RE: graphs10 Nov 2021 09:53
James, your 9:04 post - fully agree with it.
EchDelta, they cannot delay equipment to save cost. It doesn’t work that way.
BV, you cannot have all the equipment arriving at site at the same time - is unworkable.
If we are going to see any gas next Feb/Mar we MUST see equipment arriving at site NOW.
It takes time to install, pre-commission equipment (individually) then cold commission as a process, then hot commission with gas flowing. It takers time. If we don’t see equipment at site in November, then the chances of first gas by mid-March are very slim.
As I posted earlier, if we don’t see equipment at site this week then we should start making noise on Angus door.