Production update

11 Oct 2012 07:00

Hambledon Mining Plc

("Hambledon" or "the Company")

Activities Report for the Quarter Ended 30 September 2012

Hambledon Mining plc (AIM: HMB), the Kazakhstan gold mining and development company, provides its operational report for the three months from 1 July to 30 September 2012. A copy of this report will be available on the Company's website, www.hambledon-mining.com

Production figures for the three months from 1 July - 30 September 2012:

July August September Total
Milled tonnes (dry) 49,992 61,054 56,196 167,242
Gold grade (g/t) 1.41 1.16 1.51 1.35
Contained gold (gms) 70,488 70,822 84,855 226,165
Contained gold (oz) 2,266 2,276 2,728 7,270
Gold recovery % 80.0 81.5 81.0 80.80
Recovered gold (oz) 1,812 1,854 2,209 5,875
Recovered silver (oz) 2.082 2,768 2,619 7,469

MINING AND PROCESSING OPERATIONS

During the quarter ended 30 September 2012, open pit mining operations extracted 185,300 tonnes of ore averaging 1.2g/t Au.

The metallurgical plant processed 167,242 tonnes of open pit and underground material and produced a total of 5,875 ounces of gold and 7,469 ounces of silver; with plant recovery averaging 80.8%. Plant throughput was constrained by reduced tailings dam capacity which will improve in Q4 with the reinstatement of Tailings Dam No. 3.

UNDERGROUND

Trial mining from the underground delivered 15,125 tonnes of ore averaging 3.32g/t Au. Some of this ore has already been processed and the remainder will be processed in Q4.

During the past quarter a strategic review of the underground operations was completed which led to a decision to temporarily suspend underground operations. The contractor is currently completing mining of accessible ore zones and will demobilise from site in late October 2012 at which point capital expenditure on the underground mine will temporarily cease.

UNDERGROUND DRILLING

As part of the strategic review of the underground operation, Hambledon's 25,000m diamond drill programme will continue. To date, some 17,500 metres has been drilled. The next set of drill results will be announced shortly.

INFRASTRUCTURE

The repair to Tailings Dam No. 3 is complete. The dam is expected to be commissioned in November 2012 after receipt of government permits.

Enquiries;

HAMBLEDON MINING:

Telephone +44 (0)207 233 1462

Charles Zorab

FAIRFAX I.S. PLC (NOMAD AND BROKER):

Telephone +44 (0)207 598 5368

Ewan Leggat/Katy Birkin

TAVISTOCK COMMUNICATIONS:

Telephone +44 (0)207 920 3150

Ed Portman/Jos Simson

Copyright Business Wire 2012

Date   Source Headline
12th Aug 20217:00 amBUSInternational Credit Rating for AltynGold
19th Jul 20217:00 amBUS2nd quarter results
30th Jun 20214:40 pmRNSSecond Price Monitoring Extn
30th Jun 20214:35 pmRNSPrice Monitoring Extension
25th Jun 20215:53 pmBUSAGM Statement
15th Jun 20215:11 pmBUSNotice of AGM
17th May 20217:00 amBUSInitiation Research by Renaissance Capital
11th May 20217:00 amBUS1st Quarter Results
30th Apr 20216:21 pmBUSFinal Results
15th Mar 20217:00 amBUSRenaissance Capital appointment
10th Mar 20217:00 amBUSUnderground mine development update
1st Mar 20217:00 amBUSFirst processing results from Terensai exploration area
1st Feb 20217:00 amBUSAltynGold Plc Quarter Four 2020 production update
9th Dec 20207:00 amBUSChange of Name
8th Dec 20207:00 amBUSThird quarter productions results and financial update
20th Nov 202011:50 amBUSCapital Reorganisation
22nd Oct 20203:04 pmBUSStandard form for notification of major holdings
20th Oct 20207:00 amBUSShare consolidation and change of name
13th Oct 20207:00 amBUSExpansion of the Tailing Storage Facility at Sekisovskoye Gold Processing Plant
7th Oct 20207:00 amBUSInfrastructure development of the Sekisovskoye underground mine
6th Oct 20205:00 pmBUSIssue of Equity
30th Sep 20206:25 pmBUSHalf-year Report
10th Aug 20204:41 pmRNSSecond Price Monitoring Extn
10th Aug 20204:36 pmRNSPrice Monitoring Extension
10th Aug 202011:35 amBUSAltyn's production update 2Q 2020
23rd Jul 20204:40 pmRNSSecond Price Monitoring Extn
23rd Jul 20204:35 pmRNSPrice Monitoring Extension
21st Jul 20204:40 pmRNSSecond Price Monitoring Extn
21st Jul 20204:36 pmRNSPrice Monitoring Extension
20th Jul 20209:18 amBUSSubsoil use contract extended until 2030
15th Jul 20204:41 pmRNSSecond Price Monitoring Extn
15th Jul 20204:35 pmRNSPrice Monitoring Extension
13th Jul 20204:36 pmRNSPrice Monitoring Extension
30th Jun 20207:00 amBUSAIX Bond placement complete
26th Jun 20204:41 pmRNSSecond Price Monitoring Extn
26th Jun 20204:36 pmRNSPrice Monitoring Extension
26th Jun 20201:36 pmBUSAGM Statement
15th Jun 20207:00 amBUSSocial responsibility update
9th Jun 20207:00 amBUSProduction and financing update
29th May 20205:00 pmBUSAnnual General Meeting (AGM) - 2020
26th May 20207:00 amBUSDrilling rig delivery
22nd May 20205:00 pmBUSIssue of New Shares
18th May 20207:00 amBUSAltyn Plc: Extension to subsoil mining contract at Sekisovskoye
11th May 20207:00 amBUSQ1 production results
1st May 20207:00 amBUSAnnual Financial Report
16th Apr 20204:41 pmRNSSecond Price Monitoring Extn
16th Apr 20204:36 pmRNSPrice Monitoring Extension
16th Mar 20207:00 amBUSAltyn Plc - Production update
28th Feb 20206:11 pmBUSStandard form for notification of major holdings
11th Dec 201911:02 amBUSBond Issue

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.