Operational Update

14 May 2013 07:00

RNS Number : 6126E
Amerisur Resources PLC
14 May 2013
 



14 May 2013

 

Amerisur Resources Plc ("Amerisur" or the "Company")

 

Operational Update

 

Amerisur Resources Plc, the oil and gas producer and explorer focused on South America, will hold its Annual General Meeting (AGM) today at 9:30 AM. At that meeting Giles Clarke, Chairman, and John Wardle, Chief Executive will provide the following summary on recent progress.

 

Colombia - Platanillo Block

 

·; Platanillo-11 encountered a 49.5 ft total net pay in the U sand and 17 ft net pay in the T sand.

 

·; Alea-1R sidetrack encountered a 40 ft total net pay in the U sand and 8.5 ft in the T sand.

 

·; Platanillo Field production currently at approximately 5,400 bopd, constrained by pipeline and export facility upgrade works.

 

·; Total field production capacity estimated at 7,500 bopd before the contribution of Platanillo-11 and Alea-1R ST1.

 

The well Platanillo-11, located on Platform 5 South (5S) has been drilled to a total depth of 8,733ft MD using the Latco-01 drilling rig. Platanillo-11 is a directional well, deviated approximately 1,697 ft south east of platform 5S. The well encountered an interval of 95 ft Gross, 49.5 ft net indicated pay in the U sand and 34 ft gross, 17 ft net in the T sand. As predicted by our geophysical model, the N sand was not well developed at this point. It is expected the well will be completed and placed on production during May.

 

The Latco-01 rig will be skidded onto the next slot within the 5S location and will spud well Platanillo-12. Platanillo-12 is a directional well whose reservoir target is located 1,837ft to the south west of the 5S location.

 

Alea-1, drilled in 1988 and re-entered in 2007 by Ecopetrol, was sidetracked to a location approximately 1,008ft to the north west of the original well location. This well, named Alea-1R ST1, encountered a gross pay interval of 85ft and 40ft net pay interval in the U sands. The T sand exhibited 18ft gross and 8.5ft net. It is expected that this well will also be completed and placed on production during May.

 

Post completion and testing of Alea-1R ST1, the Serinco D-10 drilling rig will be moved to the Platanillo-2 well in the same location in order to side track it. It is planned to re-enter and sidetrack that well to a structurally more favourable position for oil production.

 

Platanillo field production continues to be constrained by local export conditions but the Company continues to develop new alternatives for oil delivery, and expects those options to allow a continued growth in production over the coming months. As part of its efforts to enhance export capacity from the Platanillo, the Company has signed an agreement with the operator of the Rio Loro oil reception facility, Huila Colombia, to receive a minimum of 3,500BOPD from the Platanillo field. Current Platanillo Field production is running at approximately 5,400 bopd against an estimated capacity of 7,500 bopd before the contribution of Platanillo-11 and Alea-1R ST1.

 

Colombia - Fenix Block

 

Interpretation of the newly acquired 2D seismic data continues. The Company expects to drill a further exploration well in Fenix during the year.

 

Paraguay

 

A gravity survey has been initiated in the western blocks in Paraguay. Additionally the Company has performed geochemical analysis on cuttings from the Asuncion wells in the San Pedro block.

 

Giles Clarke, Chairman said:

 

"I am very pleased with the strong progress we have made over the last year. Our hard work in the fields has been rewarded with exceptional results, which we will continue to build upon. Our portfolio is both widening and deepening, creating along term, sustainable and very profitable business."

 

ENDS

 

A short presentation which will be given at the AGM will be available shortly after the AGM on the website www.amerisurresources.com.

 

Competent person: Technical information in this announcement has been reviewed by John Wardle Ph.D., the Company's Chief Executive. John Wardle has 28 years' experience in the industry, having worked for BP, Britoil, Emerald Energy and Pebercan, and is a trained drilling engineer.

 

 

ENQUIRIES:

 

FTI Consulting

Billy Clegg/ Natalia Erikssen

 

Tel: +44 (0)207 831 3113

 

RBC Capital Markets

Martin Eales/ Pierre Schreuder

 

Tel: +44 (0)207 653 4000

Investec

Chris Sim / Ben Colegrave

 

Tel: +44 (0)207 597 4000

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBRGDUISBBGXX
Date   Source Headline
5th Feb 20187:00 amRNSMonthly Production, OBA and Operational Update
22nd Jan 20187:00 amRNSEcuador Update
4th Jan 20187:00 amRNSMonthly Production, OBA and Operational Update
18th Dec 20171:30 pmRNSNotification of major holdings
14th Dec 20177:00 amRNSPlatanillo-27 Update
4th Dec 20177:00 amRNSMonthly Production, OBA and Operational Update
1st Dec 20174:41 pmRNSSecond Price Monitoring Extn
1st Dec 20174:36 pmRNSPrice Monitoring Extension
1st Dec 20177:00 amRNSBlock Listing Six Monthly Return
21st Nov 20177:00 amRNSOperational Update - CPO-5
13th Nov 20177:00 amRNSOperations Update
6th Nov 20177:00 amRNSMonthly Production, OBA and Operational Update
31st Oct 20179:24 amRNSDirector Share Dealing
27th Oct 20173:51 pmRNSCPO-5 Update
26th Oct 20177:00 amRNSPlatanillo-25 Update
24th Oct 201710:15 amRNSDirector Share Dealing
19th Oct 20177:00 amRNSOperational Update
18th Oct 20173:16 pmRNSBlock Listing Six Monthly Return
12th Oct 201712:22 pmRNSNotification of Major Shareholdings
2nd Oct 20177:00 amRNSMonthly Production, OBA and Operational Update
26th Sep 20179:26 amRNSDirector Share Dealing
25th Sep 20173:35 pmRNSDirector Share Dealing
25th Sep 20177:00 amRNSInterim Results
20th Sep 20175:48 pmRNSTR-1 Notification of Major Holdings
4th Sep 20177:00 amRNSMonthly Production and OBA Throughput Update
24th Aug 20177:00 amRNSNotice of Interim Results
9th Aug 20177:00 amRNSMariposa-1 Update CPO-5 Block
3rd Aug 20177:00 amRNSOperational Update
5th Jul 20177:00 amRNSMonthly Production, OBA and Operations Update
15th Jun 20177:00 amRNSPlatanillo Operations Update
12th Jun 20177:00 amRNSMonthly Production and OBA Throughput Update
30th May 20177:00 amRNSMariposa-1 Update CPO-5 Block
25th May 20177:00 amRNSPlatanillo-21 Update
9th May 201712:33 pmRNSResult of AGM
9th May 20179:30 amRNSAGM Statement
8th May 20177:00 amRNSAppointment of Senior Independent Director
4th May 20172:25 pmRNSSuccessful drilling at CPO-5 Block - Llanos Basin
4th May 20177:00 amRNSPlatanillo Operations Update
2nd May 20177:00 amRNSMonthly Production and OBA Throughput Update
25th Apr 20175:59 pmRNSHolding(s) in Company
21st Apr 20178:34 amRNSAGM Statement (Replacement)
21st Apr 20177:00 amRNSOperations Update - Platanillo-21 Spudded
20th Apr 20176:29 pmRNSNotice of Annual General Meeting
20th Apr 20177:00 amRNSOperations Update
10th Apr 20177:00 amRNSFinal Results for the year ended 31 December 2016
6th Apr 20177:00 amRNSAppointment of independent non-executive Director
4th Apr 20177:00 amRNSMonthly Production and OBA Throughput Update
30th Mar 201710:35 amRNSPlatanillo-22 Update
27th Mar 20177:00 amRNSColombia Operations Update
23rd Mar 20178:13 amRNSReserves & Resources Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.