The Company has also commenced above-ground engineering studies and, following a detailed review of several companies, has now selected one to produce a preliminary design for a production system that will be suited to the flow rates and gas composition within the Rukwa Basin.
This study has commenced with several processing facility options already being reviewed. These will include a smaller, lower rate pilot plant that would allow for early production as well as larger, modular systems that can be scaled-up. The design work will include helium liquefaction, storage and transportation with the aim of providing a well head to off-taker processing system. This would enable the Company to streamline all downstream and mid-stream activities.