. The exploration and resource information contained in this report pertaining to Zani Kodo and SEMHKAT have been reviewed and verified by Dr Du Plessis, and, the resource information contained in this report pertaining to Trojan mine, Shangani mine, Hunters Road and Freda Rebecca Gold Mine have been reviewed and verified by Mr. Arthur.

Enquiries:

Mwana Africa PLC Tel: +44 (0)20 7654 5580

Kalaa Mpinga

Donald McAlister

 

Nominated Adviser and Broker

Ambrian Partners Limited Tel: +44 (0) 20 7634 4700

Anthony Rowland / Jen Boorer

 

Joint Broker

XCAP Securities plc

Jon Belliss / John Grant / Parimal Kumar Tel: +44 (0)20 7101 7070

 

Public Relations

Merlin Tel: +44 (0)20 7726 8400

David Simonson

Anca Spiridon

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAXEXFAPFFFF
Date   Source Headline
21st Aug 20124:59 pmRNSNotice of AGM
21st Aug 20127:02 amRNSSEMHKAT agreement
13th Aug 20127:00 amRNSBNC Rights Issue Update
24th Jul 20127:01 amRNSOperations and Exploration Update
12th Jul 201211:05 amRNSPurchase of Shares by Director
6th Jul 20127:05 amRNSPurchase of Shares by Director
5th Jul 20122:27 pmRNSPurchase of Shares by Director
4th Jul 20127:05 amRNSDirectorate Change
4th Jul 20127:00 amRNSFinal Results
19th Jun 20127:02 amRNSISO 14001 and OHAS 18001 Certification
7th Jun 20127:02 amRNSFunding to restart the Trojan Nickel Mine
7th Jun 20127:01 amRNSDirectorate Change
18th May 201211:44 amRNSAdmission & Total Voting Rights
18th May 20127:00 amRNSDisposal of 15% interest in Freda Rebecca
23rd Apr 20122:50 pmRNSBlock Listing Six Monthly Return and Increase of B
23rd Apr 20127:05 amRNSQ1 Operations and Exploration Report
20th Apr 20123:40 pmRNSDirector's Interests and Total Voting Rights
19th Apr 20123:11 pmRNSEGM Statement
4th Apr 20124:40 pmRNSSecond Price Monitoring Extn
4th Apr 20124:35 pmRNSPrice Monitoring Extension
3rd Apr 20123:42 pmRNSPosting of Circular
2nd Apr 20127:00 amRNSFundraising to raise approximately US$35m
13th Mar 20129:26 amRNSHolding(s) in Company
2nd Feb 20127:00 amRNSZani Kodo Resource Update
27th Jan 20127:00 amRNSOperations and Exploration Update
12th Jan 20122:03 pmRNSHolding(s) in Company
5th Jan 20127:00 amRNSAppointment of Director
12th Dec 20117:00 amRNSHalf Yearly Report
24th Oct 20114:40 pmRNSSecond Price Monitoring Extn
24th Oct 20114:35 pmRNSPrice Monitoring Extension
21st Oct 20114:38 pmRNSBlock Admission return
18th Oct 20117:00 amRNSOperations and exploration update
26th Sep 20111:24 pmRNSConvertible Loan Facility for BNC
19th Sep 20113:50 pmRNSClarification regarding press coverage
14th Sep 20111:42 pmRNSResults of AGM and Board Change
5th Sep 20114:47 pmRNSGrant of Options
25th Aug 20114:54 pmRNSDirector/PDMR Shareholding
23rd Aug 20114:16 pmRNSIndigenisation & Economic Empowerment Legislation
18th Aug 20116:27 pmRNSReplacement - Notice of AGM
18th Aug 20115:00 pmRNSNotice of AGM
16th Aug 20117:00 amRNSFreda Rebecca Gold Mine - Project Finance Update
10th Aug 20117:00 amRNSOperations and Exploration Update
1st Aug 20117:00 amRNSResource Update Zani Kodo
26th Jul 20117:00 amRNSAudited Results for the year to 31 March 2011
30th Jun 20117:00 amRNSTotal Voting Rights
20th Jun 20117:00 amRNSAppointment of Joint Broker
16th Jun 20117:00 amRNSOperational Update
15th Jun 20115:13 pmRNSHolding(s) in Company
14th Jun 20119:00 amRNSDirectors Interests
9th Jun 201110:10 amRNSResult of EGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.