RE: Webinar10 Nov 2021 14:53
Very nice Webinar put together by Touchstone. As you know and EIA is required in order to apply for a CEC for the 200MMscf/day gas, 5,000bbl/day condensate and 8,800 bbl storage facility to be sited at Cascadura A. Phase one is Cascadura A which is expected to produce 70-80 MMscf/day plus 1,500-2,000 bbl/day condensate. Start-up for this phase was given as 2022 (no quarter was given but obviously Q4). Cascadura B and C is designed to allow increased production to the facility limit of 200 MMscf/day gas and 5,000 bbl/day condensate. Timeframe given was 2024 (no quarter). They also have to build a 5m wide x 7km long road from Saunders Trace to site. Also an 8.3km. x 6” diameter condensate line from Cascadura to Heritage’s condensate manifold at Saunders trace. NGC to construct a 20” diameter pipeline from Casc A to the 30” transnational pipeline. All for now - still ongoing. Waiting to see expected cost of these projects.