Arckaringa Project Update

13 Aug 2012 07:00

RNS Number : 8339J
Altona Energy PLC
13 August 2012
 



13th August 2012

 

ARCKARINGA PROJECT UPDATE

 

All Required Regulatory Approvals Secured for Test Drilling

 

Altona Energy ("The Company") is pleased to announce an update to its flagship Arckaringa project in South Australia, the results of which will allow the drilling programme to proceed. The company has recently had its Program for Environmental Protection and Rehabilitation (PEPR) approval extended by six months to November by the South Australian Department of Manufacturing, Innovation, Trade, Resources and Energy (DMITRE) in view of the time taken by the Government to issue the Water Affecting Activity (WAA) permit and time needed to make required changes to the drilling programme as part of the Work Area Clearance (WAC) process.

 

Also, the WAA Permit -required to cover the hydro-geological test and other drill holes, pursuant to the terms of the PEPR - was recently granted by the South Australian Arid Lands Natural Resources Management Board under the newly expanded and strengthened regulations governing water affecting activities in the Arid Lands regions of South Australia.

 

Following discussions with the Native Title claimant group Antakarinji Matu-Yankunytjatjara Aboriginal Corporation (AMYAC) and its representatives, the WAC process has also now formally been completed. The discussions have been ongoing since October 2011 and led to a formal acceptance by AMYAC on 12 July that the drilling programme design and drill hole locations meet the terms of the WAC (as required under the PEPR granted by DMITRE ). As a result, all drill hole locations are now cleared for drilling. 

 

The WAC process involved the relocation and/or redesign of six of the proposed maximum 31 drill holes to protect aboriginal heritage concerns during, and as a result of, the drill programme . These changes were achieved co-operatively and were checked by technical consultants in China and Australia to ensure that the technical objectives of the programme would still be achieved. During discussions, AMYAC and the Arckaringa JV partners have maintained their positive relationship and have agreed to work together to achieve and implement a framework or Memorandum of Understanding (MOU) that can lead to a Native Title Agreement to cover respective rights, responsibilities and economic opportunities during any future mining and development project at Wintinna.

 

With permits and approvals now in place, CNOOC NEIA is clear to finalise its selection of drilling programme consultants from China and Australia - including drilling contractors and other service providers - to allow the programme to proceed. The key objectives of the programme are:

 

·; to extract bulk samples of coal to test and extend the coal quality profile

·; to complete in-fill coal and coal geotechnical boreholes to facilitate open cut mine design (especially in an area covering the potential initial box cut)

·; to complete hydro-geological test wells to enable the refinement of the existing hydro-geological model and underpin a groundwater management plan.

 

Attaining these objectives is essential to the progress of the Bankable Feasibility Study (BFS) for the Arckaringa CTL and Power Project.

 

Chris Lambert, Executive Chairman of Altona Energy commented: "This is a significant moment for the Arckaringa project. All regulatory approvals are now in place to allow the commencement of the drilling programme. We have also achieved some important regulatory and community relations milestones as we have worked through the approval process, which will stand our future field activities in very good stead . Large scale long-term projects like Arckaringa certainly have their challenges for everyone involved, but it is clear that we have made some very sound progress in the last few months, and we look forward to updating the market with more news on the drilling programme as it becomes available."

 

For further information, please visit www.altonaenergy.com or contact:

 

Altona Energy Plc

Christopher Lambert, Chairman

Christopher Schrape, Managing Director

Peter Fagiano, Executive Director

 

 

+44 (0) 20 7024 8391

 

WH Ireland Ltd

Adrian Hadden

James Bavister

 

 

+44 (0) 20 7220 1666

Old Park Lane Capital Plc

Michael Parnes

Luca Tenuta

 

 

+44 (0) 20 7493 8188

Tavistock Communications

Mike Bartlett

Simon Hudson

 

+44 (0) 20 7920 3150

 

-ends-

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLBKBDQOBKDAFD
Date   Source Headline
1st Jun 20107:00 amRNSCNOOC-NEIA - Successful FIRB Assessment
30th Apr 20107:00 amRNSTotal Voting Rights
23rd Apr 20104:03 pmRNSExercise of Options
21st Apr 20107:00 amRNSCNOOC-NEIA's Submission of FIRB Application
20th Apr 20107:00 amRNSFormal Signing of Joint Venture
16th Apr 201010:00 amRNSBoard Change & Director Dealings
7th Apr 20103:15 pmRNSHolding(s) in Company
1st Apr 20103:26 pmRNSExercise of Options
30th Mar 20107:00 amRNSPlacing to raise ?3.0 million
30th Mar 20107:00 amRNSCNOOC-NEI Joint Venture Success Fees & Options
30th Mar 20107:00 amRNSInterim Results
11th Mar 20107:00 amRNSAppointment of Project Technology Executive
9th Mar 20103:12 pmRNSExercise of Options
24th Feb 20107:00 amRNSNew Website and Presentation
9th Feb 20107:00 amRNSAppointment of Broker and Nominated Adviser
29th Jan 20107:00 amRNSTotal Voting Rights
14th Jan 20103:00 pmRNSDirector/PDMR Shareholding
12th Jan 20104:22 pmRNSExercise of Options
5th Jan 20104:00 pmRNSDirector/PDMR Shareholding
18th Dec 200912:30 pmRNSResult of AGM
18th Dec 200910:02 amRNSChairman's AGM Statement
17th Dec 200912:00 pmRNSRe Rentech Announcement
2nd Dec 200911:45 amRNSHolding(s) in Company
23rd Nov 20097:00 amRNSFinal Results
18th Nov 20097:00 amRNSSign Binding Agreement with CNOOC-NEI
10th Nov 20093:45 pmRNSHolding(s) in Company
3rd Nov 20097:00 amRNSHolding(s) in Company
30th Oct 20097:00 amRNSTotal Voting Rights
2nd Oct 20092:00 pmRNSExercise of Options
9th Sep 20095:57 pmRNSHolding(s) in Company
8th Sep 20097:00 amRNSJoins Global Carbon Capture and Storage Institute
28th Aug 20097:25 amRNSTotal Voting Rights
27th Aug 20094:40 pmRNSHolding(s) in Company
7th Aug 20093:50 pmRNSHolding(s) in Company
3rd Aug 20097:30 amRNSPlacement to Invesco Perpetual
3rd Aug 20097:00 amRNSFinancing Update
26th Jun 20097:00 amRNSJV Terms Sheet Agreed with CNOOC-NEI
14th May 20092:00 pmRNSInvestor Relations Presentation
31st Mar 20099:30 amRNSInterim Results
6th Jan 20099:00 amRNSHolding(s) in Company
23rd Dec 200811:30 amRNSCompany Website
19th Dec 20084:13 pmRNSAGM Statement
8th Dec 20081:30 pmRNSDirector/PDMR Shareholding
26th Nov 20089:08 amRNSFinal Results
1st Sep 20087:00 amRNS1.287bn Tonne JORC Compliant
20th Aug 20081:00 pmRNSIssue of Options
19th Aug 20087:00 amRNSMOU with CNOOC
8th Aug 200811:30 amRNSHolding(s) in Company
8th Aug 20087:00 amRNSAppointment of Ambrian Partne
1st Aug 20083:00 pmRNSDirector's Disclosure Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.