The latest Investing Matters Podcast with Jean Roche, Co-Manager of Schroder UK Mid Cap Investment Trust has just been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAltyngold Regulatory News (ALTN)

Share Price Information for Altyngold (ALTN)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 110.50
Bid: 110.00
Ask: 111.00
Change: -2.50 (-2.21%)
Spread: 1.00 (0.909%)
Open: 113.00
High: 0.00
Low: 0.00
Prev. Close: 113.00
ALTN Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Project Update

30 Nov 2006 07:01

Hambledon Mining PLC30 November 2006 HAMBLEDON MINING PLC Recent progress (All references to "£" are to the British Pound and "ounces" are to troy ounces) Hambledon Mining plc ("Hambledon" or the "Group" or the "Company"), anAIM-listed mining and exploration company developing precious metal deposits inKazakhstan, reports progress on its Sekisovskoye project. Highlights •Mining activities in the year to date have been more than double the planned rate. •Initial ore stockpiles for process plant commissioning have been established. •Foundations for the mill building, warehouse and major equipment (ball mills, leach tanks, crushers) have been completed. •Construction of mill building well advanced with all materials on site. Construction of main arches of warehouse completed. •All major equipment has been procured and some 90% of contracts for final construction let. €110 kV powerline and substation nearing completion three months ahead of schedule. •Excavation of the "starter" tailings dam nearing completion and geomembrane liner received at site. •Start of commissioning of process plant on schedule for the second quarter 2007. •Diamec diamond drill rig previously used underground has been modified for surface use; drilling with this unit commenced at Tserkovka in October and will continue throughout the winter. Nicholas Bridgen, Chief Executive of Hambledon Mining plc, commented: "As a result of the skilled local workforce and better than expectedproductivity of the equipment, mining operations have exceeded all ourexpectations. We have now shifted all the site earthworks to our own mining teamwhich will reduce the costs significantly. "Progress to date is ahead of schedule and we remain on course towards start-upof the process plant, as previously estimated, in the second quarter of 2007". Sekisovskoye Update Mining activities at Sekisovskoye commenced in early June. The volume ofmaterial mined so far in 2006 is some 107% in excess of that submitted in themining plans approved by the State Mining Committee. This material includes themining and stockpiling of over 22,000 tonnes of ore from previously unidentifiedore zones, which can be used for the commissioning of the process plant in 2007.As expected from this type of deposit, ore is being found in zones previouslythought to be waste, and this should have a positive impact on future strippingratios and total ore tonnage. Pit development has focused on the expansion of the existing North Pit toprovide construction material for the processing plant as well as advance accessto the high grade No.2 orebody and to the top of Sedukha Hill to allow for thephased development of the Main Pit in 2007. Drilling and blasting in hard rockareas of the open pit have begun using the Company's Atlas Copco blasthole rigand a local blasting contractor. The mining activities have been so successful that construction work planned tobe undertaken by local earthmoving contractors will now be carried out by theSekisovskoye mining team at much lower cost. This work includes topsoilstripping, access road construction and construction of the process planttailings dam. These higher than planned mining volumes have been achieved inpart due to the much higher than planned productivity of the Hitachi Zaxis 850excavators and the fleet of Belaz trucks, as well as the contribution of theequipment trainers from Altas Copco in Sweden and a Mine Training Consultantfrom Perth, Australia, in enhancing the already high skill level of the localemployees. Foundations for the mill building and major equipment (ball mills, leach tanks,crushers) are essentially complete. Indeed, concrete pouring at Sekisovskoye hasstretched the capabilities of the local concrete suppliers in Ust Kamenogorsk.The first of the two 1.2 megawatt ball mills is on track for shipment in earlyDecember as is a modular boiler house, with installation to commence immediatelyupon receipt. The second large ball mill is expected to be shipped in January.Site construction activities are continuing on a 24-hour, 7-day basis. Construction of the 110 kilovolt substation and 4.5 km overland powerline isahead of schedule and will be completed as soon as the main transformer isdelivered. Excavation of the starter tailings dam is nearing completion and wallconstruction is well advanced. Installation of the geomembrane is to becompleted in the spring of 2007 immediately prior to commissioning. Exploration activities are also continuing as per our commitments toshareholders. The Diamec drill rig that was purchased for underground drillinghas been converted to a winterized surface unit, with drilling initiated in lateOctober in the Tserkovka licence area. Overall, the mine preparation is ahead of schedule and the Directors are verypleased with the progress made to date. Note to editors Hambledon Mining plc is an AIM-listed mining and exploration company which isdeveloping an open pit mine and constructing an 850,000 tonnes per yeartreatment plant at its Sekisovskoye gold deposit in East Kazakhstan. After thestart of open pit processing, the Company plans to develop the much largerunderground resources. Production from the open pit will average over 40,000 ounces per annum for fiveyears, though this is expected to rise to around 100,000 ounces when the highergrade underground ore is added to the feed. The Company also holds the rights toand is exploring the adjacent Tserkovka licence territory which includes severalareas of interest including the Tserkovka deposit itself. Enquiries Hambledon Mining plcNicholas Bridgen, Chief Executive Telephone +7 701 733 8915 Bankside ConsultantsMichael Spriggs / Michael Padley Telephone +44 207 367 8888 This information is provided by RNS The company news service from the London Stock Exchange
Date   Source Headline
10th Jan 20117:00 amBUSProduction Update
15th Dec 20105:57 pmBUSHolding(s) in Company
13th Dec 201012:37 pmBUSHolding(s) in Company
10th Dec 201012:46 pmBUSHolding(s) in Company
10th Dec 201012:24 pmBUSHolding(s) in Company
1st Dec 20102:17 pmBUSHolding(s) in Company - Replacement
10th Nov 201012:33 pmBUSHolding(s) in Company
8th Nov 20105:39 pmBUSIssue of options
5th Nov 201012:11 pmBUSDirector/PDMR Shareholding
2nd Nov 20109:29 amBUSDirectorate Change
13th Oct 20101:06 pmBUSHolding(s) in Company
13th Oct 201011:47 amBUSHolding(s) in Company
12th Oct 20108:30 amBUSProduction Update
5th Oct 201012:38 pmBUSHolding(s) in Company
22nd Sep 20109:00 amBUSHolding(s) in Company
21st Sep 20107:00 amBUSHalf-yearly Report
17th Sep 20107:10 amBUSDirectorate Change
9th Aug 201012:29 pmBUSHolding(s) in Company
8th Jul 20107:00 amBUSProduction Update
6th Jul 201012:29 pmBUSHolding(s) in Company
23rd Jun 201012:11 pmBUSResult of AGM
23rd Jun 20107:43 amBUSAGM Statement
25th May 20101:03 pmBUSNotice of AGM
19th May 20107:00 amBUSPurchase of Ore
12th May 20107:00 amBUSFinal Results
7th May 201012:11 pmBUSHolding(s) in Company
14th Apr 20108:07 amBUSProduction Update
29th Mar 20104:35 pmRNSHolding(s) in Company
9th Mar 20107:00 amBUSHolding(s) in Company
11th Feb 201011:13 amBUSUpdate
14th Jan 20107:30 amBUSProduction Update
12th Jan 201011:41 amBUSHolding(s) in Company
23rd Dec 20094:14 pmRNSDirector/PDMR Shareholding
14th Dec 200912:45 pmBUSDirector/PDMR Shareholding
9th Oct 20098:11 amBUSProduction Update
30th Sep 20095:26 pmBUSHolding(s) in Company
23rd Sep 20097:00 amBUSIssue of Equity
18th Sep 20095:35 pmBUSHolding(s) in Company
17th Sep 20097:00 amBUSHalf-yearly Report
10th Sep 20094:06 pmBUSHolding(s) in Company
20th Jul 200910:38 amBUSAGM Statement
14th Jul 200910:15 amBUSProduction Update
9th Jul 200911:50 amRNSHolding(s) in Company
19th Jun 200912:30 pmBUSAnnual Financial Report
9th Jun 20097:00 amBUSFinal Results
9th Jun 20097:00 amBUSProduction Update
15th Apr 20099:23 amBUSProduction Update
11th Mar 200911:49 amBUSDirector/PDMR Shareholding
11th Mar 20097:00 amBUSMine Equipment Update
23rd Feb 20093:58 pmBUSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.