RE: Planning Application24 Feb 2020 19:51
8.1 PERMISSION is recommended subject to the following conditions
1. Three years for commencement of development
2. Development carried out in accordance with the approved plans
3. Implementation of the Surface Water Management Plan 2018 Update, WSP,
December 2018 and associated drawings and calculations.
4. Flood Risk mitigation measures for finished floor levels and access road, parking
areas, pedestrian areas.
5. Decommissioning and reinstatement of the land
6. Construction Traffic Management Plant
7. HGV movements
8. Construction and implementation of the access road prior to operation of the facility
9. Use of the access road to the site for the operation of the facility with the access on
the west boundary of the site for emergency use
10.Provision of traffic counter loops, capable of recording the number of HGVs.
11.Travel Plan, Travel Plan co-ordinator and Freight Management Plan
12.Mitigation as set out in the Tree Survey and Arboricultural Impact Assessment.
13.Landscaping plan
14.Construction noise
15.Construction hours
16.Operational noise emissions
17.Air quality monitoring
18.Compliance and Certification of BREEAM rating ‘Very Good’
19.Provision of BREEAM Completion Certification within twelve months of completion
of development.
20.Prior to commencement an Assessment of Potential risk of contamination
21.If possible contamination discovered on site during works
22.Remediation works completed prior to occupation
23.Construction Environment Management Plan
24.Reasonable Avoidance Measures (RAMs) in respect to GCN
25.Tree removal with low bat roost potential felled in accordance with RAMs
26.Detailed lighting plan to demonstrate how habitats would not be disturbed.
27.Large mammal survey to be submitted
28.Detailed mitigation strategy for water voles
29. A 10 year woodland habitat management plan
30.Material / details of external surfaces of buildings and external plant.
page 71
Informative:
1. No site clearance shall be carried out during bird breeding season (1st March to 31st
August inclusive).