Excellent news out30 Aug 2016 08:18
The Environmental Impact Study for the development and construction of, and the mining permit for the Project have now been approved and issued respectively by the Provincial Mining Authority. This is a significant milestone in terms of the continuing development and construction of the Project. Initial earthworks commenced at the Project in April 2016 and all equipment and plant supplies for the Project have now been purchased. Construction is also advancing as planned with initial production expected to commence during September 2016. A total of US$13 million will be invested in the project to take it into production including cap