Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAltyngold Regulatory News (ALTN)

Share Price Information for Altyngold (ALTN)

Share Price is delayed by 15 minutes
Get Live Data
1,100.00    95.00 (9.45%)
Bid:
1,105.00
Ask:
1,055.00
Spread: -50.00 (-4.525%)
Market Cap: £300.66m
ALTN Live PriceLast checked at - London Stock Exchange

Intraday Altyngold Share Chart

Production Update

14 Jan 2010 07:30

Hambledon Mining plc("the Company")

PRODUCTION UPDATE

The Company reports its production for the three months from 1 October 2009 to 31 December 2009.

October November December Total
Milled tonnes (dry) 75,596 70,352 55,246 201,194
Gold grade (g/t) 1.01 1.02 1.13 1.05
Contained gold (gms) 76,352 71,759 62,152 210,263
Contained gold (oz) 2,455 2,307 1,998 6,760
Gold recovery % 79.0% 80.3% 80.98% 80%
Recovered gold (oz) 1,940 1,851 1,618 5,409
Recovered silver (oz) 4,194 4,538 4,746 13,478

Operation of the process plant ran very smoothly in October and November. Lower tonnages were processed in December due to mill relines and a major rebuild of the crushing facility, resulting in 5 days milling lost. Extreme (-45C) weather conditions in the second week of December also impacted the production for December. Currently, temperatures are even lower, which will have an impact on January figures.

The new mobile crushing facility has arrived in Ust Kamenogorsk, having been long delayed by customs. It is expected to be commissioned in early February. This machine will initially be used to re-crush frozen ore that has caused blockages in the circuit and low milling rates during the winter period. It will also be able to act as a back-up unit for the main jaw crusher, albeit with reduced capacity. During the summer period when the re-crushing of frozen ore is not required, it will be used to produce aggregates for own use or sale.

An engine failure on one of our two Hitachi excavators in October put the machine out of operation for seven weeks resulting in lower mining rates than planned and requiring low grade stockpiled ore to be blended with the higher grade ore mined during the quarter. This resulted in the overall grade of ore being processed being 1.05 g/t instead of the 1.27 g/t planned.

Negotiations for a renewal of the Alpha Bank stand-by loan facility of $2m. have been concluded and agreed.

UNDERGROUND DEVELOPMENT

Approval for the first phase of the underground development was received in late December. A contract with a local underground contractor was signed at the end of December to commence work on the development of the underground project. This work is expected to commence in mid January.

A tender process for supply of underground equipment has been completed. It is expected that orders will be placed for this equipment in the first quarter of 2010 which would result in delivery of equipment in time to allow commencement of stoping operations in late 2010.

Surface infrastructure construction for the underground operation started in the December quarter with a road being constructed to the portal site, surface sedimentation ponds being constructed and power lines and surface transformers being installed.

Enquiries:

Hambledon Mining:Telephone +44 (0)20 7233 1462Charles Zorab

Fairfax I.S. PLC:Telephone +44 (0)207 598 5368Nominated Adviser and BrokerEwan Leggat

Copyright Business Wire 2010

Date   Source Headline
12th Feb 20267:00 amBUSBoard changes
22nd Jan 20267:00 amBUSQ4 and FY 2025 Production and Operational Update
27th Oct 20257:00 amBUS3rd Quarter Results
27th Oct 20257:00 amBUSInvestor presentation
25th Sep 20257:01 amBUSDirectorate change
25th Sep 20257:00 amBUSHalf-year Report
18th Jul 20257:00 amBUSH1 2025 operational update
20th Jun 20255:28 pmBUSAGM Statement
10th Jun 20257:00 amBUSAGM Statement
30th May 20257:00 amBUSStatement re media comment
12th May 20257:00 amBUS1st Quarter Results
25th Apr 20258:06 amBUSLaunch New Website
25th Apr 20257:00 amBUSAnnual Financial Report
27th Jan 20257:00 amBUSQ4 production results
11th Nov 20247:00 amBUS3rd Quarter Results
30th Sep 20247:00 amBUSHalf-year Report
15th Jul 20247:00 amBUS6 months production update
3rd Jul 20247:00 amBUSStrategy/Company/Operations Update
1st Jul 20247:00 amBUSAIX Bond Programme
24th Jun 202412:18 pmBUSAGM Statement
24th Oct 20237:00 amBUS3rd Quarter Results
29th Sep 20237:00 amBUSHalf-year Report
23rd Jun 202312:14 pmBUSAGM Statement
19th Jun 20237:00 amBUS1st Quarter Results
9th May 20238:12 amBUSStatement re. Suspension
9th May 20237:30 amRNSRestoration - ALTYNGOLD PLC
5th May 20231:19 pmBUSAnnual Financial Report
2nd May 20237:30 amRNSSuspension - ALTYNGOLD PLC
28th Apr 20237:00 amBUSStatement re. Suspension
4th Apr 20233:42 pmBUSIssue of Bonds on AIX
15th Mar 20237:00 amBUSFourth quarter revenue and production update
19th Jan 20232:32 pmBUSAppointment of auditors
13th Dec 202210:56 amBUSRepayment of US$10m bonds
5th Dec 20227:00 amBUSFinancing update
10th Nov 20227:00 amBUS3rd Quarter Results
26th Sep 20227:00 amBUSHalf-year Report
1st Aug 20227:00 amBUS2nd Quarter Results
25th Jul 20224:41 pmRNSSecond Price Monitoring Extn
25th Jul 20224:35 pmRNSPrice Monitoring Extension
25th Jul 20227:00 amBUSFunding updtate
4th Jul 202212:28 pmBUSAGM Statement
27th Jun 20227:00 amBUSFinal Results
16th May 20227:00 amBUS1st Quarter Results
31st Jan 20227:00 amBUS4th Quarter results
24th Jan 202210:21 amBUSDirectorate change
10th Jan 20221:58 pmBUSStatement regarding situation in Kazakhstan
24th Dec 202112:41 pmRNSSecond Price Monitoring Extn
24th Dec 202112:36 pmRNSPrice Monitoring Extension
12th Oct 20217:00 amBUS3rd Quarter Results
15th Sep 202111:05 amBUSCorporate presentation invite

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.